City of Simi Valley
Staff Report
March 23, 2026
To: City Council
From: Public Works Department
Ron Fuchiwaki, Public Works Director
Subject: Approve the Sim i Valley Traffic Signal Conditions Assessment Report, establish a new Capital Improvement Project for traffic signal upgrades , approve a Supplemental Budget Request, and amend contracts with Econolite Staff Recommendation
It is recommended that the City Council:

1. Approve the City of Simi Valley Traffic Signal Conditions Assessment report (Attachments A and B);

2. Establish a new Capital Improvement Project (CIP) to complete the Phase 0 (Attachment C) recommendations of the Traffic Signal Conditions Assessment report;

3. Approve a Supplemental Budget Request in the amount of $ 250,000 from the General Fund and authorize an interfund transfer to the new CIP project;

4. Amend the contract with Econolite Control Products, Inc. (Attachment D) to extend the contract for one year, until October 6, 2027 , and increase the not-to-exceed budget by $175,000 for a total contract not to exceed amount of $375,000;

5. Amend the contract with Econolite Services, Inc. (Attachment E) to increase the not-to-exceed amount by $75,000, for a total contract not -to-exceed amount of $1,200,000.

Background
The City owns and maintains 121 traffic signal s. In response to the City’s traffic signal infrastructure increasingly malfunctioning or operating in "flashing red" conditions , staff retained Kimely-Horn and Associates, Inc. (Consultant) to conduct a traffic signal conditions assessment to review, inspect, and create a list of prioritized repairs and/or upgrades to improve traffic signal operations. Recommendations were categorized by Phase, and upon City Council approval, a project will be established to accomplish the goals of Phase 0 to modernize equipment by replaci ng old traffic signal controllers. The City would purchase the equipment directly, and the controller s would then be programmed and installed by our current signal maintenance contractor.

Agenda Item No.
9A
Discussion
Th
e City’s traffic signal infrastructure has been increasingly malfunctioning or operating in "flashing red" conditions. While most flashing red operations last for only a few hours or less, others have remained in that condition for up to several weeks. The construction of traffic signals in the City has occurred over many decades. While each traffic signal was designed for the state of the practice at the time of construction, equipment age can lead to failures, which then defaults to flashing red operati on. Additionally, older equipment has become less resistant to fluctuations in electrical service and is prone to failure due to planned or unplanned outages, or P ublic Safety Power Shutoffs, as frequently occurs with Southern California Edison.

T
he City’s Consultant conducted an assessment of existing traffic signal equipment and prepared a cost estimate to repair and/or modernize that equipment. The following infrastructure was subject to assessment by the Consultant:
• T
raffic signal cabinets and equipment
• Traffic signal controllers
• Traffic signal poles and associated equipment
• In-ground utility boxes and underground equipment, including conduits and wiring • Video and loop detection equipment
• Emergency vehicle recognition and preemption equipment • Battery Backup Systems (BBS)
• Pedestrian and Equestrian Push Buttons
• Interconnection Systems
• Railroad equipment
F
ollowing the inspections, the Consultant prepared a comprehensive list of improvements and upgrades based on Phases. Phase 0 would be accomplished near -term, Phase 1 would be short to mid -term projects, and Phase 2 would be long- term or identified as more complex projects. If approved, this project would complete the Phase 0 improvements, which consist of replacing the City’s oldest and unrepairable (if they were to fail) traffic signal controllers. Should a traffic signal controller fail and no spare equipment is available, the traffic signal may operate in flashing red conditions for extended periods of time. While replacing the traffic signal controllers significantly improves reliability and repairability, it does not mean the traffic signal may not malfunction in the future. Phases 1 and 2 would replace wiring and other equipment that are the source of other malfunctions that cause abnormal operations.

D
evelopment of a separate capital project to complete Phases 1 and 2 is ongoing. Phases 1 and 2 are estimated to cost approximately $14,109,000 including contingencies for construction and engineering. It is anticipated that the project would be a multi-year effort over ten years to reduce the number of facilities simultaneously under construction and the impact on the general fund.

C
urrently, City Staff relies upon citizen reports when traffic signals are in red flash or malfunction. Existing traffic signal controllers are not network-ready, and do not interface 2 with centralized traffic signal management software. The equipment improvements recommended in this report will prepare the traffic signals to be network -ready. Upon implementation of a networked system, staff at City Hall will be notified of malfunctions as they arise, which will decrease delays in repairs and inconvenience to the community.

T
he intersections planned for Phase 0 improvements are listed in Attachment C. The list is modified as compared to the traffic signal conditions assessment: The traffic signal controllers along Madera Road at Country Club Drive West, Irvine Road/Shaver Court, Bonita Drive, and Strathearn Place would be upgraded as part of a comprehensive project. Madera Road is a coordinated facility that, under most conditions, provides a green signal as vehicles travel north and south along the corridor . This requires specialized equipment and communications between traffic signals, which would be replaced as part of this separate project . The controller at the intersection of First Street and Royal Avenue has been upgraded as part of the HSIP Cycle 11 Project.

T
o accomplish the Phase 0 improvements, s taff proposes to use existing contracts with both Econolite Control Products, Inc. (ECPI) for controller purchases and Econolite Services, Inc (ESI) for controller installation services. The City exclusively uses Econolite equipment to standardize maintenance, repairs, and communications with traffic signal equipment. In addition, purchas ing equipment directly from ECPI saves the City thousands of dollars in equipment markups . It is necessary to amend the contract wi th ECPI for both time and budgetary reasons to accomplish Phase 0.

