Page IV-23 JUNE 2026
SECTION 11 FINAL ACCEPTANCE OF THE WORK
The Contractor will notify the Engineer, in writing, of the completion of the work, and the Engineer will promptly satisfy himself as to the actual completion, and when he is so satisfied he will recommend acceptance to the City Council at its next regular meeting. The date of completion will be the date of acceptance of the work by the City Council.
Agenda Item #7.4:
Page IV-24 JUNE 2026
SECTION 12 MEASUREMENT AND PAYMENT
12.01 Measurement
12.01.1 Unit Price Work
(a) General
Measurement shall be as herein provided except as otherwise specified in Part V Technical Specifications.
Unless otherwise specified, quantities of work shall be determined from measurements or dimensions in horizontal plane. However, linear quantities of pipe, piling, fencing, and timber shall be considered as being the true length measured along the longitudinal axis.
Unless otherwise provided in these Special Provisions or Specifications, volumetric quantities shall be the product of the mean area of vertical or horizontal sections and the intervening horizontal or vertical dimension. The planimeter shall be considered an instrument of precision adapted to the measurement of all areas. (b) Certified Weights
When payment is to be made on the basis of weight, the weighing shall be done on certified platform scales or, when approved by the Engineer, on a completely automated weighing and recording system. The Contractor shall furnish the Engineer with duplicate licensed weigh-master’s certificates showing the actual net weights. The City will accept the certificates as evidence of the weights delivered.
When payment is to be made on the basis of cubic yardage, the yardage shall be recorded by the landfill on each truck ticket as it enters the landfill for disposal, and if the method is preapproved by the Engineer.
(c) Units of Measurement
Measurements shall be in accordance with U.S. Standard Measures. A pound is an avoirdupois pound. A ton is 2,000 pounds avoirdupois. The unit of liquid measure is the U.S. gallon.
12.01.2 Lump Sum Contracts
When required by these Special Provisions or requested by the Engineer, the Contractor shall submit to the Engineer within 15 days after award of Contract, a detailed schedule in triplicate, to be used only as a basis for determining progress payments on a lump sum contract or any designated lump sum bid item. This schedule should equal in total the lump sum bid and shall be in such form and sufficiently detailed as to satisfy the Engineer that it correctly represents a reasonable apportionment of the lump sum.
12.02 Payment
Payment shall be made as herein provided except as otherwise specified in Part V Technical Specifications.
Once each month the Engineer will make an approximate measurement of the work performed through the last day of the preceding month and estimate its value based on the contract unit prices.
When the work has been satisfactorily completed, the Engineer will determine the quantity of work performed and prepare the final estimate of the value thereof.
From each progress estimate, 5% will be deducted and retained by the City, and the remainder less the amount of all previous payments will be paid to the Contractor, except that the Contractor may elect to provide for the substitution of securities for any moneys which would otherwise be withheld Agenda Item #7.4:
Page IV-25 JUNE 2026
by the City to ensure performance under the Contract or may request the City to make payment of retentions earned directly to an escrow agent subject to the provisions of Section 22300 of the Public Contracts Code.
The quantities listed in the bid schedule do not govern final payment. Payments to the Contractor will be made only for the actual quantities of contract items constructed in accordance with the Specifications. If, upon completion of the construction, these actual quantities show either an increase or decrease from the quantities given in the bid schedule, the contract unit prices will still prevail subject to the provisions of Part IV, Section 8 of these Special Provisions.
Payment will not be made for materials wasted or disposed of in a manner not called for under the Contract. This includes rejected material not unloaded from vehicles, material rejected after it has been placed and material placed outside of the plan lines. Unless otherwise provided, no payment will be made for materials delivered to the site but not incorporated in the work. Such quantities will not be included in the final pay quantities. No compensation will be allowed for disposing of rejected or excess material.
Whenever any portion of the work is performed by the City at the Contractor’s request, the cost thereof shall be charged against the Contractor, and may be deducted from any amount due or becoming due from the City.
Whenever immediate action is required to prevent impending injury, death, or property damage, and precautions which are the Contractor’s responsibility have not been taken and are not reasonably expected to be taken, the City may, after reasonable attempt to notify the Contractor, cause such precautions to be taken and shall charge the cost thereof against the Contractor, or may deduct such cost from any amount due or becoming due from the City. City action or inaction under such circumstances shall not be construed as relieving the Contractor or his Surety from liability.
At the expiration of 35 days from the date of recordation of the Notice of Completion by the County Clerk, the amount deducted from the final estimate and retained by the City will be paid to the Contractor except such amounts as are required by law or as are authorized by the Contract to be further retained.
If within the time fixed by law, a properly executed notice to stop payment is filed with the City due to the Contractor’s failure to pay for labor or materials used in the work, all money due for such labor or materials will be withheld from payment to the Contractor in accordance with the applicable laws.
It is the intent of the Specifications and Contract Documents to provide for the construction of complete and finished facilities and works of improvement unless otherwise specifically provided.
Except for authorized changes in the work, payment for said complete and finished facilities and works of improvement will be made only on the basis of the contract items of work listed in the Proposal. All other work, including the furnishing of plant, labor, materials, tools, equipment and incidentals, provided for in the Specifications and Contract Documents, or required for the proper completion of the work as a whole, or for complying with any requirements of the Specifications and Contract Documents, for which no separate payment has been provided shall be a supplementary obligation of the Contractor and payment therefore shall be considered included in the prices paid for the various contract items of work listed in the Proposal.
It is mutually agreed between Contractor and the City that any payments made under the Contract shall not be conclusive evidence of the performance of the Contract, either wholly or in part, against any claim of the City of Sonoma, and no payment shall be construed to be an acceptance of any defective work or improper materials.
Agenda Item #7.4:
Page IV-26 JUNE 2026
The Contractor further agrees that the payment of the final amount due under the Contract, and the adjustment and payment for any work done in accordance with any alterations of the same, shall release the City of Sonoma, the City Council, and all officers, agents and employees thereof from any and all claims or liability on account of work performed under the Contract or any alteration thereof.
12.03 Payment Withholds
Withholds are not retentions under Section 7107 of the Public Contracts Code. For provisions for withholds refer to the Standard Specifications (2018).
Agenda Item #7.4:
Page IV-27 JUNE 2026
SECTION 13 TIMING OF PAYMENT
13.01 Timing of Payment
Billing and payment shall consist of one billing progress payment per month, addressed to City Hall, No. 1 The Plaza, Sonoma, CA 95476, Attention: Accounts Payable; and payment by City check will be made within thirty (30) calendar days of the date of the City Engineer’s approval of the progress payment. Contractor’s progress payment shall include name of project, name of City project manager, and City accounting code in order for proper and timely payment to be made.
Timing of payment may extend beyond 30 calendar days if the Contractor does not have an administrative/office assistant available for questions on a daily basis.
Agenda Item #7.4:
Page IV-28 JUNE 2026
SECTION 14 PROPOSAL REQUIREMENTS AND CONDITIONS
14.01 State Standard Specifications and Plans
The work embraced herein shall be done in accordance with the Contract Documents, Standard Specifications dated 2018 and the Standard Plans dated 2018, of the Department of Transportation insofar as the same may apply and these Special Provisions.
In case of conflict between the Standard Specifications and these Special Provisions, the Special Provisions shall take precedence over and be used in lieu of the conflicting portions.
Revisions to the Standard Specifications set forth in these Special Provisions shall be considered as part of the Standard Specifications for the purposes set forth in Section 5-1.02, "Contract Components," of the Standard Specifications. Whenever either the term "Standard Specifications is amended" or the term "Standard Specifications are amended" is used in the Special Provisions, the indented text or table following the term shall be considered an amendment to the Standard Specifications. In case of conflict between such amendments and the Standard Specifications, the amendments shall take precedence over and be used in lieu of the conflicting portions.
14.02 Plans
The following plans are an integral part of the Contract.
Figure 1, Location and Limits of Slurry Seal.
City Standard Details Standard Plan No.
Local Street Typical Section 101
Collector Street Typical Section 102
Arterial Street Typical Section 103
Standard Pedestrian Crosswalk Continental Crosswalk 104 Construction General Notes 1 and 2 105
Sign, Post and Foundation Installation 115
Frame and Cover Adjustment 116
Survey Monument Installation 117
Caltrans Standard Plans
Pavement Markers and Traffic Lines Typical Details A20A Pavement Markers and Traffic Lines Typical Details A20B Pavement Markers and Traffic Lines Typical Details A20C Pavement Markers and Traffic Lines Typical Details A20D Pavement Markings Arrows A24A
Pavement Markings Arrows and Symbols A24B
Pavement Markings Symbols and Numerals A24C
Pavement Markings Words A24D
Pavement Markings Words, Limits and Yield Lines A24E
Pavement Markings Crosswalks A24F
Object Markers A73A
Agenda Item #7.4:
PART V -
TECHNICAL
SPECIFICATIONS
Agenda Item #7.4:
TOC-i JUNE 2026
Table of Contents
PART V – TECHNICAL SPECIFICATIONS
SECTION 10 GENERAL ..................................................................................................... V-1 10-1.01 GENERAL ......................................................................................................... V-1 10-1.01C EXISTING CONDITIONS ............................................................................. V-2 10-1.01D MOBILIZATION/DEMOBILIZATION ........................................................ V-2 10-1.03 TIME CONSTRAINTS ..................................................................................... V-3 10-1.04 MEETINGS ....................................................................................................... V-3 10-1.04A PRECONSTRUCTION MEETING ............................................................... V-3 10-1.04B SITE MOBILIZATION MEETING ............................................................... V-3 10-1.04C PROGRESS MEETINGS ............................................................................... V-4 10-1.05 CONSTRUCTION SCHEDULE ....................................................................... V-5 10-1.06 DUST CONTROL ............................................................................................. V-5 10-1.07 WATERING ...................................................................................................... V-5 10-1.08 UTILITIES......................................................................................................... V-6 SECTION 12 TEMPORARY TRAFFIC CONTROL .......................................................... V-7 12-1 GENERAL .............................................................................................................. V-7 12-1.01 GENERAL ......................................................................................................... V-7 12-2 PUBLIC NOTIFICATION ..................................................................................... V-7 12-3 TEMPORARY TRAFFIC CONTROL DEVICES ................................................ V-9 12-3.01 GENERAL ......................................................................................................... V-9 12-4 MAINTAINING TRAFFIC .................................................................................. V-10 12-4.01 GENERAL ....................................................................................................... V-10 12-4.02C(3)(m) CLOSURE REQUIREMENTS .......................................................... V-11 12-9 MEASUREMENT AND PAYMENT .................................................................. V-13 12-9.01 PAYMENT ...................................................................................................... V-13 SECTION 13 WATER POLLUTION CONTROL ............................................................ V-14 13-1 GENERAL ............................................................................................................ V-14 13-1.01A SUMMARY .................................................................................................. V-14 13-2 WATER POLLUTION CONTROL PROGRAM ................................................ V-14 13-2.01C SUBMITTALS .............................................................................................. V-14 13-3 STORM WATER POLLUTION PREVENTION PLAN .................................... V-14 13-3.01A SUMMARY .................................................................................................. V-14 13-4 JOB SITE MANAGEMENT ................................................................................ V-14 13-4.03B SPILL PREVENTION AND CONTROL/CASQA (BMP WM-4) .............. V-14 13-4.03D(5) LIQUID WASTE ..................................................................................... V-15 13-4.03E NONSTORM WATER MANAGEMENT/CASQA WATER
CONSERVATION PRACTICES (BMP NS-1 AND NS-2) ......................................... V-15 13-4.03E(7) PAVING, SEALING, SAW CUTTING, GROOVING AND GRINDING ACTIVITIES .................................................................................................................. V-15 13-4.04 PAYMENT ....................................................................................................... V-16 13-6 TEMPORARY SEDIMENT CONTROL .............................................................. V-16 13-6.03C TEMPORARY DRAINAGE INLET PROTECTION/CASQA STORM DRAIN INLET PROTECTION (BMP SE-10) ........................................................................... V-16 13-6.04 PAYMENT ....................................................................................................... V-16 Agenda Item #7.4:
TOC-ii JUNE 2026
SECTION 14 ENVIRONMENTAL STEWARDSHIP ...................................................... V-17 14-11.12 REMOVAL OF YELLOW TRAFFIC STRIPE AND PAVEMENT MARKING WITH HAZARDOUS WASTE RESIDUE ................................................................... V-17 SECTION 15 EXISTING FACILITIES ............................................................................. V-21 15-1.01 GENERAL ........................................................................................................ V-21 15-1.04 PAYMENT ...................................................................................................... V-21 SECTION 37-3 SLURRY SEALs ...................................................................................... V-22 37-3.01 GENERAL ........................................................................................................ V-22 37-3.01A SLURRY SEAL ............................................................................................ V-22 37-3.01A(3) SUBMITTALS ......................................................................................... V-22 37-3.01A(4)(c) ACCEPTANCE ................................................................................... V-23 37-3.01B(2) AGGREGATE .......................................................................................... V-24 37-3.01C CONSTRUCTION ......................................................................................... V-24 37-3.02 SLURRY SEALS ............................................................................................ V-24 37-3.02B MATERIALS ................................................................................................ V-24 37-3.02B(3) POLYMER MODIFIED ASPHALTIC EMULSIONS ........................... V-24 37-3.02C CONSTRUCTION ........................................................................................ V-24 37-3.02C(1) GENERAL ............................................................................................... V-24 37-3.02C(2) PROPORTIONING .................................................................................. V-25 37-3.02C(3) MIXING AND SPREADING EQUIPMENT .......................................... V-25 37-3.02C(4) PLACEMENT .......................................................................................... V-25 37-3.02D PAYMENT ................................................................................................... V-27 SECTION 37-6 CRACK TREATMENT ........................................................................... V-28 37-6.01 GENERAL ........................................................................................................ V-28 37-6.01C SUBMITTALS .............................................................................................. V-28 37-6.02 MATERIALS .................................................................................................. V-28 37-6.03 CONSTRUCTION........................................................................................... V-28 37-6.04 PAYMENT ...................................................................................................... V-29 SECTION 84 MARKINGS ................................................................................................ V-30 84-1.01 GENERAL ........................................................................................................ V-30 84-1.03 CONSTRUCTION............................................................................................ V-30 84-2.01C SUBMITTALS .............................................................................................. V-30 84-2.02 MATERIALS .................................................................................................. V-30 84-2.04 PAYMENT ...................................................................................................... V-31 Agenda Item #7.4:
Page V-1 JUNE 2026
SECTION 10 GENERAL
10-1.01 GENERAL
The work to be done includes the furnishing of all plant, labor, materials, tools, equipment, transportation and incidentals, including all specials and appurtenances, necessary to complete all the Work provided for in the Figure 1 as contained herein, Specifications and Contract Documents for CIP T-3, 2026 CITYWIDE SLURRY SEAL PROJECT NO. 2602.
In general, the work consists of street surface treatment (slurry seal) for various streets throughout the City, including surface preparation, crack seal, slurry seal, removal and replacement of pavement striping and markings, protection of existing utility structures, curb and gutter, cross gutter, traffic control, water pollution control and other related work as set forth on the project Figures and Specifications.
