CONTRACT AMENDMENT REGISTER
August 8, 2023
Contract No.
Dept.
Service
Vendor
RFP (Y/N) & Council Approval Date
Cooperative Purchasing (Y/N) & Source
Current Term and Expiration Date
Current Not-to-Exceed
Amendment / Change Order
No.
Additional Term and Date
Additional Comp & CPI
New Not-to-Exceed
Funding Source Account No.
Adopted Budget
TERM AND COMPENSATION
1 PW
Project Management Services – Well 10 Project
Desi Alvarez, dba MCM Management Co.
Y
1/20/2015
N
7/30/2023
$425,000
3 4 months
11/30/2023
$16,000
$441,000
500-40-5840
Yes
COMPENSATION ONLY
2 PW
Professional Consultant Services – Interim Water Superintendent Project Partners, Inc.
Y
1/10/2023
N
12/27/2023
$100,000
2 N/A
$101,600
$201,600
500-40-5423
Yes
TERM ONLY
3 PW
Water Engineering Services
AKM Consulting Engineers
Y
7/11/2017
N
7/11/2023
$600,000
4 1 year
7/11/2024
N/A
N/A
500-40-5423
Yes
CHANGE ORDERS
None
N/A: Not applicable