C
onsistent with Simi Valley Municipal Code § 2-9.201(e), staff recommends dispensing with additional competitive bidding requirements for these purchases and services because the commodity and maintenance services can only be provided in a manner compatible with the City’s existing Econolite -based traffic signal system, and standardization of City equipment will result in cost savings to the City through reduced equipment mark-ups and streamlined maintenance and operations.

Sta
ff also desire s to amend the existing traffic signal maintenance contract with ESI.

Installation of new traffic signal controllers requires “reprogramming” the information in each controller to ensure compatibility with the existing traffic signal cabinet equipment.

ESI will perform the reprogramming in their facility and install the new traffic signal controller in the cabinet at each location. Existing equipment will be removed and recycled. Staff anticipates the work can be accomplished within three to four months.

Fin
ancial Impact
$25
0,000 for Phase 0 ($175,000 for equipment and $75,000 for installation). A Supplemental Budget Request in the amount of $250,000 from the General Fund is being requested as part of the City Council’s action.
3 City Council Priority
This item supports the Reliable Infrastructure Pillar of Excellence to maintain and upgrade roads, facilities, and technology systems to ensure safe, efficient, and resilient public services.

Suggested Motion
I move that the City Council:

1. Approve the City of Simi Valley Traffic Signal Conditions Assessment report;

2. Establish a new Capital Improvement Project to complete the Phase 0 recommendations of the Traffic Signal Conditions Assessment report;

3. Approve a Supplemental Budget Request in the amount of $250,000 from the General Fund and authorize an interfund transfer to the new CIP project;

4. Amend the contract with Econolite Control Products, Inc. to extend the contract for one year, until October 6, 2027, and increase the not -to-exceed budget by $175,000 for a total contract not to exceed amount of $375,000;

5. Amend the contract with Econolite Services, Inc. to increase the not -to-exceed amount by $75,000, for a total contract not-to-exceed amount of $1,200,000.

Summary
In response to the City’s traffic signal infrastructure increasingly malfunctioning or operating in "flashing red" conditions , the City retained a Consultant to conduct a traffic signal conditions assessment to review, inspect, and create a list of prioritized repairs or upgrades to improve traffic signal operations. Recommendations were categorized by Phase, and upon approval by the City Council a project will be established to accomplish the goals of Phase 0 to modernize equipment by replacing old t raffic signal controllers.

The City would purchase the equipment directly , and the City’s current signal maintenance contractor would then be program and install the equipment. It is recommended that the City Council a pprove the City of Simi Valley Traffic Signal Conditions Assessment report; establish a new capital improvement project to complete the Phase 0 recommendations of the Traffic Signal Conditions Assessment report; approve a supplemental budget request in the amount of $250,000 from the General Fund; amend the Contract with Econolite Control Products, Inc. to extend the contract and increase the not to exceed budget by $175,000 for a total contrac t not to exceed amount of $375,000; and amend the contract with Econolite Services, Inc. to increase the not to exceed amount by $75,000, for a total contract not to exceed amount of $1,200,000.

Prepared by: Justin Link, Principal Engineer
4 Attachments:

A
ttachment A – Traffic Signal Conditions Assessment Executive Summary Attachment B – Traffic Signal Conditions Assessment Technical Memo and Recommendations
Attachment C – Intersections for Phase 0 Improvements
Attachment D – Contract Amendment Econolite Control Products, Inc.

Attachment E – Contract Amendment Econolite Services, Inc. 5 i

EXECUTIVE SUMMARY

CITY OF SIMI VALLEY TRAFFIC SIGNAL CONDITIONS ASSESSMENT The City of Simi Valley, located in Ventura County, California, with a population of approximately 126,000 residents, owns and operates a total of 121 traffic signals. In Spring 2025, Kimley-Horn performed a comprehensive field inventory and condition assessment of these traffic signals to support the City in maintaining a reliable and efficient traffic signal system. This assessment evaluated the existing infrastructure and identified necessary upgrades to enhance traffic safety, signal performance, and the effective utilization of City resources.

Existing Conditions
The assessment involved detailed documentation for each intersection's equipment and hardware.

Key data collected included:
· Cabinet type, location, and key type
· Traffic signal controller type and condition
· Presence of emergency vehicle and railroad preemption systems · Interconnect and communication infrastructure
· Detection equipment including video and loop detectors Photographs and documentation of each cabinet’s interior were taken for detailed review.

Additionally, the physical infrastructure, including signal heads, pedestrian pushbuttons, and detection equipment, was reviewed and documented.

The evaluations focused on the following components:
· Signal controllers: Assessed for type and state of operation for potential replacement needs. · Battery backup systems (BBS): Identified intersections without these critical systems to prioritize installation.
· Signal heads/poles: Inspected for damage or inefficiency, with recommendations for replacements.
· Pull boxes and wiring: Examined for integrity and operational reliability, recommending replacements where necessary.
· Pedestrian push buttons: Checked for presence and functionality, with specific replacements or additions noted.
· Countdown pedestrian signal heads: Recommended for intersections to enhance safety for pedestrian crossing.

Attachment A
6 ii
Recommendations
Recommendations were developed upon completion of detailed field review. The recommendations were classified into three phases based on immediacy and priority:

Phase 0 – Immediate Implementation
Controller Replacement:
· 25 intersections identified for immediate controller upgrades to Econolite Cobalt controllers due to screen/button issues and overall age.

Phase 1 – Short/Mid-Term Projects
These include a mix of controller replacements, battery backup system installations, signal head and pull box replacements, cable wiring installations, push button upgrades, and countdown pedestrian head installations.
· Controller upgrades at 41 moderate-priority and 19 low-priority intersections. · Installation of battery backup systems at 106 intersections lacking such systems for enhanced reliability during power outages.
· Replacement of traffic signal heads and pull boxes found with minor damages or cracks at 15 and 76 intersections, respectively.
· Cable wiring updates at 65 intersections to improve durability and simplify maintenance. · Push button replacement/modifications at three (3) locations. · Installation of countdown pedestrian heads at 41 intersections to enhance pedestrian safety.