10-1.01A APPROXIMATE LOCATION AND QUANTITIES OF WORK FOR BASE BID
The following tables, along with the Figures provided herein, lists the approximate limits of work and is the basis for the Bid Schedule quantities.
Agenda Item #7.4:
Page V-2 JUNE 2026
No. Street (Slurry Seal
Application Area)
Limits of Work Approximate Quantity
Limit From Limit To Length
(ft)
Avg.
Width
(ft)
Area
(sf)
1 Bettencourt Street Third Street West
Second Street
West 643 34 21,862
2 Bragg Street Clay Street
DE N/O Cooper
Street 335 33 11,055
3 Church Street
Fourth Street
West Third Street West 611 32 19,552
4 Clay Street
Fryer Creek
Drive Broadway 1471 37 54,427
5 Fourth Street East East Napa Street East Spain Street 634 29 18,386 6 Leveroni Road
234' W/O
Broadway Broadway 234 38 8,892
7 Napa Road Broadway
742' E/O
Broadway 742 40 29,680
8 Napa Road
742' E/O
Broadway
City Limits/175' E.
of Pueblo 1197 32 38,304
9 Oak Lane Chase Street Cul de Sac 428 32 13,696
10 Third Street West Arroyo Way Bettencourt Street 390 34 13,260 11 Third Street West
Bettencourt
Street Andrieux Street 264 37 9,768
12 Third Street West Andriuex Street Robinson Street 896 37 33,152 13 Third Street West Robinson Street W. Napa Street 549 40 21,960 14 Third Street West West Napa Street West Spain Street 609 38 23,142 Total for Base Bid (Streets) (Rounded) 317,140
10-1.01C EXISTING CONDITIONS
The City does not guarantee the nature and/or character of surface conditions or of any other materials to be encountered in the work, including the condition of the existing pavement. Should actual conditions be found to differ from those indicated on the Figures or in the Specifications, the Contractor shall have no claim against the City.
The City will not provide a staging area for this project. The Contractor shall make his own arrangements for a staging area on private property. All costs and expenses associated with the staging area shall be borne by the Contractor at no cost to the City. Any staging area proposed for use by the Contractor that is within the City’s or County’s right-of-way must be approved by the City Engineer or County Inspector. Vehicles will not be allowed to park off of the pavement. 10-1.01D MOBILIZATION/DEMOBILIZATION
Mobilization/Demobilization will be made in two equal payments at the lump sum (LS) allowance in the Bid Schedule, which price shall constitute full compensation for all such work. The scope of Agenda Item #7.4:
Page V-3 JUNE 2026
work for Mobilization shall include, but not limited to, obtaining all bonds, insurance and permits, moving onto the site of all plant and equipment, preparation and attendance at all project meetings, preparation and maintenance of the construction schedule, dust control, water for construction, and compliance with all other work within this section. Payment for Demobilization shall occur when all required items per the Contract are fulfilled and the site is free of equipment and clean. 10-1.03 TIME CONSTRAINTS
Refer to Notice to Bidders for time allowed for completion of all work under the contract. The Contractor shall diligently prosecute the work to completion within the time provided.
The City expects to issue to the Contractor a Notice to Proceed for the work, effective as soon as practicable after execution of the construction contract. 10-1.04 MEETINGS
10-1.04A PRECONSTRUCTION MEETING
The City will schedule meeting after Notice of Award. The attendance required at the meeting includes the City, Engineer and Contractor. The agenda will include the following items:
1. Execution of City-Contractor Agreement;
2. Submission of executed bonds and insurance certificates;
3. Distribution of Contract Documents;
4. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule;
5. Designation of personnel representing parties in Contract, and Engineer;
6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures;
7. Scheduling;
8. Submission of list of permits and licenses the Contractor shall obtain indicating the agency required to grant the permit, the expected date of submittal for the permit, and required date for receipt of the permit; and
9. Hazardous and non-hazardous residue and contingency of payment on adequate disposal.
The City will record minutes and distribute copies within two days after meeting to participants, with two copies to Engineer, City, and those affected by decisions made. 10-1.04B SITE MOBILIZATION MEETING
The City will schedule the site mobilization meeting at the Project site prior to Contractor occupancy.
The attendance required at the meeting includes the City, Engineer, Contractor, Contractor's Superintendent, and major Subcontractors. The agenda will include the following items:
1. Use of premises by City and Contractor;
2. City's requirements;
Agenda Item #7.4:
Page V-4 JUNE 2026
3. Construction facilities and controls provided by City;
4. Temporary utilities provided by City;
5. Survey and layout;
6. Security and housekeeping procedures;
7. Schedules;
8. Application for payment procedures;
9. Procedures for testing;
10. Procedures for maintaining record documents; and
11. Inspection and acceptance of equipment put into service during construction period.
The City will record minutes and distribute copies within two days after meeting to participants, with two copies to Engineer, City, and those affected by decisions made. 10-1.04C PROGRESS MEETINGS
The City will schedule and administer meetings throughout the progress of the Work at maximum biweekly intervals. The City will make arrangements for the meetings, prepare agenda with copies for participants, and preside at the meetings. The attendance required at the meeting includes the Job superintendent, major subcontractors and suppliers, City, Engineer, as appropriate to agenda topics for each meeting. The agenda will include the following items:
1. Review minutes of previous meetings;
2. Review of Work progress;
3. Field observations, problems, and decisions;
4. Identification of problems impeding planned progress;
5. Review of submittals schedule and status of submittals;
6. Review of off-site fabrication and delivery schedules;
7. Maintenance of progress schedule;
8. Corrective measures to regain projected schedules;
9. Planned progress during succeeding work period;
10. Coordination of projected progress;
11. Maintenance of quality and work standards;
12. Effect of proposed changes on progress schedule and coordination; and
13. Other business relating to Work.
The City will record minutes and distribute copies within two days after meeting to participants, with two copies to Engineer, City, and those affected by decisions made.
Agenda Item #7.4:
Page V-5 JUNE 2026
10-1.05 CONSTRUCTION SCHEDULE
After notification of award, and prior to the start of any work, the Contractor shall submit to the Engineer for approval his proposed construction schedule in accordance with the Special Provisions Part IV, Subsection 7.04. Said schedule shall incorporate the requirements specified herein, including coordination with utilities. Work shall not begin until said schedule has been approved by the Engineer.
The construction schedule must be a Critical Path Method (CPM) schedule identifying the critical path, constrained to the original contract completion date. Submit a plotted original, time-scaled network diagram on a sheet at least 8-1/2 by 11 inches with a title block and timeline.
The schedule must include the following, at a minimum:
Contract milestones and constraints;
Critical submittal development, review and acceptance;
Material procurement; and
All work steps and construction activities.
The Contractor shall plan his operations in such a manner as to cause as little inconvenience as possible to public traffic and the various facilities located adjacent to the work; including any time or construction phasing constraints provided in these specifications. 10-1.06 DUST CONTROL
The Contractor shall at all times provide for the abatement of dust nuisance. When required by the Engineer, the Contractor shall furnish and operate a self-loading motor sweeper with spray nozzles as often as necessary to keep paved areas acceptably clean and free of dust. 10-1.07 WATERING
Recycled water for use in the work (slurry seal, dust control, etc.) will be available from Sonoma County Water Agency Sonoma Valley County Sanitation District, at 22675 Eighth Street East, Sonoma, CA. Contact Sonoma County Water Agency for recycled water rates and charges. Potable water may be available by request from the City. The Contractor is responsible for all costs associated with obtaining recycled water or potable water. Prior to using any water, the Contractor may need to obtain a permit from the Sonoma County Water Agency Sonoma Valley County Sanitation District or City.
The Contractor shall comply with all requirements of the permit and all water used shall be measured by means of a meter. The Contractor, at his option and expense, may obtain water from some source other than the Sonoma Valley County Sanitation District or City water system.
All water trucks and/or other tanks used by the Contractor shall have an approved air-gap separation between the free-flowing discharge end of the supply pipe and the overflow rim of the receiving vessel.
The air-gap shall be at least double the diameter of the supply pipe measured vertically above the overflow rim of the vessel, but in no case less than one inch.
Agenda Item #7.4:
Page V-6 JUNE 2026
10-1.08 UTILITIES
The Contractor's attention is directed to the existence of underground utility lines, power, telephone, and cable television poles and to sewer, water, and storm drain facilities within the area in which construction is to be performed.
Prior to starting work, the Contractor shall (a minimum of two working days in advance) call Underground Service Alert (USA), toll free, at (800) 227-2600 or call 811 and provide USA with all necessary data relative to the proposed work. USA will accept calls and process information to participating agencies who have underground facilities in the area between the hours of 7:30 a.m. and 5:00 p.m. daily, except Saturdays, Sundays, and holidays. Between the hours 5:00 p.m. and 7:30 a.m. calls will be recorded and then processed after 7:30 a.m. For emergency situations, after hours and on Saturdays, Sundays and holidays, the Contractor shall contact the organization owning the affected facility. Upon notification, agencies having facilities in the area of the proposed excavation will mark their locations in the field using USA standard colors and codes to identify the facility.
The Contractor will be required to work around utility facilities and other improvements that are to remain in place within the construction area, or that are to be relocated and relocation operations have not been completed, and he will be held liable to the owners of such facilities or improvements for any damage to such facilities or interference with service resulting from his operations.
Agenda Item #7.4:
Page V-7 JUNE 2026
SECTION 12 TEMPORARY TRAFFIC CONTROL
12-1 GENERAL
12-1.01 GENERAL
Construction area traffic control devices shall be installed and maintained in accordance with the applicable sections of these Special Provisions, the Standard Specifications, the current edition of the California Manual on Uniform Traffic Control Devices (CA MUTCD), the Americans with Disabilities Act (ADA) and as directed by the Engineer.
12-2 PUBLIC NOTIFICATION
12-2.1 GENERAL NOTIFICATIONS
The Contractor shall be required to notify and cooperate with the public, transit companies, local law enforcement agencies, and any other persons or agencies who may be affected by this project.
Contractor shall notify affected parties, including property owners near staging area, at least five (5) working days prior to construction. Other notifications may be required during project construction as outlined below. The Contractor must submit notifications for City review and acceptance prior to notification.
Notifications will be provided by the Contractor relating to, but not limited to, the following items:
General information;
Traffic delays and alternate routes;
Driveway closures;
Temporary relocation of bus stops;
Mail delivery; and
Solid waste/recycling pick-up.
Such notice shall state that all vehicles and equipment need to be moved off of the street and include the expected date for start of construction, a general description of the construction activity to take place, expected duration of the activity, and the name, address, and 24-hour telephone number of the Contractor. The form of notice shall be subject to approval of the Engineer and shall be provided to the Engineer for approval, prior to distribution.
At five (5) calendar days and again at forty-eight (48) hours prior to beginning any construction operations which will, in any way, inconvenience the business or resident/property owner or affect their operations or preclude access to their property, the Contractor shall distribute approved written notices to all adjoining residents and businesses, property owners, tenants and applicable parties. A separate written notice shall be provided for (1) streets directly affected by project construction (2) streets indirectly affected by the project construction and (3) those properties that are affected by the Contractor’s selected staging area. At a minimum, the Contractor shall deliver written notices to residents on Bettencourt Street, Bragg Street, Church Street, Clay Street, Fourth Street East, Leveroni Road, Napa Road, Oak Lane, Third Street West, and others indirectly affected by slurry seal when no other outlet or detour is available, advising them of the planned construction schedule and operations.
At the same time, a separate notice must be provided to all resident/property owner or business and/or school that is impacted based on the Contractor’s staging area. Re-scheduled operations shall require Agenda Item #7.4:
Page V-8 JUNE 2026
new notices. The Contractor is directed to Sections 12-2 for additional traffic control and special requirements pertaining to advance public notification.
The Contractor shall maintain a 24-hour cellular telephone. The Contractor shall check for messages at least once every twelve hours, seven days a week, including weekends and holidays. The Contractor shall respond promptly to all calls. The cost of maintaining the 24-hour telephone as herein specified shall be considered as included in the various other contract items and no additional compensation shall be allowed therefore.
If operations have been postponed or cancelled with no work in the proposed area for more than five (5) working days, the Contractor shall re-notify the affected residents and businesses with new notices a minimum of twenty-four (24) hours prior to the start of the work.
The Contractor shall notify:
Sonoma Valley Unified School District at least forty-eight (48) hours in advance of any street closing which will affect the school bus routes at any time school is in session; St. Francis Solano Catholic School at least forty-eight (48) hours in advance of any street closing which will affect the school at any time school is in session; U. S. Postal Service at least forty-eight (48) hours in advance of any street closing which will affect mail deliveries; and
Sonoma County Transit at (707) 585-7516 five calendar days prior to any lane closures or restrictions in turning movements.
City of Sonoma Police Department at (707) 996-3602 at least forty-eight (48) hours in advance of any street closing.
Sonoma Valley Fire Department at (707)996-2102 at least forty-eight (48) hours in advance of any street closing.
Sonoma Garbage Collectors at (707) 996-7555 at least one week (7 days) in advance of any street closing.
The Contractor shall maintain an updated and chronological record at the job site of all written notifications along with a list of recipients. Such records shall be made available upon request by the Engineer.
Failure to comply with the above notification requirements could result in cancellation of the day’s work by the Engineer. No extension of time or additional cost will be granted for delays to the Contractor caused by any work cancellations.
No work shall take place prior to the required notification, re-notification, or coordination work with affected facilities.
12-2.2 NOTIFICATION SIGNS
The Contractor shall install “Senate Bill 1” signs (furnished by the City) at locations determined by the City at each of the project streets. The City will provide direction for location of signs during Agenda Item #7.4:
Page V-9 JUNE 2026
construction. The Contractor shall move and relocate signs during the progress of work, per the direction of the City.
Contractor shall provide and install “Businesses Open During Construction” signs (minimum of 4 each) at appropriate streets. The signs shall be submitted to the City for layout approval prior to fabrication.
The City will provide direction for location of signs during construction. The Contactor shall move and relocate signs during the progress of the work, per the direction of the City. 12-3 TEMPORARY TRAFFIC CONTROL DEVICES
12-3.01 GENERAL
Prior to commencing construction which will affect existing vehicular and pedestrian traffic, the Contractor shall submit, for review by the Engineer, Traffic Control Plans on 11" x 17" sheets of paper which contains only information specifically related to work zone vehicular and pedestrian traffic control. If the Contractor proposes to use the current edition of the CA MUTCD published by Caltrans in lieu of a traffic control plan, in specific work operations, they shall submit in writing for consideration which Typical Application Diagram will be used and how it will be applied for each work operation.
Traffic Control Plans or proposals shall be submitted for review at least two weeks prior to implementation.
Traffic Control Plans shall contain a title block which contains the Contractor's name, address, phone number, project superintendent's name, contract name, dates and hours traffic control will be in effect, and a space for review acknowledgment.
The content of the Traffic Control Plan shall include, but is not limited to, the following:
1. Show location and limits of the work zone.
2. Give dimensions of lanes affected by traffic control that will be open to traffic.
3. Indicate signing, cone placement, and other methods of delineation and reference to appropriate Caltrans Standards.
4. Dimension location of signs and cone tapers.
5. Identify side streets and driveways affected by construction and show how they will be handled.
6. Show how pedestrian traffic will be handled through the construction site. Pedestrian pathways through the work zone shall be in compliance with the requirements of ADA during and after work hours.
