Change Order Form
5/24/23
Signal Hill PD Target System Upgrade
Project #23-12
Customer PO# 2300200
Change Order #1
Additional work – Installation of electrical conduit and 120v service to target system master control cabinet.
Install Master Control Cabinet Inside Range Area Near Control Room. Run 1-Inch Conduit In Left Upper Corner
Of Range To Target Area. Install 4"X4" Deep Junction Box On Ceiling Left Side At Target Area. Install Pull String In Conduit For Data Cables. Run Dedicated Circuit From Control Room Subpanel To Master Control Cabinet. Land Wiring On Control Board. Install 3/4-Inch Conduit From Master Control Cabinet To Master Control
Screen In Control Room. Install Pull String In Conduit For Data Cables. Install 3/4-Inch Conduit From Control Cabinet To Provide Wireless Box.
Total Cost for CO #1 $5,807.00
Original PO value $45,746.00
New Total $51,553.00