Phase 2 – Long-Term Projects
These projects are suggested for long-term planning and depend on future funding availability. They focus on improvements that do not immediately impact operations but will benefit the infrastructure longevity, including:
· Video detection installations or replacements at 58 intersections, prioritizing those currently lacking such technology.
· Conduit replacements at 112 intersections showing wear and degradation. · Pole replacements at 10 intersections where significant physical damage was observed.

Cost Estimate and Intersection Overview
Table 1 outlines unit cost assumptions that were used for the planning level cost estimate for the recommended improvements (Phases 0-2). The source of these costs are based on available recent construction bid results of similar projects, to reflect current market pricing as of October 2025. 7 iii
Table 1: Planning Level Cost Estimate
Additionally, a qualitative overview was completed to understand the state of the overall traffic signal system. This was accomplished by identifying the types of critical improvements out of the recommended improvements and then categorizing each intersection based on the number of critical improvements needed.

The categories of recommended improvements, withcritical improvements highlighted in bold, are as follows:
o Controllers
o Battery Back-up Systems (BBS)
o Signal Heads
o Pull Boxes
o Wiring
o Push Buttons
o Countdown Pedestrian Head
o Video Detection
o Conduit
o Poles
Each intersection was then placed into one of the following groups based on the number of critical improvements needed:
o Require Immediate Attention
o Serviceable
o In Good Condition
Table 2 presents the qualitative overview.
8 iv
Table 2: City Intersections Qualitative Overview
Intersection Condition # of Intersections
Require Immediate Attention
4+ Critical Categories 40 (33%)
Serviceable
2-3 Critical Categories 73 (60%)
In Good Condition
0-1 Critical Category 8 (7%)
As illustrated in Table 2, 33% require immediate attention, 60% are serviceable, and 7% of the City’s intersections are in good condition based on the current assessment.

Next Steps
This traffic signal inventory provides a comprehensive assessment and phased recommendations for the City’s traffic signal infrastructure, emphasizing immediate, short/mid-term, and long-term improvements. It is recommended that the City update this inventory periodically to incorporate progress and reassess priorities.
9 City of Simi Valley
Traffic Signal
Conditions
Assessment
Prepared for:

October 3, 2025
Prepared by:

Attachment B
10 1
City of Simi Valley Traffic Signal Conditions Assessment

TECHNICAL MEMORANDUM
To: Justin Link, P .E., T.E., Principal Engineer / City Traffic Engineer, City of Simi Valley Anthony Gallo, P .E., Senior Engineer, City of Simi Valley From: Sri Chakravarty, P .E., T.E.

Charis Ahn, P .E.

Ramsay Goyal, CNU-A, AICP Candidate
Kimley-Horn and Associates, Inc.

Date: October 3, 2025
Subject: City of Simi Valley Traffic Signal Conditions Assessment

1. INTRODUCTION
The City of Simi Valley is located in Ventura County, California, and has a population of approximately 126,000 residents. The City operates and maintains 121 traffic signals, a map of which is included as Figure 1. In Spring 2025, Kimley-Horn staff conducted a comprehensive field inventory and evaluation of existing traffic signal equipment and conditions at all 121 City-operated intersections. The fieldwork forms the basis for extensive documentation of the City’s traffic signal infrastructure, allowing staff to evaluate the current equipment condition to support informed decision-making for future maintenance and upgrades. With field verification and infrastructure documentation, the project aims to assist the City in maintaining a reliable and efficient traffic signal system, ensuring traffic safety, optimizing signal performance, and maximizing the impact of city resources, future investment, and planning efforts.

Figure 1: Traffic Signal Intersections in the City of Simi Valley 11 2
City of Simi Valley Traffic Signal Conditions Assessment

2. EXISTING CONDITIONS
The existing conditions of the 121 intersections throughout the City of Simi Valley were surveyed in Spring 2025. Existing conditions summary sheets and intersection timing sheets are viewable for each intersection at this online web map and also included in Appendix B (Traffic Signal Equipment) and Appendix C (Timing Sheets) of this memo by intersection. The following section details the information collected at each surveyed intersection.

2.1 Inside Cabinet
At each intersection, the field review teams documented the status of equipment and hardware inside each intersection cabinet.

The following data was collected for each of the 121 intersections:
` Cabinet type
` Cabinet location
` Cabinet key type
` Traffic signal contr
oller
` Presence of switch
` Malfunction monitor/port type
` Power supply type
` Presence of emergency
vehicle pr
eemption
` Presence of railr
oad preemption
` Presence of Bus
Interface Unit (BIU)
` Presence of inter
connect and fiber
optic communication infrastructure
` Presence of video or loop
detection equipment
` Timing plans (photographed or
downloaded fr
om controller)
Photographs of each cabinet interior, including close-up photographs of each intersection’s controller, switch, malfunction monitor/port, power supply, emergency vehicle preemption equipment, detector rack, video or loop detection hardware, and communication hardware are included on the inventory sheets for each of the City’s 121 intersections (which are also available on the online GIS web map linked above).

2.2 Intersection Review
The intersection infrastructure on all corners, legs, and approaches was documented. The following data was collected for each of the 121 intersections:
` Battery backup type
` Service type and location
` Pole type
` Signal mast arm length
` Number of signal heads
` Number of
pedestrian signal heads
` Presence of luminair
e and wattage
` Presence of pedestrian
pushbutton and functionality;
` Number, type, and description of
signal-mounted signs
` Presence of video detection
equipment, manufactur
er, and
mounting location
12 3
City of Simi Valley Traffic Signal Conditions Assessment

3. RECOMMENDATIONS
Based on the condition of existing intersection infrastructure, recommendations were categorized into three (3) phases:

An intersection-by-intersection breakdown of project prioritization is included in Appendix A.