7. Identify message board locations. A minimum of eight (8) changeable message boards shall be required, one in each direction of travel. Location to be determined by Engineer, for the following streets:
a. Leveroni Road;
b. Napa Road; and
c. Third Street East.
8. Contractor shall take special care to avoid school drop off and pickup periods for Church Street and Third Street West between W. Napa Street and W. Spain Street (for work around St. Francis Agenda Item #7.4:
Page V-10 JUNE 2026
Solano Catholic School). Work shall be phased to occur outside of school drop-off or pickup hours.
9. Contractor must coordinate with Cogir Senior Living (located on Napa Road), Freidman’s Home Improvement (located on Napa Road) and the Lodge at Sonoma (located on Leveroni Road/Clay Street) for work around delivery schedules.
10. Demonstrate how two-way traffic will be maintained, which must be maintained on all arterial and major/minor collector streets, as determined in coordination with the City during construction.
No work except for installation of project identification signs will be allowed to commence prior to approval of the Work Zone Traffic Control Plans.
12-4 MAINTAINING TRAFFIC
12-4.01 GENERAL
Pedestrian and Vehicular access shall be maintained at all times to all existing driveways, except when work in the immediate vicinity poses a safety risk to the public. If access is interrupted, the Contractor shall perform the work in an expeditious manner such that access can be restored as quickly as possible while maintaining a safe worksite. Pedestrian access and circulation that is fully wheelchair accessible shall be maintained by the Contractor through the project area. The full width of the traveled way shall be open for use by public traffic on Saturday, Sundays and designated legal holiday(s), after 4:00 p.m. on Fridays and the day preceding designated legal holidays, and when construction operations are not actively in progress, unless work has specifically been authorized by the Engineer.
The location of traffic control signing, barricades, and other facilities shall be monitored frequently (four to five times per day) by the Contractor to verify their proper location. All traffic signal and other traffic control devices shall be maintained at all times.
The Contractor shall conduct his operations so as to cause the minimum obstruction and inconvenience to traffic and to places of business, multiple dwelling units and residences adjacent to the work. The Contractor shall notify the Engineer of his planned work and utility service interruption at least five working days in advance to allow time to notify residents and businesses.
When construction activities will prevent vehicle access to individual driveways the Contractor shall notify the affected businesses and residents per Section 12-2, “Traffic Control”, of these Special Provisions. Full access shall be provided to all driveways during non-working hours.
Free access shall be provided at all times to existing fire hydrants, water meters, water valves and mailboxes. Utility companies shall be provided access to their facilities as required. The Contractor shall cooperate with the Sonoma Garbage Collector to the extent necessary to maintain existing trash collection schedules.
The Contractor shall furnish, erect and maintain all warning signs, lights, barricades, detour and directional signs and such other devices as are considered necessary by the Engineer to provide adequate warning and direction to public traffic. The Contractor shall furnish flagmen whenever necessary to provide for safety of the public and/or workmen. Handheld or vehicle mounted radios shall be provided as necessary for communications between flagmen.
Agenda Item #7.4:
Page V-11 JUNE 2026
Whenever necessary, the Contractor shall furnish an adequate number of competent flagmen whose sole duties shall consist of directing the movement of public traffic through or around the work area, maintaining the traffic control system and maintaining advanced warning signs and detour signs. If any component in the traffic control system, detour signs, etc. is damaged, displaced or ceases to operate or function as intended, from any cause, the Contractor shall immediately repair said component to its original condition, or replace said component, and shall restore the component to its original location. 12-4.02C(3)(m) CLOSURE REQUIREMENTS
Traffic control and access shall be in accordance with Part IV, Subsection 6.08 of these Special Provisions and as provided herein.
The Contractor shall plan his operations in such a manner as to cause as little inconvenience as possible to public traffic and the various facilities located adjacent to the work.
Traffic shall be permitted to pass through the work area, and access to private driveways, businesses, and garages shall be provided except when precluded by necessary construction for reasonable periods of time as approved by the Engineer. The Contractor shall coordinate their work schedule around businesses deliveries. The Contractor shall accommodate and provide full access as required for businesses to accept deliveries and full access/egress for entering and existing customer traffic.
The Contractor shall maintain at least one lane of traffic at all times. Road closures to through traffic will be permitted, pending acceptance of the Contractor’s traffic control plan. A minimum of one lane, not less than 11-feet wide, shall be open for use by public traffic in each direction with adequate traffic control and signing and one-way traffic control with flaggers as necessary.
All streets and sidewalks shall be opened to public use and traffic at the end of each day’s work or whenever work ceases for any reason. For streets closed to through traffic, sidewalks shall remain open.
The Contractor shall not park construction vehicles contractor employee vehicles, stage materials or stockpiles in front of any business or residential driveway access and the Contractor shall maintain access to private parking lots within the block where work is in progress. Construction vehicles shall not be left running for any length of time if parked in front of a business or residential unit.
On identified local/residential streets the Contractor will normally be allowed use of each block (between nearest intersections) for their sole use, without the need to provide two-way traffic through that block. The Contractor will be required to maintain vehicle access to homes and other properties within the block where work is in progress.
The Contractor shall keep the City of Sonoma Fire Department informed regarding the closure of any traveled way. At a minimum, the Contractor shall call the Fire Department daily to report any traveled way closure. This means immediately upon closure for that day and again immediately after removal of the closure. For closures over multiple days, the daily notification still applies. This requirement does not apply for single lane closures on multiple lane streets. Where necessary, and only after receiving written approval from the Engineer, the Contractor may temporarily suspend curb side parking in their immediate work zone. Contractor shall hand deliver Notification to businesses and residents at least 72 hours prior to construction in the affected areas.
Notification shall be as follows:
Agenda Item #7.4:
Page V-12 JUNE 2026
1. A notice placed on the front door of each home or business where curb side parking will be suspended and attempt made to notify each business or resident verbally that work will be underway within the block and that curb side parking will be suspended during stated working hours and request that vehicles be parked out of the roadway by 8:00 a.m. Service of notice shall not bar use of cars within the block, as individual plans change and emergencies arise.
2. Type 1 barricades every 50 (-100 feet depending on street) feet adjacent to the curb where parking will be suspended with a notice posted on the barricade stating specific dates and times that curb side parking will be temporarily suspended. If work will not take place in the posted area, then Contractor shall remove “No Parking” notices. The no parking notice shall include day of the week written out or properly abbreviated with 3 or 4 letters; the month shall be written out or properly abbreviated with 3 or 4 letters; date or dates of restriction shall be listed completely; the beginning and ending times shall be clearly listed on the sign. Signs shall be mounted such that the words, “No Parking” are at an elevation at least 3 feet and not more than 7 feet above the adjacent flow line. The signs/barricades shall be placed as needed to control the parking of cars within the construction zone.
The Contractor shall maintain vehicle access to all homes and other properties along the work zone and within 300 feet on cross streets. During slurry operations, the Contractor will be allowed to temporarily suspend vehicle access to a limited number of driveways when approved by the Engineer. When approved by the Engineer and at least 72 hours prior to suspending access to any driveway, the Contractor shall give both written and verbal notice to the affected businesses and residents and place barricades adjacent to the driveways with posted notices stating the specific dates and times of the suspension for that area. The notice shall also indicate an alternate parking location. Suspension of access to driveways will be permitted only as approved by the Engineer and only between the hours of 8:00 am and 4:30 pm.
The Contractor shall be fully responsible for adequate removal of all parked cars. All vehicle removals shall be coordinated by the Contractor with the City of Sonoma Police Department. The Contractor shall notify the Police Traffic Sergeant upon posting of the parking restrictions. For removal of parked vehicles, the Contractor shall notify the Police Traffic Sergeant not less than 2 hours prior to the needed removal with the address nearest the parked vehicle, make, model, color, and license number. The City shall not be responsible for any delay or additional cost associated with the removal of parked cars which obstruct the construction operation.
If a vehicle owner successfully contests a towing citation in court, and their citation is dismissed for causes related to the Contractor’s failure to perform the requirements of this section, the Contractor shall reimburse the City for the cost of any claims associated with the towing citation.
The Contractor shall cooperate and allow City or utility company work crews to use the traffic control system when set up for the Contractor’s work.
Cross streets will require maintenance of at least one-half (1/2) width of each street for traffic purposes, unless a parallel route is approved by the Engineer. Flagging will only be allowed between the hours of 8:30 am and 4:00 pm.
Barricades and flaggers shall be positioned to allow safe turns at intersections and curves.
Agenda Item #7.4:
Page V-13 JUNE 2026
The Contractor shall maintain traffic control as necessary and as directed by the Engineer for "cattracking" operations by City Forces. Flaggers, barricades, signing, etc., shall remain in place for protection of City personnel until such time as all temporary lane delineation is complete. 12-9 MEASUREMENT AND PAYMENT
12-9.01 PAYMENT
Traffic Control shall be paid for at the contract lump sum price, which price shall include full compensation for furnishing all labor, materials, tools and equipment, and doing all work involved in vehicular and pedestrian traffic control, including but not limited to, providing, placing, maintaining, and removal of temporary paths and/or ramps, temporary relocation of regulatory signs, changeable message boards, project and public notification signs, written public notifications, flagging, excavation, compaction, furnishing, and placement of asphalt concrete and/or PCC, barricades, toe-rails, hand rails, complying with CA MUTCD Standards for Pedestrian Safety, coordination efforts and any other items necessary for vehicle and pedestrian traffic control not specifically enumerated in the plans or these specifications, and no additional allowance will be made therefor.
Agenda Item #7.4:
Page V-14 JUNE 2026
SECTION 13 WATER POLLUTION CONTROL
13-1 GENERAL
13-1.01A SUMMARY
Water pollution control shall be performed in accordance with Section 13, Water Pollution Control, of the Standard Specifications and these Special Provisions.
Information on forms, reports and other documents can be found in the following Caltrans manuals:
1. Field Guide for Construction Site Dewatering
2. Storm Water Pollution Prevention Plan (SWPPP) and Water Pollution Control Program (WPCP) Preparation Manual (June 2011).
3. Construction Site Best Management Practices (BMP) Manual.
4. Construction Site Monitoring Program (CSMP) Guidance Manual.
Manuals and templates are available at Caltrans Division of Construction website:
https://dot.ca.gov/programs/construction/storm-water-and-water-pollution-control.
A Storm Water Pollution Control (WPCP) program must be developed and implemented for all projects where soil disturbance from work activities is less than 1 acre. A Storm Water Pollution Prevention Plan (SWPPP) must be developed and implemented for all projects where soil disturbance is equal-to or greater-than 1 acre.
It is anticipated that the soil disturbance will be less than 1 acre for this Project.
In this technical specification, the California Stormwater Quality Association (CASQA) Best Management Practice (BMP) Handbook BMP numbers are appended to the associated Standard Specification sections. If a conflict occurs, the CASQA BMP Handbook BMP’s shall govern. 13-2 WATER POLLUTION CONTROL PROGRAM
13-2.01C SUBMITTALS
The program to control water pollution required to be submitted under this section of the Standard Specifications shall include a spill contingency plan that establishes clean-up procedures that will be followed in the event of a spill of potentially hazardous, toxic or polluting materials. 13-3 STORM WATER POLLUTION PREVENTION PLAN
13-3.01A SUMMARY
This project is exempt from the State Water Resources Control Board General NPDES Permit for the Discharge of Storm Water related to Construction Activities (Construction General Permit), and not required to have a Storm Water Pollution Prevention Plan (SWPPP), therefore Section 13-3, Storm Water Pollution Prevention Plan, of the Standard Specifications does not apply to this project. 13-4 JOB SITE MANAGEMENT
13-4.03B SPILL PREVENTION AND CONTROL/CASQA (BMP WM-4)
If a spill occurs at the construction site and the Contractor does not take immediate action and adequate steps to contain and clean up the spill, especially if rain is threatening or if a discharge to a storm drain or creek could occur, the City shall have the right, in its sole and absolute discretion, to clean up spill Agenda Item #7.4:
Page V-15 JUNE 2026
using City forces or independent contractor. The cost of any such cleanup, in addition to recovery of any penalty of fine imposed upon the City, plus administrative charge of fifteen percent (15%) of the costs incurred by the City, shall be deducted from any amounts owed to the Contractor hereunder.
In the event there are insufficient amounts owed to Contractor hereunder to cover the foregoing costs and charges, the City shall have the right to pursue any other remedy to recover same, including, but not limited to, proceeding against any surety or bond in favor of the City. The City’s rights under this section are intended to be in addition to and not in lieu of any imposed by the City against Contractor for violations of City Code Chapter 17-12, “Storm Water”. 13-4.03D(5) LIQUID WASTE
Liquid waste includes water generated from excavation dewatering. Minimize transfer piping by locating containers near the excavation to be dewatered while protecting the containers from moving vehicles and equipment.
13-4.03E NONSTORM WATER MANAGEMENT/CASQA WATER
CONSERVATION PRACTICES (BMP NS-1 AND NS-2)
13-4.03E(7) PAVING, SEALING, SAW CUTTING, GROOVING AND GRINDING
ACTIVITIES
The following additional BMPs shall be implemented for street paving, repaving, reconstruction, patching, digouts or resurfacing.
1. Restrict paving and repaving activity to exclude periods of rainfall or predicted rainfall unless required by emergency conditions;
2. Install BMPs at all susceptible storm drain inlets and manholes to prevent paving products and tack coat from entering;
3. Prevent the discharge of release agents including soybean oil, other oils, or diesel to the storm water drainage system or watercourses;
4. Minimize non-storm water runoff from water use for the roller and for evaporative cooling of the asphalt;
5. Clean equipment over absorbent pads, drip pans, plastic sheeting or other material to capture all spillage and dispose of properly;
6. Collect liquid waste in a container, with a secure lid, for transport to a maintenance facility to be reused, recycled, or disposed of properly;
7. Collect solid waste by shoveling and vacuuming or sweeping and securing in an appropriate container for transport to a maintenance facility to be reused, recycled, or disposed of properly;
8. Cover “cold-mix” asphalt (i.e., pre-mixed aggregate and asphalt binder) with protective sheeting during a rainstorm;
9. Cover loads with tarp before haul-off to a storage site, ensuring that trucks are not overloaded;
10. Minimize airborne dust by using water spray during grinding;
11. Protect stockpiles with a cover or sediment barriers during a rain event; Agenda Item #7.4:
Page V-16 JUNE 2026
12. Sweep streets daily as-needed and as required by the Engineer; and
13. Avoid stockpiling soil, sand, sediment, asphalt material and asphalt grindings materials or rubble in or near storm water drainage system or watercourses. 13-4.04 PAYMENT
Full compensation for conforming to the requirements of this Section shall be considered as included in the contract prices paid for various contract items of work under Section 37-3 “Slurry Seal,” which price shall include all work required and necessary to comply with the NPDES permit, prepare and implement a written program to control water pollution, and furnishing, installing, maintaining and removing BMPs and no additional allowance will be made therefor. 13-6 TEMPORARY SEDIMENT CONTROL
13-6.03C TEMPORARY DRAINAGE INLET PROTECTION/CASQA STORM DRAIN INLET PROTECTION (BMP SE-10)
Contractor shall implement storm drain inlet protection BMPs per the Contractors submitted storm water management plan.