3.1 Phase 0 – Immediate Implementation
Controller Replacement
Phase 0 projects are recommended for immediate implementation. City staff informed that there are 25 new Econolite Cobalt controllers available and requested to identify intersections for controller upgrades. Intersections with existing ASC/2-2100, ASC/2S-2100, or ASC-8000 controllers were deemed as high priority for replacement based on the age of the controller and associated wear and tear such as screen and button issues. Example location depicted in Figure 2 (right) at the intersection of Cochran/Liberty. Maintenance requests or changes to signal timing patterns at these intersections have been more difficult to implement as these controllers have a higher likelihood of experiencing issues. The controller upgrade at these 25 intersections is anticipated to immediately alleviate these issues. These intersection locations are included in Appendix A.

3.2 Phase 1 – Short/Mid-Term Projects
Phase 1 projects are recommended for short and mid-term implementation. Projects included as short and mid-term include controller replacement, battery back-up system installation, signal head replacement, pull boxes replacement, cable wiring installation, push button installation, and countdown pedestrian head installation as further described below. A list of specific intersections pertaining to each recommendation is included in Appendix A.

Controller Replacement
The replacement of older model controllers with Cobalt controllers in Phase 1 consists of 41 intersections with controllers deemed as moderate priority replacement and 19 intersections deemed as low priority replacement. Intersections identified as moderate priority replacement have older ASC/2S-2100 model controllers, although in better condition than the ASC/2S-2100 controllers identified for high priority replacement as part of Phase 0. Intersections identified as low priority replacement have ASC/3-2100 model controllers that are newer models, but less advanced than the Cobalt controllers. Figure 3 (right) illustrates an example of the Cobalt controller that all existing intersection controllers should be upgraded to.

Battery Backup System (BBS) Installation
A total of 106 intersections in the City lack battery backup systems (BBS) and are recommended for BBS installation as part of Phase 1 improvements. Installing battery backup systems at intersection cabinets enhances traffic signal reliability and safety. During power outages caused by severe weather, collisions, or infrastructure failures, these systems allow traffic signals to operate normally or in flashing operation for a few hours, reducing driver confusion and the risk of collisions. Battery backup systems allow traffic signals to maintain their programmed timing sequences uninterrupted, which is especially crucial at high-traffic intersections and near essential facilities like hospitals and schools. Figure 4 (right) depicts an example of a location with an existing BBS that all existing traffic signal cabinets should be upgraded to include.

Figure 2: Existing ASC/2-2100 controller
with faded screen (Cochran/Liberty)
Figure 3: Existing Cobalt controller
(Alamo/Atherwood)
Figure 4: Existing BBS
(Cochran/Erringer)
PHASE 0 PHASE 1 PHASE 2
Immediate Implementation Short/Mid-Term Projects Long-Term Projects 13 4
City of Simi Valley Traffic Signal Conditions Assessment Signal Head Replacement
There are 15 intersections with one or more traffic signal heads recommended for replacement due to minor damage or cracks.

Figure 5 (right) illustrates an example location with an existing dented traffic signal head.

Pull Box Replacement
Pull box replacement is identified for 76 intersections where the pull boxes were observed to be damaged or cracked.

Such damage can allow dirt, dust, water, or objects to intrude into the conduit area, potentially impacting the wiring of traffic signal infrastructure and hindering intersection operations. Figure 5 (right) illustrates an example location with an existing cracked pull box.

Cable Wiring Installation
65 intersections were identified to be re-wired with cables to replace the individual signal wires. Figure 6 (right) depicts example condition of pull box with existing #14 AWG wires. Installing cables instead of individual wires in conduits enhances durability and reliability for traffic signals by providing superior protection against environmental factors. This reduces the risk of signal malfunctions and ensures consistent operation. Additionally, cables simplify maintenance and upgrades. Their bundled structure makes it easier for technicians to handle and replace sections, reducing service time, minimizing traffic disruptions, and lowering maintenance costs.

Push Button Installation
Three (3) locations were identified for replacement or modification of a pedestrian push button. The traffic signal at Long Canyon east of Wood Ranch is missing an equestrian push button on one of its poles, despite having an equestrian push button on its other pole (Figure 7); the intersection of Tierra Rejada and Village has a damaged pedestrian push button on pole 5; and the intersection of Tapo Canyon and Cochran had 2 push buttons on pole 6, one of which is not needed.

Countdown Pedestrian Signal Head Installation
41 intersections were identified for the replacement of one or more existing pedestrian signal heads with countdown signal heads. Example location reflected in Figure 8.

Countdown pedestrian signal heads offer the benefit of providing pedestrians with clear, numerical indicators of the remaining time to cross, enhancing safety by reducing uncertainty. This visual countdown helps prevent pedestrians from starting to cross when the time remaining is insufficient, thereby improving overall traffic flow and reducing the likelihood of collisions. While 25 intersections have only one pedestrian signal head warranting replacement, 16 intersections have up to 8 pedestrians signal heads recommended for replacement with countdown equipment. Cumulatively, 90 pedestrian signal heads across the city do not currently feature full countdown functionality and are recommended for replacement.

Figure 5: Dented Signal Head and Cracked Pull Box (First/Agnew) Figure 6: Pull box with existing #14 AWG individual wires (Cochran/Sequoia)
Figure 7: Missing equestrian push button
(Long Canyon/Ped Xing E/O Wood Ranch)
Figure 8: Existing pedestrian head missing
countdown (Alamo/Erringer)
14 5
City of Simi Valley Traffic Signal Conditions Assessment

3.3 Phase 2 – Long-Term Projects
Long-term projects are suggested improvements that do not directly impact the operation of the intersection. While improvements would benefit the intersection’s infrastructure, for many of these projects, the city has yet to identify funding sources. As a result, these projects have unidentified future horizons and can be addressed when funding is available. Long-term recommended projects include video detection installation or replacement, conduit replacement, and pole replacement.

Video Detection Installation/Replacement
Video detection replacement or installation is identified for 58 intersections, including 27 deemed as moderate priority replacements and 31 deemed as high priority installations. High priority intersections do not currently have video detection equipment but would benefit from the reliability of this technology to ensure smooth intersection operations. Moderate priority intersections in this category already have video equipment, but this equipment could benefit from replacement to newer equipment (Figure 9).

Conduit/Pole Replacement
112 intersections are identified for conduit replacement, as conduit at the intersection is observed to be showing signs of wear and degradation. 10 intersections have been identified for pole replacement. Figure 10 (below) depicts an example location of a traffic signal pole dented with visible damage.

4. NEXT STEPS
This memorandum offers a comprehensive field inventory of the current traffic signal equipment conditions across Simi Valley and provides recommendations of traffic signal infrastructure improvements for immediate, short-term, mid-term, and long-term phases. It is recommended that this memorandum be periodically updated to incorporate progress made and to reassess goals and priorities in the coming years.

Figure 9: Existing video detection with
older Iteris equipment (Cochran/Stearns)
Figure 10: Existing traffic signal pole with visible
damage (Wood Ranch/Country Club)
15 Appendix A
Recommended List of Improvements Table
16  7
City of Simi Valley Traffic Signal Conditions Assessment

EXISTING
Recommendations
PHASE 0
Immediate Projects
PHASE 1
Short/Mid-Term Projects
PHASE 2
Long-Term Projects
Comments/Notes
Intersection No.

Intersection Location Controllers
Poles Controllers Controllers Battery Back-up
Systems Signal Heads Pull Boxes Wiring Push Buttons Countdown Pedestrian Head Video Detection Conduit Poles
As-built Year X (H) - High Priority
Replacement
X (M) - Moderate
Priority Replacement
X (L) - Low Priority
Replacement
X - BBS to be Installed
X (#) - Number of
Signal Heads to be
Replaced
X - PBs to be Replaced X - Cables to be
Installed
X (#) - Number of
Push Buttons to
be Replaced. See
Comments/Notes for
additional context.

X (#) - Number of Ped
Heads to be Installed
X (H) - High Priority
Installation
X (M) - Moderate
Priority Replacement
X - Conduit to be
Replaced
X (#) - Number of
Poles to be Replaced
1 Alamo/Erringer ASC/3-2100 2004 X (L) X X (2)
2 Alamo/Atherwood Cobalt 1991 X X X X (H) X
3 Alamo/Sycamore ASC/3-2100 1988 X (L) X X X X
4 Alamo/Galena ASC/3-2100 2008 X (L) X X X X (H) X
5 Alamo/Sequoia ASC/3-2100 1988 X (L) X X X X
6 Alamo/Lemon Cobalt 1997 X X X (1)
7 Alamo/Santa Lucia Veterans Plaza Cobalt 2003 X X X (H) X 8 Alamo/Michael Clark ASC/3-2100 2003 X (L) X X X (1) X 9 Alamo/Tapo Cobalt 1990 X X X (1) X (H) X
10 Alamo/Texas ASC/2S-2100 1994 X (M) X X (H) X
11 Alamo/Stearns/Indian Hills ASC/2S-2100 2005 X (M) X X 12 Cochran/Park Center ASC/2S-2100 1994 X (M) X X X (M) X Both Econolite & Iteris video detection present. 13 Cochran/Freedom Cobalt G-Series 1998 X X X X
14 Cochran/Liberty ASC/2-2100 1998 X (H) X X
15 Cochran/Callahan ASC/2S-2100 1991 X (H) X X X X (M) X 16 Cochran/Erringer ASC/2S-2100 2014 X (M) X X (M) X
17 Cochran/Justin Cobalt G-Series 1984 X X X X (M) X
18 Cochran/Sycamore ASC/2S-2100 1998 X (M) X (M) X
19 Cochran/Capitol ASC/3-2100 1988 X (L) X X X
20 Cochran/Colonial ASC/3-2100 1986 X (L) X X X
21 Cochran/Galena ASC/2S-2100 1990 X (M) X X X X (1)
22 Cochran/Sequoia Cobalt G-Series 1988 X X X X X (1)
23 Cochran/Parkdale ASC/2S-2100 1991 X (M) X X X X (1) X 24 Cochran/Tracy ASC/2-2100 1980 X (H) X X X X
25 Cochran/Winifred ASC/2S-2100 1999 X (H) X X (1) X (H) X 26 Cochran/Tapo Cobalt G-Series 2000 X X (2) X X (H) X
27 Cochran/Steams ASC/3-2100 No As-Built X (L) X X X X (2) X (M) X X (1) 28 Cochran/Stow ASC/2-2100 No As-Built X (H) X X X X (M) X 29 Cochran/Yosemite ASC/2S-2100 1985 X (M) X X X X (H) X 30 Erringer/Arcane ASC/3-2100 2007 X (L) X X X
31 Erringer/Arroyo Simi ASC/3-2100 2013 X (L) X X X
32 Erringer/Heywood ASC/2-2100 1987 X (H) X X (1) X X (M) X 33 Erringer/Patricia ASC/3-2100 1991 X (L) X X X X X (M) X Damaged ped head on pole 1. 34 Erringer/Larch ASC/2S-2100 1983 X (H) X X X X (1) X (M) X Both Econolite and Iteris video detection present. 35 Erringer/Falcon ASC/2S-2100 2003 X (M) X X X (4) X
36 Erringer/Legacy ASC/2S-2100 2003 X (M) X X (8) X
37 Erringer/Lost Canyons ASC/2S-2100 2003 X (M) X X (5) X 38 First/Mellow Lane ASC/2S-2100 No As-Built X (M) X X (1) X 8 equestrian push buttons also present. 39 First/Bennett ASC/2S-2100 2000 X (H) X X (1) X (1)
40 First/Fitzgerald ASC/2S-2100 2002 X (M) X X
17  8
City of Simi Valley Traffic Signal Conditions Assessment