13-6.04 PAYMENT
Full compensation for conforming to the requirements of this Section shall be considered as included in the contract prices paid for various contract items of work under Section 37-3 “Slurry Seal,” which price shall include all work required and necessary to comply with the NPDES permit, prepare and implement a written program to control water pollution, and furnishing, insulating, maintaining and removing BMPs and no additional allowance will be made therefor.
Agenda Item #7.4:
Page V-17 JUNE 2026
SECTION 14 ENVIRONMENTAL STEWARDSHIP
14-11.12 REMOVAL OF YELLOW TRAFFIC STRIPE AND PAVEMENT MARKING
WITH HAZARDOUS WASTE RESIDUE
14-11.12A GENERAL
Section 14-11.12 applies if the removal of existing yellow thermoplastic and yellow painted traffic stripe and pavement marking that will produce hazardous waste residue is specified in the special provisions. Section 14-11.12 includes specifications for removing, handling, and disposing of yellow thermoplastic and yellow painted traffic stripe and pavement marking. The residue from the removal of this material is a Department-generated hazardous waste.
Residue from the removal of yellow thermoplastic and yellow painted traffic stripe and pavement marking contains lead chromate. The average lead concentration is at least 5 mg/l soluble lead or 1,000 mg/kg total lead. When applied to the roadway, the yellow thermoplastic and yellow painted traffic stripe and pavement marking contained as much as 2.6 percent lead. Residue produced from the removal of this yellow thermoplastic and yellow painted traffic stripe and pavement marking contains heavy metals in concentrations that exceed thresholds established by the Health & Safety Code and 22 CA Code of Regs. For bidding purposes, assume the residue is not regulated under the Federal Resource Conservation and Recovery Act, 42 USC § 6901 et seq.
The work associated with the disposal of hazardous waste residue identified by test results to be regulated under the Resource Conservation and Recovery Act (RCRA), if any, is change order work.
Removal of existing yellow thermoplastic and yellow painted traffic stripe and pavement marking exposes workers to health hazards that must be addressed in your lead compliance plan. Yellow thermoplastic and yellow paint may produce toxic fumes when heated. 14-11.12B SUBMITTALS
14-11.12B(1) GENERAL
Reserved
14-11.12B(2) WORK PLAN
Submit a work plan for the removal, containment, storage, and disposal of yellow thermoplastic and yellow painted traffic stripe and pavement marking. The work plan must include:
1. Objective of the operation;
2. List of removal equipment;
3. Procedures for the removal and collection of yellow thermoplastic and yellow painted traffic stripe and pavement marking residue, including dust;
4. Type of hazardous-waste storage containers;
5. Description of storage location and how it will be secured;
6. Hazardous waste sampling protocol and Quality Assurance requirements and procedures; Agenda Item #7.4:
Page V-18 JUNE 2026
7. Qualifications of sampling personnel;
8. Name and address of the analytical test laboratory certified by the State Water Resources Control Board's (SWRCB) Environmental Laboratory Accreditation Program (ELAP) for all analyses to be performed;
9. Name of the hazardous waste transporter and the transporter's:
a. California Department of Toxic Substances Control (DTSC) registration certificate b. Proof of compliance with the California Highway Patrol Biennial Inspection of Terminals Program; and
10. Name and address of the disposal site that will accept the hazardous waste residue.
If ordered, submit a revised work plan within 5 business days of notification. 14-11.12B(3) ANALYTICAL TEST RESULTS
Submit analytical test results of the residue and chain of custody documentation before:
1. Requesting the Engineer's signature on the waste profile document for the disposal facility;
2. Requesting from the Engineer the generator's EPA Identification Number for disposal; and
3. Removing the residue from the job site.
14-11.12B(4) DISPOSAL DOCUMENTATION
Submit documentation of proper disposal from the receiving landfill within 5 business days of transporting residue from the job site.
14-11.12C REMOVAL
When grinding or other authorized methods are used to remove yellow thermoplastic and yellow painted traffic stripe and pavement marking that produces a hazardous waste residue:
1. Immediately contain and collect the residue, including dust; and
2. Use a High Efficiency Particulate Arrestance (HEPA) filter-equipped vacuum attachment operated concurrently with the removal operations or other equivalent approved method for collection of the residue.
Store hazardous waste residue in labeled and covered containers. Labels must comply with the provisions of 22 CA Code of Regs §§66262.31 and 66262.32. Mark labels with:
1. Date the hazardous waste is generated;
2. The words "Hazardous Waste;"
3. Composition and physical state of the hazardous waste (for example, asphalt grindings with thermoplastic or paint);
4. The word "Toxic;"
Agenda Item #7.4:
Page V-19 JUNE 2026
5. Name, address, and telephone no. of the Engineer;
6. Contract No.; and
7. Contractor or subcontractor name.
Use metal containers approved by the U.S. Department of Transportation for the transportation and temporary storage of the removed residue. Handle the containers such that no spillage occurs. Store containers in a secured enclosure. Acceptable secure enclosures include a locked chain link fenced area or a lockable shipping container located within the project limits until disposal as approved. 14-11.12D SAMPLING AND TESTING OF RESIDUE
Hazardous waste residue from the removal of yellow thermoplastic and yellow painted traffic stripe and pavement marking must be tested as required by the disposal facility and including:
1. Total lead by US EPA Method 6010B;
2. Total chromium by US EPA Method 6010B;
3. Soluble lead by the California Waste Extraction Test;
4. Soluble chromium by the California Waste Extraction Test;
5. Soluble lead by the Toxicity Characteristic Leaching Procedure; and
6. Soluble chromium by the Toxicity Characteristic Leaching Procedure.
From the first 220 gal of hazardous waste or portion thereof, if less than 220 gal are produced, a minimum of 4 randomly selected samples must be taken and analyzed individually. Samples must not be composited. From each additional 880 gal of hazardous waste or portion thereof, if less than 880 gal are produced, a minimum of 1 additional random sample must be taken and analyzed.
Use chain of custody procedures consistent with chapter 9 of US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846) while transporting samples from the job site to the analytical laboratory.
Before performing the analyses, the laboratory must homogenize each sample. The homogenization process must not include grinding of the samples. The aliquot taken from the sample must be:
1. Obtained in an amount large enough for all analyses to be performed;
2. Homogenized a 2nd time; and
3. Used for the total and soluble analyses after the 2nd homogenization. 14-11.12E TRANSPORT AND DISPOSAL OF RESIDUE
Request the generator's EPA Identification Number when the Engineer accepts waste characterization test results documenting that the residue is a hazardous waste.
The Engineer signs the manifests as the hazardous waste generator within 2 business days of 1) receiving and accepting the analytical test results and 2) receiving your request for the generator's EPA Identification Number.
Agenda Item #7.4:
Page V-20 JUNE 2026
If test results demonstrate that the residue is a nonhazardous waste and the Engineer accepts this determination, dispose of the residue at an appropriately permitted CA Class II or CA Class III facility.
The City does not adjust payment for the disposal of nonhazardous residue at CA Class II or Class III facility.
14-11.12F MEASUREMENT AND PAYMENT
Remove Yellow Thermoplastic/Painted Traffic Stripe shall be made at the contract lump sum (LS) in the Bid Schedule, which price shall constitute full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all of the work involved in removal, containment, storage, and disposal of yellow thermoplastic traffic stripe and pavement markers, as shown on the plans, as specified in the Standard Specifications and these special provisions, and as directed by the Engineer. No additional compensation will be allowed.
Full compensation for (1) work plan for the removal, containment, storage, and disposal of yellow thermoplastic and yellow painted traffic stripe and pavement marking hazardous waste residue, (2) analytical test results, (3) US EPA ID no. request, (4) receiving landfill documentation of proper disposal are included in the linear foot (LF) contract price paid for “Bid Item No. 3 - Remove Yellow Thermoplastic/Painted Traffic Stripe” and no separate payment will be made therefor.
Additional disposal costs for hazardous waste residue regulated under RCRA, as determined by test results, will be paid for as extra work as specified in Section 4-1.05, "Changes and Extra Work," of the Standard Specifications.
If analytical test results demonstrate that the residue is a non–hazardous waste and the Engineer agrees to disposal at a non–hazardous waste disposal facility, no cost adjustment will be made.
The City shall not make any payments on this contract until after the analytical test results are accepted and the hazardous or non-hazardous residue is collected and disposed of at a permitted disposal facility.
Agenda Item #7.4:
Page V-21 JUNE 2026
SECTION 15 EXISTING FACILITIES
15-1.01 GENERAL
Existing facilities disturbed by construction shall conform to the applicable provisions of Section 5-
1.36 of the Standard Specifications. Special care shall be taken by the Contractor to protect adjacent property, improvements, utilities facilities, lawns, landscape features and landscape irrigation and shrubbery from damage. Any such objects or improvements so damaged shall be replaced or restored in-kind by the Contractor, at the Contractor’s own expense, to the satisfaction of the Engineer.
Unless approved for re-use in the work by the Engineer, all items and materials removed shall be immediately hauled from the site of the work and properly disposed of at approved locations.
Contractor shall dispose of asphalt and concrete materials at an approved recycling site. 15-1.04 PAYMENT
Full compensation for conforming to the requirements of this Section shall be considered as included in the contract prices paid for various contract items of work under Section 37-3 “Slurry Seal,” which price shall include all work required and necessary to protect existing adjacent property, improvements, utility facilities, lawns, landscape features and landscape irrigation and shrubbery from damage.
Agenda Item #7.4:
Page V-22 JUNE 2026
SECTION 37-3 SLURRY SEALS
37-3.01 GENERAL
37-3.01A SLURRY SEAL
This section shall consist of furnishing and placing a Type II slurry seal onto existing asphalt cement (AC) pavement at locations and to the limits shown on the Figures contained herein in conformance with the requirements of Section 37-3, “Slurry Seals and Micro-Surfacing,” of the Revised Standard Specifications and the International Slurry Seal Association Publication A105, dated February 2010 (copies available from www.slurry.org), except where specified otherwise in these Special Provisions.
The completed slurry seal shall leave a homogeneous mat, adhere firmly to the prepared surface, and have a friction resistant surface texture throughout its service life.
Cracks from ¼-inch and less than 1-inch in width shall be sealed per Section 37-6, “Crack Treatments” of these Special Provisions.
37-3.01A(3) SUBMITTALS
At least 15 days before starting placement of a slurry seal or micro-surfacing, submit:
1. Asphaltic emulsion, polymer modified asphaltic emulsion, or micro-surfacing emulsion data as follows:
a. Supplier and Type/Grade of asphaltic emulsion;
b. Type of modifier polymer for polymer modified asphaltic emulsion or micro-surfacing emulsion; and
c. Copy of the specified test results for asphaltic emulsion, polymer modified asphaltic emulsion, or micro-surfacing emulsion.
2. Aggregate test results for the followings:
a. Gradation;
b. Los Angeles Rattler;
c. Percent of crushed particles;
d. Sand equivalent; and
e. Durability.
Submit a laboratory report of test results and the proposed mix design from an authorized laboratory.
The authorized laboratory must sign the laboratory report and mix design.
The report must include:
1. Test results used in the mix design compared with specification requirements
2. Proportions based on the dry weight of aggregate, including ranges, for:
a. Aggregate;
b. Water;
c. Additives;
d. Mineral filler; and
e. Slurry seal emulsion or micro-surfacing emulsion residual asphalt content.
Agenda Item #7.4:
Page V-23 JUNE 2026
3. Recommended changes to the proportions based on heating the mixture to 100 degrees F and mixing for 60 seconds, if atmospheric temperatures during application will be 90 degrees F or above, for:
a. Water;
b. Additives; and
c. Mineral filler.
4. Quantitative moisture effects on the aggregate's unit weight determined under ASTM C29M If the mix design consists of the same materials covered by a previous laboratory report, you may submit the previous laboratory report that must include material testing data performed within the previous 12 months for authorization.
If you change any of the materials in the mix design, submit a new mix design and laboratory report at least 10 days before starting slurry seal or micro-surfacing work.
Submit a certificate of compliance as specified for asphaltic emulsion in section 94-1.01C of the Standard Specifications with each shipment of asphaltic emulsion, polymer modified asphaltic emulsion or micro-surfacing emulsion.
The Contractor shall furnish to the Engineer weight or load slips verifying the quantities of aggregate and asphaltic emulsion. Slips shall be provided to the Engineer on the day of the delivery. 37-3.01A(4)(c) ACCEPTANCE
Slurry seal acceptance is based on:
1. Visual inspection for the following:
a. Uniform surface texture throughout work limits.
b. Marks in the surface:
i. Up to 4 marks in the completed slurry seal that are up to 1 inch wide and up to 6 inches long per 1,000 square feet of slurry seal placed, at discretion of the Engineer.
ii. No marks in the completed slurry seal that are over 1 inch wide or 6-inches long.
c. Excessive raveling consisting of the separation of the aggregate from the polymer modified asphaltic emulsion.
d. Bleeding consists of the occurrence of a film of asphalt material on the surface of the slurry seal or micro-surfacing.
e. Delaminating of slurry seal from the existing pavement f. Rutting or wash-boarding.
g. Any other visible defect in the quality of the work.
Agenda Item #7.4:
Page V-24 JUNE 2026
37-3.01B(2) AGGREGATE
Aggregate for slurry seal must comply with the gradations shown for Type II. Aggregate for slurry seal shall be black in color.
37-3.01C CONSTRUCTION
Construction requirements per Section 37-3.02C “Construction” of these Special Provisions. 37-3.02 SLURRY SEALS
37-3.02B MATERIALS
37-3.02B(3) POLYMER MODIFIED ASPHALTIC EMULSIONS
Asphalt emulsion shall be polymer modified asphalt emulsion, grade PMCQS1h cationic conforming with the requirements of Section 37-3.02B(3), “Polymer Modified Asphaltic Emulsions” and conform to the requirements in the Standard Specifications.
37-3.02C CONSTRUCTION
37-3.02C(1) GENERAL
Prior to applying the slurry seal, loose materials, oil spots, dirt, pavement striping and markers, vegetation and other objectionable material that may compromise the slurry seal to be placed shall be removed from the existing surface and the pavement structural integrity shall be restored. The pavement surface shall be cleaned by sweeping, flushing or other means necessary to remove all extraneous material. The Engineer shall approve all surface preparation prior to the application of slurry seal.
Use grinding or other approved methods for striping, pavement marking or pavement marker removal, including removal of existing double-sided yield to pedestrian object marker.
The Contractor shall inspect the roadways and pathways to be sealed and determine if overhanging branches will be disturbed by the slurry seal trucks. Any such branches shall be pruned by the Contractor at his expense prior to initiation of slurry seal placement. Prior to pruning any branches over 2 inches in diameter, the Contractor shall obtain approval from the City. Forty-eight (48) hour notice shall be provided for City review and comment.