EXISTING
Recommendations
PHASE 0
Immediate Projects
PHASE 1
Short/Mid-Term Projects
PHASE 2
Long-Term Projects
Comments/Notes
Intersection No.

Intersection Location Controllers
Poles Controllers Controllers Battery Back-up
Systems Signal Heads Pull Boxes Wiring Push Buttons Countdown Pedestrian Head Video Detection Conduit Poles
As-built Year X (H) - High Priority
Replacement
X (M) - Moderate
Priority Replacement
X (L) - Low Priority
Replacement
X - BBS to be Installed
X (#) - Number of
Signal Heads to be
Replaced
X - PBs to be Replaced X - Cables to be
Installed
X (#) - Number of
Push Buttons to
be Replaced. See
Comments/Notes for
additional context.

X (#) - Number of Ped
Heads to be Installed
X (H) - High Priority
Installation
X (M) - Moderate
Priority Replacement
X - Conduit to be
Replaced
X (#) - Number of
Poles to be Replaced
41 First/Arcane ASC/2S-2100 1987 X (M) X X
42 First/Royal ASC/2S-2100 1992 X (H) X X X (1) X
43 First/Easy ASC/2S-2100 1992 X (M) X X X X
44 First/Agnew ASC/3-2100 1988 X (L) X X (1) X X X (2) X 45 First/Cochran Cobalt 1992 X X
46 First/Simi Town Center ASC/2S-2100 No As-Built X (M) X X X (8) X 47 Kuehner/Smith ASC/2S-2100 1997 X (M) X X X X (H) X
48 Kuehner/Katherine ASC/2S-2100 1985 X (M) X X X (H) X X (1) 49 Kuehner/Sandalwood ASC/2-2100 1997 X (H) X X X X (1) X (H) X 50 Long Canyon E/O/Wood Ranch ASC/2S-2100 No As-Built X (M) X X X (1) X (1) X (H) X 1 equestrian push button present.

Missing equestrian PB on other pole.
51 Long Canyon/Canyon View/Vineyard Dr ASC/2S-2100 No As-Built X (M) X X (8) X 52 Long Canyon S/O/Bluegrass ASC/2-2100 No As-Built X (H) X X X (H) X 2 equestrian push buttons also present. 53 LA/Madera Cobalt G-Series 1997 X X X
54 LA/Simi Village-Socrates ASC/2S-2100 1996 X (M) X X X (M) X 55 LA/Sinaloa ASC/3-2100 1988 X (L) X X (1) X X X (1) X 56 LA/Fifth Cobalt G-Series 1996 X X (1) X X X (H) X
57 LA/First Cobalt G-Series 1998 X X (M) X
58 LA/Patricia ASC/2S-2100 1990 X (M) X X (1) X X X
59 LA/Executive ASC/2S-2100 1990 X (M) X X (1) X X (H) X 60 LA/Hubbard ASC/2S-2100 1990 X (M) X X (1) X X X (H) X 61 LA/Donville ASC/2S-2100 1990 X (H) X X (1) X X X (H) X 62 LA/Galt Cobalt 2000 X X (H) X
63 LA/Erringer Cobalt G-Series 1990 X X X
64 LA/Sycamore Cobalt 1989 X (M) X
65 LA/Church Cobalt G-Series 1996 X X X X
66 LA/Sequoia Cobalt 1988 X X (2) X
67 LA/Surveyor ASC/2S-2100 No As-Built X (M) X X X X (H) X 68 LA/Tapo Canyon Cobalt G-Series 1990 X X (2) X (H) X
69 LA/Tapo ASC/3-2100 1996 X (L) X X (M) X
70 LA/Hidden Ranch ASC/2S-2100 2002 X (M) X X X X (1)
71 LA/Stearns Cobalt 1987 X X X X (1) X
72 LA/Stow ASC/2S-2100 1987 X (H) X X (1) X X X
73 LA/Yosemite Cobalt G-Series 1994 X X (1) X X
74 LA/Rory Cobalt G-Series 1982 X X X X (1) X
75 LA/Anastasia-Christine ASC/2S-2100 1996 X (M) X X X X (M) X 76 Madera/Country Club W ASC/2S-2100 1990 X (H) X X X (M) X 77 Madera/Presidential ASC/2S-2100 2014 X (M) X X X
78 Madera/Wood Ranch Cobalt G-Series 1999 X X X X (1)
79 Madera/Sunset Garden ASC/2S-2100 No As-Built X (M) X X X (1) 80 Madera/Country Club E Cobalt G-Series 1990 X X X X X (1) 3 equestrian push buttons also present. 18  9
City of Simi Valley Traffic Signal Conditions Assessment

EXISTING
Recommendations
PHASE 0
Immediate Projects
PHASE 1
Short/Mid-Term Projects
PHASE 2
Long-Term Projects
Comments/Notes
Intersection No.