All crack sealing work shall be completed at minimum of two days prior to application of slurry seal.
Prior to commencing the slurry seal operation, all surface utility covers including but not limited to survey monuments, manholes, water valves, etc. shall be protected by thoroughly covering the surface with an appropriate adhesive and oiled or plastic paper. No adhesive material shall be permitted to cover, seal or fill the joint between the frame and cover of the structure. Covers are to be uncovered and cleaned of slurry material by the end of the same work day. The Contractor shall take precautions to remove any slurry that may cover these appurtenances.
Protection and maintenance of the street surface to the condition required for proper slurry application shall be the sole responsibility of the Contractor and no additional expense will be allowed. The Agenda Item #7.4:
Page V-25 JUNE 2026
Contractor shall, at the direction of the City, repair and reseal all areas of the street which have not been sealed properly and completely or have been damaged by traffic. 37-3.02C(2) PROPORTIONING
The aggregate shall be proportioned using a belt feeder operated with an adjustable cutoff gate. The height of the gate opening shall be readily determined. The emulsion shall be proportioned a positive displacement pump. Any variable rate emulsion pump, if used, shall be equipped with a means to seal the adjusting unit in its calibrated condition.
The delivery rate of aggregate and emulsion per revolution of the aggregate feeder shall be calibrated at the appropriate gate settings for each mixer-spreader truck used on the project. The calibration shall demonstrate that delivery rates of dry aggregate and emulsion residue are within the recommended percentages stated in the laboratory mix design. The Contractor shall provide written calibration documentation for each application truck which has been performed within the last calendar year. The Contractor shall further provide a short calibration demonstrating gate settings and liquids are delivering job materials within the mix design recommended ranges. 37-3.02C(3) MIXING AND SPREADING EQUIPMENT
All equipment, tools, and machines used in the application of slurry seal shall be maintained in satisfactory working condition at all times. A minimum of two (2) slurry seal machines shall be on the job and in good operating condition at all times.
The slurry seal shall be mixed in a self-propelled mixing machine equipped with a continuous flow pug mill, capable of accurately delivering and automatically proportioning the aggregate, emulsified asphalt, mineral filler, water and admixtures to a double shafted, multi-blade pug mill mixer capable of minimum speeds of 200 revolutions per minute. Mix retention time in the pug mill shall be less than three (3) seconds. The mixing machine shall have sufficient storage capacity of aggregate, emulsified asphalt, mineral filler and water to maintain an adequate supply to the proportioning controls and make fifteen (15) tons of emulsion mix.
The mixing machine shall be equipped with hydraulic controls for proportioning the material by volume to the mix. Each material control device shall be calibrated, properly marked, pre-set and lockable.
The mixing machine shall be equipped with a water pressure and nozzle type spray bars to provide a water spray immediately ahead of the spreader box. The mixing machine shall be equipped with an approved fines feeder that provides a uniform, positive, accurately metered, pre-determined amount of the mineral filler at the same time and location that the aggregate is fed.
A burlap drag or other approved flexible drag or screed shall be attached to the rear of the spreader box.
A drag stiffened by hardened slurry is ineffective and is to be replaced immediately.
The slurry seal retention time in the pug mill shall be less than three seconds. No retention of mixed slurry seal shall be allowed within the pug mill by gate shut-off or other mechanical means. Transit mix trucks shall not be used.
37-3.02C(4) PLACEMENT
The slurry seal (mixture) shall be spread per the application range requirements of Type II slurry seal per Section 37-3.02C(4), “Placement,” of the Standard Specifications.
Agenda Item #7.4:
Page V-26 JUNE 2026
The slurry seal shall not be placed if either the temperature or the air temperature is below 55 degrees F and falling, but may be applied when both the air and pavement temperature is 45 degrees F or above and rising. The mixture shall not be applied if high relative humidity prolongs the curing beyond a reasonable time.
Longitudinal joints shall be butt jointed and should be located outside of the typical wheel paths, where possible.
Handwork shall be kept to a minimum. Areas which cannot be accessed by the mixing machine shall be surfaced using hand squeegees to provide complete and uniform coverage. Handwork shall exhibit the same finish as that applied by the spreader box and shall be completed prior to final surfacing. Hand tools shall be available to remove spillage. Ridges or bumps in the finished surface will not be permitted. The mixture shall be uniform and homogeneous after spreading on the existing surface and shall not show separation of the emulsion and aggregate after setting.
The Contractor shall exercise care to prevent slurry from being deposited on concrete surfaces. The Contractor shall remove slurry from surfaces not designated to be sealed each day. No additional streets shall be slurry sealed until this clean-up has been performed. The method of slurry removal shall be approved by the City. All streets to be slurry sealed shall be sealed from edge of pavement to edge of pavement. The slurry shall fully extend up to the lip of gutter but shall not overlap the gutter by more than 1 inch. Excess overlay shall be removed by methods that shall not damage the remaining slurry seal. Spreaders to be used for this operation shall meet the approval of the City.
The sites for stockpiling and batching materials shall be clean and free from objectionable materials and shall be located outside the road right-of-way. Arrangements for these sites shall be the responsibility of the Contractor. The Contractor shall provide to the City an executed written agreement with the property owner prior to commencing operations.
Any areas of chatter (wash boarding), poor coating, delaminating, segregation, uneven surfaces or poor joints shall be corrected. If any of these conditions are observed, the placement of slurry seal shall be stopped until corrections are made to the equipment to prevent such defects. At the Contractor’s expense, the Contractor shall be responsible for correcting any slurry placement that exhibits poor quality or workmanship, whether these conditions were observed during placement or after the slurry seal mix has cured.
No loads may begin to be applied after 2:00 PM.
The Contractor will only be permitted to continue with production if the following conditions are met:
a. The pavement has been properly cleaned initially and thereafter as necessary; b. Delivery tickets, samples and certificates of compliance are delivered to the Engineer by the end of the day (5:00 PM latest);
c. Complete daily production records are delivered to the Engineer by the end of the day (5:00 PM latest); and
d. Workmanship is acceptable including cleaning up of edges.
After completing slurry seal application, the Contractor shall perform complete sweepings of the project and adjacent streets where any materials have been tracked.
Agenda Item #7.4:
Page V-27 JUNE 2026
Within 4 hours after placement, slurry seals must be set enough to allow traffic without pilot cars.
Protect slurry seals from damage until it has set and will not adhere or be picked up by vehicle tires.
Slurry seals must not exhibit distress from traffic such as bleeding, raveling, separation or other distresses.
37-3.02D PAYMENT
Slurry Seal - Streets shall be paid for at the contract unit price per square foot (SF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment, water pollution prevention program, striping removal, pavement marking removal and pavement markers removal, with exception to yellow thermoplastic or paint, crack sealing, surface cleaning, protection of existing utility facilities, placing of slurry seal, protecting the slurry seal, and other incidentals for completing the work required for the installation of the slurry seal and all other related work per the Contract Documents, including all work required for preparing the water pollution control program, all work required for the installation and maintenance of erosion control measures and best management practices (BMPs) and shall consist of, but not be limited to, constructing such facilities and taking such measures as are necessary to prevent, control and abate water, mud, sediment and erosion damage to public and private property as a result of the construction of this project and per the Contract documents and Water Pollution Control Program, complete in place to the limits as shown on the Figures and as contained herein.
Agenda Item #7.4:
Page V-28 JUNE 2026
SECTION 37-6 CRACK TREATMENT
37-6.01 GENERAL
Work to be performed under this Section covers all labor, materials, tools, equipment, transportation, and incidentals necessary to crack seal existing pavements. The work includes crack sealing all cracks 1/4-inch to 1-inch wide with a hot applied rubberized crack sealant prior to placing slurry seal. Treat cracks under Section 37-6 of the Standard Specifications. 37-6.01C SUBMITTALS
Modified rubberized asphalt crack sealant shall be Type 3. 37-6.02 MATERIALS
Modified rubberized asphalt crack sealant shall be Type 3.
Sand applied to tacky crack treatment must be clean, free of clay and comply with the gradation indicated in Section 37-6.02C Sand Gradation.
37-6.03 CONSTRUCTION
Seven days prior to crack cleaning, apply a non-persistent herbicide to the cracks. Herbicide shall be applied to all cracks regardless of the crack size. Herbicide will be applied to the joint where the lip of gutter meets the asphalt roadway section. Herbicide and vegetation removal shall be completed on all roadway sections. Glyphosate based herbicide is not allowed to be used on City of Sonoma property and projects.
Apply crack treatment with a nozzle inserted into the crack. Fill the crack recessed ¼-inch. Fill the crack overband not more than 3-inches wide. If after 2 days the crack treatment is more than 1/4 inch below the specified level, the sealant fails, or the crack re-opens, re-treat the crack.
Cracks must be clean and dry before treating. Before treating, blast cracks with oil-free compressed air at a pressure of at least 90 psi.
If the pavement temperature is below 40 degrees F or if there is evidence of moisture in the crack, use a hot air lance immediately before applying crack treatment. The hot air lance must not apply flame directly on the pavement.
Heat and apply hot-applied crack treatment material under with the manufacturer's instructions.
Apply cold-applied crack treatment material with a distributor kettle, a piston, or a diaphragm barrel pump that can deliver from 50 to 75 psi. The application line must have a pressure gauge and a filter.
The pressure in the application line must not exceed 20 psi. The pressure gauge must have a regulator.
Use a high-pressure hose with a 1/2-inch NPT swivel connection and a dispensing wand.
Apply crack treatment with a nozzle inserted into the crack. Fill the crack flush. If after 2 days the crack treatment is more than 1/4 inch below the specified level, the sealant fails, or the crack reopens, re-treat the crack. Immediately remove crack treatment material that is spilled or deposited on the pavement surface.
Before opening to traffic, apply sand or the manufacturer's recommended detackifying agent to tacky crack treatment material on the traveled way.
Agenda Item #7.4:
Page V-29 JUNE 2026
Sweep up excess sand before opening to traffic.
37-6.04 PAYMENT
Full compensation for conforming to the requirements of this Section shall be considered as included in the contract prices paid for various contract items of work under Section 37-3 “Slurry Seal,” which price shall include all work required and necessary to prepare and seal cracks prior to application of slurry seal.
Agenda Item #7.4:
Page V-30 JUNE 2026
SECTION 84 MARKINGS
84-1.01 GENERAL
Work to be performed under this Section covers all labor, materials, tools, equipment, transportation, and incidentals necessary to remove and replace traffic stripes and pavement markings in compliance with Section 84 “Markings” of the Standard Specifications.
Markings must comply with the California Manual on Uniform Traffic Control Devices. 84-1.03 CONSTRUCTION
The Contractor shall locate and document all existing striping, pavement markings and pavement markers and is responsible for replacing all removed striping, pavement markings and pavement markers in the same location and/or line after slurry seal work is complete. The timing of striping, pavement marking and pavement marker removal shall coincide with the crack seal and slurry seal schedule so that the striping is restored as soon as practicable and no later than seven (7) calendar days after removal. If removed striping, pavement markings and pavement markers will not be restored within two (2) calendar days of removal, the Contractor shall place temporary markings until slurry seal work commences. The Contractor shall take all extra precautions required when removing striping, pavement markings and pavement markers, including use of temporary traffic control signs to alert motorists of the temporary changed conditions while striping is removed from the pavement surface.
The Contractor shall “cat-track” all striping and pavement markings for review by the Engineer prior to placement of final striping and pavement markings.
84-2.01C SUBMITTALS
For each lot or batch of thermoplastic, paint, and glass beads, submit:
1. Certificate of compliance, including the product name, lot or batch number, and manufacture date;
2. Materials Engineering and Testing Services (METS) notification letter stating that the material is authorized for use; and
3. Safety Data Sheet (SDS).
For glass beads used in drop-on applications and in thermoplastic formulations, submit a certificate of compliance and test results for each lot of beads specifying the EPA test methods used and tracing the lot to the specific test sample. The testing for lead and arsenic content must be performed by an independent testing laboratory.
Submit retroreflectivity readings for traffic stripes and pavement markings at locations with deficient retroreflectivity determined by the Engineer.
84-2.02 MATERIALS
Traffic stripes and pavement markings must be thermoplastic meeting requirements of Section 84-2.02 of the Standard Specifications.
Agenda Item #7.4:
Page V-31 JUNE 2026
84-2.04 PAYMENT
Pavement Markings shall be paid at the contact unit price per square foot (SF), which price shall include full compensation for furnishing all plant, labor, materials, tools, and equipment for work described in this section shall constitute full compensation for the completion of all such work as required per the Contract Documents.
Miscellaneous 4-inch White Stripe shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping including 4-inch white solid line where required for striped loading zones, or similar, including surface preparation, temporary markings and striping and all other related work per the Contract Documents.
No Passing Zones – Two Direction – Detail 22 shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping and Type D two-way yellow retroreflective pavement markers per Caltrans Standard Plan A20A Detail 22 throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Right Edgelines – Detail 27B shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping per Caltrans Standard Plan A20B Detail 27B throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Median Islands – Detail 29 shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping and Type D yellow two-way retroreflective pavement makers per Caltrans Standard Plans A20B Detail 29 throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Two-Way Left Turn Lane – Detail 32 shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping and Type D yellow two-way retroreflective pavement makers per Caltrans Standard Plans A20B Detail 32 throughout the project Agenda Item #7.4:
Page V-32 JUNE 2026
limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Channelizing Line – Detail 38 shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping and Type G one-way clear retroreflective pavement markers per Caltrans Standard Plan A20D Detail 38 throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Bike Lane Line – Detail 39 shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping per Caltrans Standard Plan A20D Detail 39 throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Bike Lane Intersection Line – Detail 39A shall be paid at the contact unit price per linear foot (LF), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of thermoplastic pavement striping per Caltrans Standard Plan A20D Detail 39A throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents. Measurement by the linear foot shall include the full stripe section as shown in the Caltrans Standard Plan, regardless of the number of individual stripes comprising the detail or the number of striping passes required.
Pavement Markers (Two-Way Blue Retroreflective) shall be paid at the contact unit price per each (EA), which price shall include full compensation for furnishing all plant, labor, materials, tools, equipment and incidentals necessary for documenting existing striping for replacement of slurry seal and for the complete layout and installation of blue two-way retroreflective pavement markers throughout the project limits, including surface preparation, temporary markings and striping and all other related work per the Contract Documents.
Full compensation for conforming to other requirements, not specifically measured and paid for as part of any one bid item, and of this section shall be considered as incidental to the work and included in the prices paid for the various items of work and no additional compensation will be allowed nor separate pavement made therefore.
Agenda Item #7.4:
Appendix A
Figure 1, Location and Limits of Slurry Seal
Agenda Item #7.4:
FIGURE 1
0 500 1,000 1,500 2,000
Feet
Project No.