Intersection
Location Controllers
Poles Controllers Controllers Battery Back-up
Systems Signal Heads Pull Boxes Wiring Push Buttons Countdown Pedestrian Head Video Detection Conduit Poles
As-built Year X (H) - High Priority
Replacement
X (M) - Moderate
Priority Replacement
X (L) - Low Priority
Replacement
X - BBS to be Installed
X (#) - Number of
Signal Heads to be
Replaced
X - PBs to be Replaced X - Cables to be
Installed
X (#) - Number of
Push Buttons to
be Replaced. See
Comments/Notes for
additional context.

X (#) - Number of Ped
Heads to be Installed
X (H) - High Priority
Installation
X (M) - Moderate
Priority Replacement
X - Conduit to be
Replaced
X (#) - Number of
Poles to be Replaced
81 Madera/Irvine-Shaver ASC/2-2100 No As-Built X (H) X X (1) X 82 Madera/Vista Lago ASC/2S-2100 No As-Built X (M) X X
83 Madera/Cancun ASC/3-2100 No As-Built X (L) X X
84 Madera/Royal ASC/2S-2100 2009 X (M) X X (1) X
85 Madera/Bonita ASC/2-2100 1998 X (H) X X X X
86 Madera/Strathearn ASC/2-2100 No As-Built X (H) X X
87 Madera/Easy ASC/2S-2100 1989 X (M) X X X X (M) X
88 Madera/Cochran Cobalt G-Series 1998 X (7) X (M) X
89 Madera/Viewline Cobalt Safetran No As-Built X X X X (M) X 90 Madera/National ASC/2S-2100 No As-Built X (M) X X X (M) X 91 Royal/Vaquero Cobalt G-Series 1994 X X X (1) X (H) X 92 Royal/Sinaloa ASC/2S-2100 1973 X (H) X X X (4) X (H) X 93 Royal/El Monte Cobalt G-Series 1998 X X X (H) X
94 Royal/Fourth ASC/2S-2100 1973 X (H) X X X
95 Royal/Buckskin ASC/2S-2100 2000 X (M) X X X (2) X (H) X 96 Royal/Crocker ASC/2S-2100 1978 X (H) X X X (1) X (H) X 97 Royal/Thompson Cobalt G-Series 2000 X X X (H) X
98 Royal/Erringer ASC/2S-2100 1987 X (M) X X X (1) X X (1) 99 Royal/Whitcomb ASC/2S-2100 1993 X (M) X X X X (1) X (H) X 100 Royal/Sycamore ASC/2S-2100 1991 X (M) X X X X (M) X 101 Royal/Corto ASC/3-2100 1995 X (L) X X X X (4) X (M) X 102 Royal/Arroyo Simi Cobalt 2013 X X
103 Royal/Sequoia ASC/2-2100 No As-Built X (H) X X X (M) X 2 equestrian push buttons also present. 104 Royal/Darrah Park ASC-8000 1997 X (H) X X X (H) X
105 Sycamore/Arroyo Simi Cobalt G-Series 2013 X X X
106 Sycamore/Heywood ASC/2S-2100 1989 X (M) X X X X (M) X 107 Tapo Canyon/Cochran Cobalt G-Series 1988 X X (1) X (2) X (M) X 2 PPB not needed on pole 6. 108 Tapo Canyon/Alamo ASC/3-2100 2003 X (L) X X X X
109 Tapo Canyon/El Paseo Dr Cobalt G-Series No As-Built X 110 Tapo Canyon/Avenida Simi ASC/2S-2100 2000 X (M) X X X 111 Tapo Canyon/Township Ave ASC/3-2100 No As-Built X (L) X X (1) 112 Tapo/Eileen Cobalt 1988 X X (1) X (1) X (H)
113 Tapo/Kadota-Township Cobalt G-Series 2000 X X X (1) X 114 Tapo/Walnut ASC/2S-2100 2007 X (M) X X
115 Tierra Rejada/Stargaze Cobalt 2000 X X X X (M) X 4 equestrian push buttons also present. 116 Tierra Rejada/Village Cobalt 2008 X X X (1) X (1) X (M) X PPB on pole 5 damaged. 117 Tierra Rejada/Ridgegate Lane ASC/3-2100 No As-Built X (L) X X X 118 Wood Ranch/Martha Morrison ASC/2S-2100 2002 X (H) X X X (1) X 119 Wood Ranch/Country Club ASC/2S-2100 1983 X (M) X X X X (1) X (H) X X (1) 120 Lost Canyons/Eagle Flight ASC/2S-2100 No As-Built X (H) X X (3) X 121 Fitzgerald/Whitcomb ASC/2-2100 No As-Built X (H) X X (H) X 19 20
Attachment C
Traffic Signal Conditions Assessment Report
Phase 0 Intersections

1. Cochran St & Liberty Way

2. Cochran St & Callahan Ave

3. Cochran St & Tracy Ave

4. Cochran St & Winifred St

5. Cochran St & Stow St

6. Cochran St & Yosemite Ave

7. Erringer Rd & Heywood St

8. Erringer Rd & Larch St

9. First St & Arcane St

10. First St & Bennett St

11. First St & Easy St

12. Kuehner Dr & Sandalwood Dr

13. Long Canyon Rd s/o Bluegrass St

14. Los Angeles Ave & Donville

15. Los Angeles Ave & Stow St

16. Royal Ave & Sinaloa Rd

17. Royal Ave & Sycamore Dr

18. Royal Ave & Fourth St

19. Royal Ave & Crocker St

20. Royal Ave & Sequoia Ave

21. Royal Ave & Darrah Park

22. Wood Ranch Pkwy & Martha Morrison Dr

23. Lost Canyons Dr & Eagles Flight Dr

24. Fitzgerald Rd & Whitcomb Ave

25. Tapo St & Walnut Ave
21 1 2 3 4 5 6
7 8
10 9
11 12
13 14 15
16 18 19
17 20
21 25
22 23
24 Esri, NASA, NGA, USGS, FEMA, Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, © OpenStreetMap contributors, and the GIS User Community 22 A ttachment D

Page 1 of 2 ends

FIRST AMENDMENT TO
AGREEMENT NO. 3250014 BETWEEN

THE CITY OF SIMI VALLEY AND
ECONOLITE CONTROL PRODUCTS INC.