Revision No. 0000
12687354
Date May 2026
Map Projection: Lambert Conformal Conic
Horizontal Datum: NAD 1983 2011
Grid: NAD 1983 2011 StatePlane California II FIPS 0402 Ft US Paper Size ANSI A
o \\ghdnet\ghd\US\Azure\EastUS\12687354\GIS\Maps\Working\12687354_SonomaSlurryPavement_2026.aprx - Data source: Parcels: . Created by: ethompson3 12687354_002_FIG1_SlurrySealLimits
Print date: 12 May 2026 - 13:18
City of Sonoma
CIP T-3, 2026 Citywide Slurry
Seal Project No. 2602
Location and Limits of Slurry Seal
Legend
Parcels Slurry Seal Limits
Broadway (Hwy 12)
W. Napa Street (Hwy 12)
Napa RoadNapa Road
Leveroni Road
E. Napa Street
Chase Street
Bettencourt Street
W. Spain Street E. Spain Street
Fifth Street West
Fifth Street East
Plaza
Park
Third Street West
Church Street
Clay Street
Oak Lane
Fourth Street East
Bragg Street
Agenda Item #7.4:
City of Sonoma
Agenda Item Summary
Meeting: City Council - 15 Jul 2026
Department
Parks & Recreation Department
Staff Contact
Dave Jahns, Parks & Recreation Director
Agenda Item Title
Establishment of an Ad Hoc Advisory Committee to Support the Development of a Comprehensive Parks and Recreation Planning Effort and Appointing Mayor Ron Wellander and Councilmember John Gurney as the Committee Members
Summary
Background
The City of Sonoma's parks and public spaces are part of diverse system that includes neighborhood parks, community gathering spaces, a historic plaza, open space preserves, trails, recreation facilities, and public landscapes that contribute significantly to the community's quality of life. Recreation programming within Sonoma is delivered through a collaborative network of nonprofit organizations, schools, community groups, sports organizations, arts and cultural organizations, and private recreation providers. While there have been several planning efforts providing important guidance over the years, the City currently does not have a centralized and comprehensive long-range plan to establish priorities, coordinate future investments, evaluate recreation needs, and identify sustainable funding strategies for the park system and accompanying programs.
With the formation of a new Parks and Recreation Department in 2025, and as part of the 2026- 27 budget process, the City Council has identified preparation of a comprehensive Parks and Recreation Plan ("Plan") as a priority initiative to establish a long-term vision for Sonoma's parks, recreation facilities, trails, urban forest, open spaces, and recreation services.
Discussion
A central component of the planning process will be meaningful community engagement to ensure the Plan reflects the needs, priorities, and aspirations of Sonoma's diverse community.
To streamline this process, staff recommends establishing a temporary Ad Hoc Committee, consisting of two City Council members, Mayor Ron Wellander and Councilmember John Gurney, to provide efficient communication between the City Council, staff, and the consultant team throughout the planning process. The committee will serve in an advisory capacity by reviewing project milestones, providing feedback to staff, and assisting in identifying community priorities. As the planning process unfold, staff also recommends establishment of a community-based Steering Committee representing a broad cross-section of stakeholders to provide ongoing input throughout the planning process.
Formal Plan recommendations will remain with the Parks, Recreation and Open Space Commission and policy direction, funding allocation, and Plan adoption will remain with the City Council during publicly noticed meetings.
If approved, the Ad Hoc committee would be established pursuant to the accompanying resolution and remain in effect until the Plan is approved and adopted by City Council.
Recommended Council Action
Agenda Item #7.5:
Staff recommends that the City Council adopt a resolution establishing a Parks and Recreation Plan Ad Hoc Committee
Alternative Actions
The council may elect to not create an Ad Hoc Committee. City Council discussions regarding the Plan would be brought forward at regularly scheduled meetings with the full council.
Financial Impact
Creation of the Ad Hoc Committee has no independent fiscal impact. Funding to complete the Plan has been allocated as part of approved 2026-27 operating budget.
Environmental Review Status
Environmental Impact Report
Negative Declaration
Exempt
Not Applicable
Approved/Certified
No Action Required
Action Requested
Attachments
Resolution
Agenda Item #7.5:
City of Sonoma
RESOLUTION # ___-2026
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SONOMA
ESTABLISHING AN AD HOC ADVISORY COMMITTEE TO SUPPORT
DEVELOPMENT OF THE CITY OF SONOMA PARKS AND RECREATION PLAN WHEREAS, the City Council has allocated funding to complete a comprehensive Parks and Recreation Plan (“Plan”) to guide future investment, maintenance, recreation services, and capital improvements; and
WHEREAS, development of the Plan will require coordination among City staff, consultants, the Parks, Recreation, and Open Space Commission, community stakeholders, and the City Council; and
WHEREAS, the City Council finds that creation of a temporary Ad Hoc Committee (“Committee”) consisting solely of less than a quorum of the Council will facilitate communication during preparation of the Plan while preserving all legislative authority with the full City Council;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Sonoma as follows:
Section 1. Establishment. The City Council establishes a temporary Ad Hoc Committee comprised of Mayor Ron Wellander and Councilmember John Gurney.
Section 2. Purpose. The Committee shall advise staff regarding project scope, consultant coordination, public engagement, review of draft planning documents, and other matters related to preparation of the Plan.
Section 3. Authority. The Committee serves solely in an advisory capacity and shall provide recommendations to staff and shall have no authority to establish policy, approve expenditures, bind the City, or act on behalf of the full City Council.
Section 4. Staff Support. The Parks and Recreation Director, or designee, shall provide administrative support to the Ad Hoc Committee. The Committee shall have such other administrative support as directed by the City Manager.
Section 5. Sunset. The Committee shall automatically dissolve upon final City Council action to adopt, disapprove, or otherwise take final action on the Plan unless earlier dissolved by the City Council.
Section 6. Brown Act. As a temporary, ad hoc advisory committee comprised of less than a quorum of the City Council, the Committee may, but need not, comply with the Brown Act as authorized by Government Code section 54952, subdivision (b).
Agenda Item #7.5:
Section 7. Effective Date. This Resolution shall take effect immediately upon adoption.
PASSED AND ADOPTED by the City Council of the City of Sonoma, on July 15, 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
__________________________________
Ron Wellander, Mayor
ATTEST:
___________________________________
Rebekah Barr, MMC, City Clerk
Agenda Item #7.5:
City of Sonoma
Agenda Item Summary
Meeting: City Council - 15 Jul 2026
Department
Parks & Recreation Department
Staff Contact
Dave Jahns, Parks & Recreation Director
Agenda Item Title
Adopt a Resolution Authorizing the Execution of a Second Amendment to the Restated Lease with Sonoma Valley Field of Dreams and Accepting Public Facility Site Improvements Summary
Background
The Field of Dreams facility is a City-owned recreational asset that serves youth sports organizations, community groups, special events, and recreational programming throughout Sonoma Valley. The property is operated and maintained by Sonoma Valley Field of Dreams pursuant to a long-term lease agreement with the City.
On August 20, 2025, the City Council authorized continued use of the Field of Dreams site for the 2026 season and provided direction to staff to explore alternatives that could reduce neighborhood impacts while maintaining the cultural and economic benefits associated with the performances. Through a collaborative effort involving Sonoma Valley Field of Dreams, Transcendence Theatre Company, City staff, engineers, contractors, and community partners, an alternative site configuration was developed that relocated the performance area and reoriented the stage and audience layout.
While the project was initiated to accommodate the revised event layout, the resulting improvements provide permanent benefits to the broader community and enhance the overall functionality of the Field of Dreams facility. Implementation of the revised layout required a series of site improvements, including grading, drainage infrastructure, accessibility enhancements, pathway improvements, installation of all-weather surfacing materials, and construction of a bio-retention basin.
Project Improvements
The completed improvements include:
Approximately 15,000 square feet of site grading and drainage improvements. Installation of approximately 115 linear feet of new storm drain infrastructure and related drainage facilities.
Construction of a bio-retention basin to improve stormwater management and water quality.
Installation of approximately 10,000 square feet of all-weather surfacing materials to improve year-round access and usability.
Pathway improvements and site circulation enhancements. Installation of an ADA-accessible parking space and improved accessible routes. Reconfiguration of portions of the facility to improve operational flexibility and event functionality.
Agenda Item #7.6:
These improvements address longstanding drainage and accessibility challenges, improve public access, enhance maintenance operations, and increase the year-round usability of the facility for youth sports, recreation programs, community gatherings, and special events. The improvements will remain public assets outside of current and future use by Transcendence Theatre Company.
Lease Amendment
The proposed Second Amendment to the Restated Lease authorizes the City to formally accept ownership of the completed improvements upon inspection and verification that the work has been completed in accordance with approved plans and applicable standards.
Consistent with the City’s 2009 First Amendment to the Restated Lease, accepted improvements would become part of the City’s real property while Sonoma Valley Field of Dreams would remain responsible for ongoing maintenance and operation of the facility pursuant to the Lease.
Financial Impact
The total estimated value of the site improvement project is approximately $175,000. Through volunteer labor, donated equipment, discounted services, and contributions from community partners, the project leveraged substantial non-City investment into a publicly owned recreational facility.
The City's contribution of $40,000 towards the completed public improvements supports general site improvements including accessibility, pathway enhancements, and addressing drainage issues. The funding is allocated in the adopted 2025-26 Parks Operations budget and will not require additional budget appropriations. Staff believes the contribution represents an appropriate investment in improvements to a City-owned recreational facility that will benefit the broader community for years to come.
Recommended Council Action
Adopt a resolution authorizing the City Manager to execute a Second Amendment to the Restated Lease with Sonoma Valley Field of Dreams, accepting the facility site improvements upon completion and inspection, and finding the action exempt from CEQA.
Alternative Actions
1. Request additional information and continue the item to a future meeting.
2. Decline to approve the lease amendment and provide alternative direction to staff.
Financial Impact
Acceptance of the site improvements authorizes a City contribution of $40,000 consisting of funds allocated in the City’s adopted FY 2025-26 Parks Operations budget. No additional budgetary action is required.
Environmental Review Status
Environmental Impact Report
Negative Declaration
Approved/Certified
No Action Required
Agenda Item #7.6:
Exempt
Not Applicable
Action Requested
Attachments
Resolution - Field of Dreams Lease Amendment
Second Amendment to Restated Lease_07.15.26
Field of Dreams Improvement - As-Builts
2009-9-18 SV Field of Dreams First Amendment (284968.1) 2007-4-17 Sonoma Valley (SV) Field of Dreams Restated Lease (284967.1) Agenda Item #7.6:
CITY OF SONOMA
RESOLUTION # ____-2026
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SONOMA APPROVING A
SECOND AMENDMENT TO THE RESTATED LEASE WITH SONOMA VALLEY FIELD OF
DREAMS, ACCEPTING FACILITY SITE IMPROVEMENTS, AND FINDING THE ACTION
EXEMPT FROM CEQA
WHEREAS, the City of Sonoma (“City”) owns the real property commonly known as the Sonoma Valley Field of Dreams facility located on First Street West; and WHEREAS, Sonoma Valley Field of Dreams (“SVFOD”) operates and maintains the facility pursuant to a Restated Lease dated April 17, 2007, as amended; and WHEREAS, during 2025 and 2026, the City, SVFOD, Transcendence Theatre Company, and numerous community partners collaborated on a series of site improvements intended to improve functionality, accessibility, drainage, circulation, and overall use of the facility; and WHEREAS, the improvements provide substantial public benefits by improving drainage and stormwater management, enhancing accessibility, increasing public safety, improving maintenance access, and supporting year-round recreational and community use of the facility; and
WHEREAS, the improvements will become permanent public improvements located on Cityowned property and will continue to benefit the community regardless of future event programming; and
WHEREAS, the estimated value of the improvements is approximately $175,000, including substantial contributions of volunteer labor, donated equipment, materials, and community support; and
WHEREAS, the City’s contribution totaling $40,000 toward the completed improvements serves a valid municipal purpose and represents an appropriate investment in a City-owned recreational facility; and
WHEREAS, City and SVFOD desire to enter into a Second Amendment to the Restated Lease providing for City’s acceptance of the improvements and establishing ownership and maintenance responsibilities; and
WHEREAS, the City Council has reviewed the proposed Second Amendment to the Restated Lease and all related materials;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Sonoma hereby:
Section 1. Recitals. The foregoing recitals are true and correct and are incorporated herein by this reference.
Section 2. Public Benefit Findings. The City Council finds that:
A. The improvements provide significant public benefits through enhanced drainage, accessibility, public safety, environmental performance, maintenance access, and recreational opportunities;
B. The improvements constitute permanent improvements to a City-owned public facility; Agenda Item #7.6:
C. The City’s contribution of $40,000 represents a reasonable investment toward site improvements; and
D. The improvements further the City’s goals of maintaining and enhancing public facilities, recreational opportunities, and community-serving infrastructure.
Section 3. Approval of Second Amendment. The City Council approves the Second Amendment to the Restated Lease between the City of Sonoma and Sonoma Valley Field of Dreams in substantially the form presented and authorizes the City Manager to execute the agreement and any related documents necessary to implement its provisions.
Section 6. Acceptance of Improvements. Upon verification by the City that the work has been completed in substantial conformance with approved plans and applicable standards, the City shall accept the improvements as public assets of the City.
Section 7. Maintenance Responsibilities. Following acceptance, Sonoma Valley Field of Dreams shall remain responsible for ongoing maintenance, repair, and operation of the improvements in accordance with the Restated Lease, as amended.
Section 8. CEQA. The City Council finds that the proposed action is exempt from the California Environmental Quality Act pursuant to CEQA Guidelines Sections 15301 and 15304 and, alternatively, pursuant to Section 15061(b)(3), as it can be seen with certainty that there is no possibility the action may have a significant effect on the environment.
Section 9. Effective Date. This Resolution shall take effect immediately upon adoption.
PASSED AND ADOPTED by the City Council of the City of Sonoma on July 15, 2026, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
_________________________________
Ron Wellander, Mayor
ATTEST:
_________________________________
Rebekah Barr, City Clerk
Agenda Item #7.6:
449436.1
SECOND AMENDMENT TO
RESTATED LEASE
THIS SECOND AMENDMENT TO RESTATED LEASE (“Second Amendment”), dated as of ____________, 2026 (“Effective Date”), is entered into between the CITY OF SONOMA, a California municipal corporation (“City” or “Lessor”), and SONOMA VALLEY FIELD OF DREAMS, a California nonprofit corporation (“Lessee”).
RECITALS
A. Lessor and Lessee are parties to that certain Restated Lease entered into on April 17, 2007 (“Restated Lease”) for that certain real property located on First Street West and commonly known as the Sonoma Valley Field of Dreams facility (“Premises”).
B. Lessor and Lessee entered into a First Amendment to the Restated Lease effective September 18, 2009 (“First Amendment”) to provide for Lessor’s acquisition and acceptance, and Lessee’s ongoing operation and maintenance, of certain storm drainage facilities on the Premises, as detailed in the First Amendment.
C. In 2026, Lessee caused the construction of certain grading, drainage, stormwater management, accessibility, pathway, paving, bio-retention, ADA access, and related site improvements on the Premises (“Improvements”). The Improvements are described in the official records of the City and applicable project plans, which records are incorporated herein and made a part hereof for the purpose of describing the location and extent of the Improvements.
D. Lessor and Lessee desire to enter into this Second Amendment to provide for Lessor’s acquisition and acceptance, and Lessee’s ongoing operation and maintenance, of the Improvements.
AGREEMENT
NOW, THEREFORE, in consideration of the foregoing recitals and the mutual covenants contained herein, the parties hereto agree as follows:
1. Lessor’s Acceptance of Improvements; Ownership. The City has determined that the installation of the Improvements was performed in accordance with the applicable City standards and guidelines. Lessor hereby accepts the Improvements installed on the Premises by Lessee. The Improvements shall be considered part of the real property of the Premises and shall remain the property of Lessor in accordance with Section 12 of the Restated Lease.
2. Payment by Lessor to Lessee for Acquisition of the Improvements. Within thirty (30) days following the full execution of this Second Amendment by the parties, Lessor shall pay Lessee the sum of Forty Thousand Dollars ($40,000) as full consideration for Lessor’s acquisition of the Improvements.
Agenda Item #7.6:
3. Operation and Maintenance of Improvements. With the exception of the accessible parking stall and accompanying loading zone improvements noted as completed “By Others” in the official record, Lessee shall be responsible for all ongoing operation and maintenance of the Improvements during the term of the Lease in accordance with Section 13 of the Restated Lease and as may otherwise be directed by Lessor. Lessee shall be solely responsible for determining and effectuating compliance with local, state, and federal law concerning the maintenance of the Improvements, including but not limited to, if applicable, state prevailing wage laws and regulations. City makes no representation as to the applicability or nonapplicability of any of local, state, or federal prevailing wage laws or regulations to the maintenance of the Improvements or any part thereof. Lessee hereby expressly acknowledges and agrees that the City has not previously affirmatively represented to Lessee that maintenance of the Improvements is not a “public work,” as defined in California Labor Code Section 1720.
Lessee shall indemnify, defend and hold harmless the City and its officers, employees, contractors and agents, with counsel reasonably acceptable to City, from and against any and all loss, liability, damage, claim, cost, expense, “increased costs” as that term is defined in California Labor Code Section 1781, court and litigation costs, fees of expert witnesses, and reasonable attorneys’ fees, which, in connection with the maintenance of the Improvements, results or arises in any way from any noncompliance by Lessee of any applicable local, state, or federal law, including, without limitation, any applicable local, state, or federal prevailing wage law or regulation. It is agreed by the parties hereto that in connection with the maintenance of the Improvements Lessee shall bear all risks of the applicability of prevailing wage laws and regulations and compliance or noncompliance thereof. The foregoing indemnity shall survive the expiration or earlier termination of the Restated Lease as amended by the First Amendment and this Second Amendment.
4. Ratification. Except as amended hereby, the Restated Lease and First Amendment remain in full force and effect.
5. Counterparts. This Second Amendment may be executed in counterparts, each of which shall be deemed to be an original, but which together shall constitute a single document.
NOW THEREFORE, Lessor and Lessee have entered into this Second Amendment as of the Effective Date:
LESSOR
CITY OF SONOMA, a municipal corporation
By: ___________________________
Name: _________________________
Title: City Manager
449436.1
Agenda Item #7.6:
449436.1
LESSEE
SONOMA VALLEY FIELD OF DREAMS, a California nonprofit corporation By: ___________________________
Name: _________________________
Title: Board President
Agenda Item #7.6:
CHAD S. MOLL DATE RCE 79721
MDC
MOLL DESIGN +
CONSULTING
PO BOX 9545
SANTA ROSA, CA 95405
(707) 481-9472
[email protected] FIELDS OF DREAMS - SITE IMPROVEMENTS 151 1ST STREET WEST, SONOMA, CA
APN 018-071-008
FIELD OF DREAMS - SITE IMPROVEMENTS
NOT TO SCALE N
VICINITY MAP
SITE
A PERFORM EROSION PREVENTION AND SEDIMENT CONTROL IN ACCORDANCE WITH TITLE 13.32 AND 14.20 OF THE SONOMA CITY MUNICIPAL CODE (SCMC).
B. THE APPROVED PLANS SHALL CONFORM TO THE CITY'S EROSION PREVENTION AND SEDIMENT
CONTROL BEST MANAGEMENT PRACTICES (BMP'S) AS WRITTEN IN THIS DOCUMENT, THE
CONSTRUCTION SITE STORMWATER POLLUTION PREVENTION HANDOUT (ATTACHED BELOW), AND
SHOULD MEET THE DESIGN CRITERIA SET FORTH IN THE MOST RECENT VERSION OF THE CALIFORNIA STORMWATER QUALITY ASSOCIATION BMP HANDBOOK FOR CONSTRUCTION.
C. THE PROPERTY OWNER IS RESPONSIBLE FOR PREVENTING STORMWATER POLLUTION GENERATED FROM THE CONSTRUCTION SITE YEAR-ROUND. WORK SITES WITH INADEQUATE
EROSION PREVENTION AND/OR SEDIMENT CONTROL MAY BE SUBJECT TO A STOP WORK ORDER AND/OR ADDITIONAL INSPECTION FEES TO VERIFY COMPLIANCE WITH THE SCMC.
D. THE MOST PROTECTIVE SHALL APPLY IF DISCREPANCIES OCCUR BETWEEN THESE NOTES, MATERIAL REFERENCED ON THE APPROVED PLANS, OR MANUFACTURER'S RECOMMENDATIONS.
E. AT ALL TIMES, THE PROPERTY OWNER IS RESPONSIBLE FOR OBTAINING AND COMPLYING WITH
THE STATE OF CALIFORNIA NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES)
GENERAL PERMIT FOR STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION AND LAND
DISTURBING ACTIVITIES SUCH AS CLEARING, GRADING, EXCAVATION, STOCKPILING, AND RECONSTRUCTION OF EXISTING FACILITIES INVOLVING REMOVAL AND REPLACEMENT.
F. THE PROPERTY OWNER MUST IMPLEMENT AN EFFECTIVE COMBINATION OF EROSION
PREVENTION AND SEDIMENT CONTROL ON ALL DISTURBED AREAS DURING THE RAINY SEASON (OCTOBER I - APRIL 30). GRADING AND DRAINAGE IMPROVEMENT SHALL BE PERMITTED DURING
THE RAINY SEASON ONLY WHEN ONSITE SOIL CONDITIONS PERMIT THE WORK TO BE PERFORMED IN COMPLIANCE WITH THE SCMC.
G. DURING THE RAINY SEASON (OCTOBER I-APRIL 30), STORMWATER BMPS REFERENCED OR
DETAILED IN THE EROSION AND SEDIMENT CONTROL PLAN FOR YOUR PROJECT AND/OR SONOMA
CITY'S SINGLE FAMILY HOME BMPS GUIDE DRAWN FROM STATE LEADERS SUCH AS CALTRANS
AND CASQA SHALL BE ALWAYS IMPLEMENTED AND FUNCTIONAL ON THE SITE, AND THE AREA OF ERODIBLE LAND EXPOSED AT ANY ONE TIME DURING THE WORK SHALL NOT EXCEED ONE ACRE.
H. DURING THE NON-RAINY SEASON, ON ANY DAY WHEN THE NATIONAL WEATHER SERVICE FORECAST IS A CHANCE OF RAIN OF 0.5 INCHES WITHIN THE NEXT 24 HOURS, STORMWATER BMPS
REFERENCED OR DETAILED IN SONOMA'S BMPS GUIDE SHALL BE IMPLEMENTED AND FUNCTIONAL ON THE SITE TO PREVENT SOIL AND OTHER POLLUTANT DISCHARGES. AT ALL OTHER TIMES, BMPS SHOULD BE STORED ON-SITE IN PREPARATION FOR INSTALLATION PRIOR TO RAIN EVENTS.
I. EROSION PREVENTION AND SEDIMENT CONTROL BMPS SHALL BE INSPECTED BY THE PROPERTY
OWNER BEFORE FORECASTED STORM EVENTS AND AFTER STORM EVENTS TO ENSURE BMPS ARE FUNCTIONING PROPERLY. EROSION PREVENTION AND SEDIMENT CONTROL BMPS THAT HAVE FAILED OR ARE NO LONGER EFFECTIVE SHALL BE PROMPTLY REPLACED. EROSION PREVENTION AND SEDIMENT CONTROL BMPS SHALL BE MAINTAINED UNTIL DISTURBED AREAS ARE STABILIZED.
J. THE LIMITS OF GRADING SHALL BE DEFINED AND MARKED ON SITE TO PREVENT DAMAGE TO SURROUNDING TREES AND OTHER VEGETATION. PRESERVATION OF EXISTING VEGETATION SHALL OCCUR TO THE MAXIMUM EXTENT PRACTICABLE. ANY EXISTING VEGETATION WITHIN THE
LIMITS OF GRADING THAT IS TO REMAIN UNDISTURBED BY THE WORK SHALL BE IDENTIFIED AND PROTECTED FROM DAMAGE BY MARKING, FENCING, OR OTHER MEASURES.
K. CHANGES TO THE EROSION PREVENTION AND SEDIMENT CONTROL PLAN MAY BE MADE TO
RESPOND TO FIELD CONDITIONS IF THE ALTERNATIVE BMPS ARE EQUIVALENT OR MORE PROTECTIVE THAN THE BMPS SHOWN ON THE APPROVED PLANS. ALTERNATIVE BMPS ARE
SUBJECT TO REVIEW AND APPROVAL BY THE ENVIRONMENTAL COMPLIANCE ANALYST, OR, IF DELEGATED, OTHER SONOMA CITY PUBLIC WORKS DEPARTMENT STAFF.
L. DISCHARGES OF POTENTIAL POLLUTANTS FROM CONSTRUCTION SITES SHALL BE PREVENTED USING SOURCE CONTROLS TO THE MAXIMUM EXTENT PRACTICABLE. POTENTIAL POLLUTANTS
INCLUDE BUT ARE NOT LIMITED TO SEDIMENT, TRASH, NUTRIENTS, PATHOGENS, PETROLEUM
HYDROCARBONS, METALS, CONCRETE, CEMENT, ASPHALT, LIME, PAINT, STAINS, GLUES, WOOD
PRODUCTS, PESTICIDES, HERBICIDES, CHEMICALS, HAZARDOUS WASTE, SANITARY WASTE, VEHICLE, OR EQUIPMENT WASH WATER, AND CHLORINATED WATER.
1. APPROVAL OF PLANS DOES NOT RELIEVE THE OWNER OF THE RESPONSIBILITY FOR THE CORRECTION OF MISTAKES, ERRORS OR OMISSIONS CONTAINED THEREIN. IF, DURING THE
COURSE OF CONSTRUCTION OF THE IMPROVEMENTS, PUBLIC INTEREST REQUIRES A
MODIFICATION OF OR A DEPARTURE FROM THE CITY STANDARDS OR THESE IMPROVEMENT
PLANS, THE CITY ENGINEER SHALL HAVE THE AUTHORITY TO REQUIRE SUCH MODIFICATION OR DEPARTURE AND TO SPECIFY THE MANNER IN WHICH THE SAME IS TO BE MADE.
2. ALL WORK AND MATERIALS SHALL COMPLY WITH THE CURRENT CITY OF SONOMA STANDARD PLANS UNLESS NOTED OTHERWISE AND NOTIFY THE CITY FOR INSPECTIONS.
A. PRIOR TO ANY WORK ON CITY OR STATE RIGHT OF WAY COMMENCES, THE CONTRACTOR
SHALL REQUEST AND HOLD A PRE-CONSTRUCTION MEETING WITH CITY AND CALTRANS PERSONNEL. THE CITY REQUIRES A MINIMUM 48-HOUR NOTICE TO ATTEND THE MEETING.
CALL (707) 938-3332 TO REQUEST A MEETING.
B. CONTRACTOR SHALL GIVE THE CITY PUBLIC WORKS DEPARTMENT 24 HOURS NOTICE BEFORE STARTING WORK AND TO REQUEST INSPECTIONS. CALL (707) 938-3332 TO SCHEDULE.
C. A CITY OF SONOMA ENCROACHMENT PERMIT SHALL BE OBTAINED PRIOR TO ANY WORK WITHIN PUBLIC RIGHT-OF-WAY.
3. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO OBTAIN ALL PERMITS NECESSARY TO
PERFORM THE IMPROVEMENTS IN THESE PLANS FROM THE APPROPRIATE AGENCIES AND TO COMPLY WITH THE AGENCIES' REQUIREMENTS. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE NATIONAL, STATE AND LOCAL LAWS.
4. HAZARDOUS MATERIALS: UPON DISCOVERY OF HAZARDOUS MATERIAL, THE CONTRACTOR
SHALL STOP THE WORK PROMPTLY AND NOTIFY THE FIRE DEPARTMENT AND PUBLIC WORKS DEPARTMENT FOLLOWED BY WRITTEN NOTICE OF ANY:
A. MATERIAL THAT THE CONTRACTOR BELIEVES MAY BE HAZARDOUS WASTE, AS DEFINED IN SECTION 25117 OF THE HEALTH AND SAFETY CODE, THAT IS REQUIRED TO BE
REMOVED TO A CLASS I, CLASS II, OF CLASS III DISPOSAL SITE IN ACCORDANCE WITH PROVISIONS OF EXISTING LAW.
B. SUBSURFACE OR LATENT PHYSICAL CONDITIONS AT THE SITE DIFFERING FROM THOSE INDICATED ON THE PLANS OR NOTES.
GENERAL NOTES EROSION PREVENTION & SEDIMENT CONTROL
NOTES (CONTINUED)
1. TOPOGRAPHIC INFORMATION PREPARED BY MIKE BUTI LAND SURVEYOR
2. PROJECT BENCHMARK IS A SET MAG NAIL AND CAP IN ASPHALT PARKING AREA. REFER TO SHEET C2 FOR LOCATION. ELEVATION = 104.51 (ASSUMED DATUM).
SURVEY NOTES
1. ALL WORK ON THIS PROJECT SHALL CONFORM TO CHAPTER 14.20 (EXCAVATIONS, GRADING AND FILLS) OF THE SONOMA MUNICIPAL CODE.
PROJECT NOTES
EROSION PREVENTION & SEDIMENT CONTROL NOTES
1. ALL IMPROVEMENTS, INCLUDING ALL MATERIAL AND WORKMANSHIP, SHALL BE DESIGNED
AND CONSTRUCTEDINACCORDANCE WITH AND AS OTHERWISE REQUIRED OR ALLOWED BY
APPLICABLE LAW AND REGULATION AND BY THE PLANS, SPECIFICATIONS, DRAWINGS, AND
REQUIREMENTS STATED HEREIN (COLLECTIVELY, THE CITY OF SONOMA STANDARD PLANS,
INCLUDING OTHER SPECIFIED PLANS AND SPECIFICATIONS INCORPORATED HEREIN BY
REFERENCE, INTHEFOLLOWING DESCENDING ORDER OF PRECEDENCE TO APPLY WHERE A
STRICTER STANDARD IS PROVIDED OR THE PRECEDING STANDARD IS SILENT OR DOES NOT ADEQUATELY COVER:
a. THESE ROAD CONSTRUCTION STANDARDS;
b. CALTRANS STANDARD PLANS (EXCEPT CENTERLINE AND EDGE LINE STRIPING SHALL BE 4" ) (MOST RECENT EDITION);
c. CALTRANS STANDARD SPECIFICATIONS (EXCEPT SPECIFICATION SECTION 39) (MOST RECENT EDITION);
d. CALTRANS STANDARD SPECIFICATIONS, SPECIFICATION SECTION 39 (2006 ED.); e. ADA STANDARDS (2010);
f. CALIFORNIA MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (CA MUTCD; LATEST REVISION);
g. SONOMA COUNTY BIKE AND PEDESTRIAN PLAN;
h. APPLICABLE COUNTY'S SPECIAL PROVISIONS, INCORPORATED HEREIN; i. APPLICABLE MUNICIPAL STANDARDS INCORPORATED HEREIN.