T
HIS FIRST AMENDMENT (“Amendment”) is made and entered into this 23 day of March 2026, by and between the CITY OF SIMI VALLEY, a general law city and municipal corporation (“CITY”), and ECONOLITE CONTROL PRODUCTS, INC. , a California Corporation ("CONTRACTOR').

1. P
ursuant to Section 3 of Agreement No. 3250014 (“Agreement”), amending existing sections Scope of Work, Agreement Date & Expiration Date, Agreement Amount to read as follows:

A
greement Date & Expiration Date: October 7, 2024 through October 6, 2027, with an option to extend for two (2) additional one-year terms.

A
greement Amount: Not-to-exceed $375,000
S
cope of Work: Procuring traffic control equipment, including but not limited to Traffic Signal Controller Cabinets, Traffic Signal Controllers, Video Detection Cameras (such as Autoscope Vision), Autoscope Communications Manager, Battery Backup Systems, and necessary Cables and Wiring, traffic signal heads, traffic signal faces and lamps, separate from the City’s existing maintenance agreement with a separate vendor, Econolite Systems, Inc.

2. E
LECTRONIC SIGNATURES. This Amendment may be executed by the Parties on any number of separate counterparts, and all such counterparts so executed constitute one Amendment binding on all the Parties notwithstanding that all the Parties are not signatories to the same counterpart. In accordance with Government Code §16.5, the Parties agree that this Amendment will be considered signed when the signature of a party is delivered by electronic transmission. Such electronic signature will be treated in all respects as having the same effect as an original signature.
3 . This Amendment may be executed in any number or counterparts, each of which will be an original, but all of which together constitutes one instrument executed on the same date.
4 . Except as modified by this Amendment, all other terms and conditions of Agreement No. 3250014 remain the same.
[
SIGNATURES ON NEXT PAGE]
23 City of Simi Valley
First Amendment to Agreement No. 3250014
Econolite Control Products Inc,

Page 2 of 2 ends

IN WITNESS WHEREOF the parties hereto have executed this contract the day and year first hereinabove written.

A
ttest: City of Simi Valley, A Municipal Corporation
By:

Lucy Blanco, City Clerk Samantha C. Argabrite, City Manager A
pproved as to Form: Econolite Control Products, Inc.

Algeria R. Ford, City Attorney By:

P
rint Name: Corey Kelly
Approved as to Content:

Title: Account Manager
Johanna Medrano, By:

Deputy Administrative Services Director/
Budget & Purchasing Print Name:

T
itle:

Ronald K. Fuchiwaki
Public Works Director
24 A ttachment E

Page 1 of 2 ends

FIRST AMENDMENT TO
AGREEMENT NO. 3250121 BETWEEN

THE CITY OF SIMI VALLEY AND

ECONOLITE SYSTEMS, INC
T
HIS FIRST AMENDMENT (“Amendment”) is made and entered into this 23 day of March 2026, by and between the CITY OF SIMI VALLEY, a general law city and municipal corporation (“CITY”), and ECONOLITE SYSTEMS, INC, a California Corporation("CONTRACTOR').

1. P
ursuant to Section 17 of Agreement No. 3250121(“Agreement”), amending an existing section; 2. Contract Sum to read as follows:
2 C
ontract Sum. The City agrees to pay the Contractor a sum not to exceed One million, one hundred two thousand dollars ($1,200,000) for the Work in the manner set forth in the Contract Documents. The City may adjust this amount as set forth in the Contract Documents.

2. E
LECTRONIC SIGNATURES. This Amendment may be executed by the Parties on any number of separate counterparts, and all such counterparts so executed constitute one Amendment binding on all the Parties notwithstanding that all the Parties are not signatories to the same counterpart. In accordance with Government Code §16.5, the Parties agree that this Amendment will be considered signed when the signature of a party is delivered by electronic transmission. Such electronic signature will be treated in all respects as having the same effect as an original signature.
3 . This Amendment may be executed in any number or counterparts, each of which will be an original, but all of which together constitutes one instrument executed on the same date.

4. E
xcept as modified by this Amendment, all other terms and conditions of Agreement No. 3250121 remain the same.
[
SIGNATURES ON NEXT PAGE]
25 City of Simi Valley
First Amendment to Agreement No. 3250121
Econolite Systems, Inc

Page 2 of 2 ends

IN WITNESS WHEREOF the parties hereto have executed this contract the day and year first hereinabove written.

A
ttest: City of Simi Valley, A Municipal Corporation
By:

Lucy Blanco, City Clerk Samantha C. Argabrite, City Manager A
pproved as to Form: Econolite Systems, Inc.

Algeria R. Ford, City Attorney By:

P
rint Name: Christopher Flores
Approved as to Content:

Title: Regional Vice President
Johanna Medrano, By:

Deputy Administrative Services Director/
Budget & Purchasing Print Name: Stephanie DeFazio
T
itle: Vice President, Field Services
Ronald K. Fuchiwaki
Public Works Director
26