NOTWITHSTANDING, CITY MAY REQUIRE ADDITIONAL WORK OR FACILITIES IN ORDER FOR
THE IMPROVEMENTS TO REASONABLY PROVIDE FOR THE INTENDED FUNCTION OR FOR PUBLIC SAFETY. ADDITIONALLY, BASED ON FIELD CONDITIONS OR FOR OTHER GOOD
CAUSE, COUNTY MAY SPECIFY DIFFERENT OR ADDITIONAL REQUIREMENTS AS NEEDED TO COVER EXTENUATING OR OTHER CIRCUMSTANCES NOT COVERED BY THESE STANDARDS.
MISC NOTES
C. UNKNOWN PHYSICAL CONDITIONS AT THE SITE OF ANY UNUSUAL NATURE, DIFFERING
MATERIALLY FROM THOSE ORDINARILY ENCOUNTERED AND GENERALLY
RECOGNIZED AS INHERENT IN WORK OF THE CHARACTER PROVIDED FOR ON THE PLANS. THE CONTRACTOR SHALL PROMPTLY INVESTIGATE THE SUSPECTED CONDITION AND, AS NECESSARY, INITIATE FURTHER ANALYSIS OF THE PROBLEM. IF
REMEDIATION IS REQUIRED, THE DEVELOPER SHALL SUBMIT A REMEDIATION PLAN
TO THE DIRECTOR OF PUBLIC WORKS AND, UPON APPROVAL BY THE DIRECTOR, SHALL IMPLEMENT THE PLAN AT THE OWNER'S SOLE EXPENSE.
5. IN THE EVENT THAT HUMAN REMAINS ARE ENCOUNTERED, THE REMAINS MUST BE TREATED
IN ACCORDANCE WITH THE REQUIREMENTS OF THE CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA) SECTION 15064.5 AND SECTION 7050.5(B) OF THE CALIFORNIA HEALTH AND SAFETY CODE.
6. CONTRACTOR SHALL CAREFULLY PRESERVE THE SURROUNDING PROPERTY BY CONFINING OPERATION WITHIN THE LIMITS OF WORK AREA. ALL EXISTING UTILITIES AND IMPROVEMENTS
THAT BECOME DAMAGED DURING CONSTRUCTION SHALL BE COMPLETELY RESTORED TO THE SATISFACTION OF THE CITY ENGINEER/OWNER.
7. EXACT LIMITS OF CURB, GUTTER, AND SIDEWALK RECONSTRUCTION SHALL BE MARKED IN THE FIELD BY THE CITY. CONCRETE TO BE REMOVED SHALL BE SAW CUT ALONG EXISTING SCORE LINES.
8. ASPHALT PAVEMENT TO BE REMOVED MAY BE CUT BY ANY METHOD THAT PROVIDES A CLEAN, STRAIGHT CUT AND DOES NOT BREAK DOWN THE REMAINING PAVEMENT EDGE.
9. NEW/REPLACEMENT CURB, GUTTER AND SIDEWALK SHALL BE CONSTRUCTED IN ACCORDANCE WITH CITY STANDARD PLANS 108 OR 110 AS APPROPRIATE. ANY CURB, GUTTER AND/OR
SIDEWALK THAT ARE IN DISREPAIR OR DAMAGED SHALL BE REPAIR, REMOVED AND REPLACED AT THE DIRECTION OF THE PUBLIC WORKS INSPECTOR.
10. CONTRACTOR SHALL OBTTAIN A TRENCH PERMIT FROM THE DIVISION OF INDUSTRIAL SAFETY PRIOR TO EXCAVATION OF ANY TRENCH OVER FIVE FEET IN DEPTH.
11. NO CONCRETE CURBS, WALLS, SIDEWALKS, ETC. SHALL BE POURED UNTIL ALL FORMS HAVE BEEN APPROVED BY THE CITY INSPECTOR.
12. TRAFFIC CONTROL PLANS SHALL BE SUBMITTED AND APPROVED BY THE CITY ENGINEER PRIOR TO ANY WORK THAT MAY AFFECT VEHICLE AND PEDESTRIAN TRAFFIC. TRAFFIC
CONTROL SHALL BE IN CONFORMANCE WITH THE CALTRANS MANUAL OF UNIFIED TRAFFIC CONTROL DEVICES (MUTCD). ON-SITE TRAFFIC CONTROL SHALL BE APPROVED BY THE CITY INSPECTOR BEFORE WORK COMMENCES WITHIN THE ROADWAY AND SIDEWALK.
MISC NOTES (CONTINUED)
2. ALL COVERED PROJECTS AND ACTIVITIES SHALL COMPLY WITH THE STANDARDS, SPECS,
AND CONDITIONS STATED HEREIN, UNLESS AS OTHERWISE SHOWN IN APPROVED PLANS
ATTACHED TO APPLICABLE PERMIT OR AS REVIEWED AND APPROVEDIN WRITING BY THE DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS.
3. FOR ANY WORK TO BE PERFORMED ON THE COUNTY RIGHT-OF-WAY, THE CONTRACTOR
SHALL OBTAIN AN ENCROACHMENT PERMIT FROM CITY OF SONOMA, BEFORE START OF WORK.
4. THE CONTRACTOR SHALL NOTIFY CONSTRUCTION INSPECTOR BEFORE STARTING WORK.
SEE "INSPECTIONS"BELOW FOR NOTIFICATIONS AND APPROVALS. FINAL INSPECTION MAY
NOT BE REQUESTED UNTIL THE GRADING INSPECTOR RECEIVES, REVIEWS AND APPROVES BOTH THE ENGINEER'S FINAL LETTER AND THE FINAL GEOTECHNICAL REPORT. THIS APPROVAL MUST BE OBTAINED PRIOR TO SCHEDULING A FINAL INSPECTION. IMPROVEMENT PLAN CONSTRUCTION NOTES(PUBLIC ROADS) GENERAL PART 1 OF 2
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFYING UNDERGROUND SERVICE ALERT (USA). CALL TOLL-FREE (800) 642-2444 OR 811 AT LEAST TWO WORKING DAYS PRIOR TO EXCAVATION. THE CONTRACTOR SHALL UNCOVER EXISTING BURIED UTILITIES WITH UTILITY OWNER TO VERIFY LOCATIONS AND ELEVATIONS OF UTILITIES. BURIED UTILITIES INCLUDE BUT ARE NOT LIMITED TO WATER, SEWER, ELECTRICAL, GAS, AND TELEPHONE. ALL
UTILITIES CONFLICTING WITH THE PROPOSED CONSTRUCTION SHALL BE RELOCATED PRIOR TO START OF CONSTRUCTION.
6. ALL UNDERGROUND IMPROVEMENTS SHALL BE INSTALLED AND APPROVED PRIOR TO ROAD PAVING AND PLACEMENT OF CURB, GUTTER, AND SIDEWALKS.
7. RESTORATION OF EXISTING SURFACING DUE TO CONSTRUCTION OF TRENCHES SHALL BE GOVERNED BY COUNTY STANDARD219 AND THE CONDITIONS IN THE APPROVED ROAD ENCROACHMENT PERMIT OR AS SHOWN ON THE APPROVED PLANS.
8. ANY GRADING OUTSIDE OF THE ROADWAY IMPROVEMENTS MAY REQUIRE A GRADING PERMIT FROM PRMD.
9. THE CONTRACTOR SHALL OBTAIN A TRENCH PERMIT FROM THE CALIFORNIA DIR DIVISION
OF OCCUPATIONAL SAFETY(CAL/OSHA) PRIOR TO THE EXCAVATION OF ANY TRENCH FIVE FEET OR GREATER IN DEPTH.
10 THE COUNTY MAY REQUIRE ADDITIONAL WORK OR FACILITIES IN THE COURSE OF THE
CONSTRUCTION OF THE PROJECT INORDER FOR THE IMPROVEMENTS TO REASONABLY PROVIDE FOR THE INTENDED FUNCTION OR FOR PUBLIC SAFETY.
THESE SPECS ARE FOR DISTURBED
SOIL COVERAGE. DO NOT USE IN THE
BIO-RETENTION PLANTERS.
M. ENTRANCE(S) TO THE CONSTRUCTION SITE SHALL BE MAINTAINED IN A CONDITION THAT WILL PREVENT TRACKING OR FLOWING OF POTENTIAL POLLUTANTS OFF-SITE. POTENTIAL POLLUTANTS
DEPOSITED ON PAVED AREAS WITHIN THE CITY RIGHT-OF-WAY, SUCH AS ROADWAYS AND
SIDEWALKS, SHALL BE PROPERLY DISPOSED OF AT THE END OF EACH WORKING DAY OR MORE FREQUENTLY AS NECESSARY. THE CONTRACTOR SHALL BE RESPONSIBLE FOR CLEANING
CONSTRUCTION VEHICLES LEAVING THE SITE DAILY TO PREVENT DUST, SILT, AND DIRT FROM BEING RELEASED OR TRACKED OFF-SITE. ALL SEDIMENT DEPOSITED ON PAVED ROADWAYS SHALL BE REMOVED AT THE END OF EACH WORKING DAY OR MORE OFTEN, AS NECESSARY.
N. ALL DISTURBED AREAS SHALL BE PROTECTED BY USING EROSION PREVENTION BMPS TO THE
MAXIMUM EXTENT PRACTICABLE, SUCH AS ESTABLISHING VEGETATION COVERAGE, HYDROSEEDING, STRAW MULCH, GEOTEXTILES, PLASTIC COVERS, BLANKETS, OR MATS.
TEMPORARY REVEGETATION SHALL BE INSTALLED AS SOON AS PRACTICAL AFTER VEGETATION REMOVAL, BUT IN ALL CASES, PRIOR TO OCTOBER 1. PERMANENT REVEGETATION OR LANDSCAPING SHALL BE INSTALLED PRIOR TO THE FINAL INSPECTION.
O. WHENEVER IT IS NOT POSSIBLE TO USE EROSION PREVENTION BMPS ON EXPOSED SLOPES,
SEDIMENT CONTROL BMPS SUCH AS FIBER ROLLS AND SILT FENCES SHALL BE INSTALLED TO PREVENT SEDIMENT MIGRATION. FIBER ROLLS AND SILT FENCES SHALL BE TRENCHED AND KEYED INTO THE SOIL AND INSTALLED ON CONTOUR. SILT FENCES SHALL BE INSTALLED APPROXIMATELY 2 TO 5 FEET FROM THE TOE OF THE SLOPE.
P. HYDROSEEDING SHALL BE CONDUCTED IN A THREE-STEP PROCESS. FIRST, EVENLY APPLY SEED MIX AND FERTILIZER TO THE EXPOSED SLOPE. SECOND, EVENLY APPLY MULCH OVER THE SEED AND FERTILIZER. THIRD, STABILIZE THE MULCH IN PLACE. AN EQUIVALENT SINGLE-STEP PROCESS, WITH SEED, FERTILIZER, WATER, AND BONDED FIBERS, IS ACCEPTABLE. APPLICATIONS SHALL BE BROAD CAST MECHANICALLY OR MANUALLY AT THE RATES SPECIFIED BELOW. A SEED MIX AND FERTILIZER SHALL BE WORKED INTO THE SOIL BY ROLLING OR TAMPING. IF THE STRAW IS USED
AS MULCH, STRAW SHALL BE DERIVED FROM WHEAT, RICE, OR BARLEY AND BE APPROXIMATELY SIX TO EIGHT INCHES IN LENGTH. STABILIZATION OF MULCH SHALL BE DONE HYDRAULICALLY BY
APPLYING AN EMULSION OR MECHANICALLY BY CRIMPING OR PUNCHING THE MULCH INTO THE SOIL. EQUIVALENT METHODS AND MATERIALS MAY BE USED ONLY IF THEY ADEQUATELY PROMOTE VEGETATION GROWTH AND PROTECT EXPOSED SLOPES.
MATERIALS AND APPLICATION RATE (POUNDS PER ACRE) SEED MIX 30% CALIFORNIA BROME (ANNUAL)
20% CALIFORNIA BROME (PERENNIAL)
15% BLUE WILDRYE
15% THREE WEEKS FESCUE
17% CALIFORNIA POPPY
3% CALIFORNIA NATIVE LUPINES, INCLUDING ONE OR MORE — LUPINUS SUCCULENTUS, LUPINUS
NANUS,AND OR LUPINUS BICOLOR
APPLICATION RATE: 1-1 1/2 LBS PER 1,000 SQUARE FEET
MULCH
• STRAW - 4000 POUNDS
HYDRAULIC STABILIZING
NON-ASPHALTIC, DERIVED FROM PLANTS
• M-BINDER OR SENTINEL - 75-100 POUNDS
EQUIVALENT MATERIAL
• PER THE MANUFACTURER, CHECK WITH THE STORMWATER COMPLIANCE ANALYST Q. DUST CONTROL SHALL BE PROVIDED BY THE CONTRACTOR DURING ALL PHASES OF CONSTRUCTION.
R. STORM DRAIN INLETS SHALL BE PROTECTED FROM POTENTIAL POLLUTANTS UNTIL DRAINAGE CONVEYANCE SYSTEMS ARE FUNCTIONAL AND CONSTRUCTION IS COMPLETE.
S ENERGY DISSIPATERS SHALL BE INSTALLED AT STORM DRAIN OUTLETS WHICH MAY CONVEY EROSIVE STORMWATER FLOW.
T SOIL, MATERIAL STOCKPILES, AND FERTILIZING MATERIAL SHALL BE PROPERLY PROTECTED WITH
PLASTIC COVERS OR EQUIVALENT BMPS TO MINIMIZE SEDIMENT AND POLLUTANT TRANSPORT FROM THE CONSTRUCTION SITE.
U SOLID WASTE, SUCH AS TRASH, DISCARDED BUILDING MATERIALS, AND DEBRIS, SHALL BE PLACED IN DESIGNATED COLLECTION AREAS OR CONTAINERS. THE CONSTRUCTION SITE SHALL BE CLEARED OF SOLID WASTE DAILY OR AS NECESSARY. REGULAR REMOVAL AND PROPER DISPOSAL SHALL BE COORDINATED BY THE CONTRACTOR.
V. A CONCRETE WASHOUT AREA SHALL BE DESIGNATED TO CLEAN CONCRETE TRUCKS AND TOOLS.
AT NO TIME SHALL CONCRETE PRODUCTS AND WASTE BE ALLOWED TO ENTER CITY WATERWAYS
SUCH AS CREEKS OR STORM NO WASHOUT OF CONCRETE, MORTAR MIXERS, OR TRUCKS SHALL BE ALLOWED ON THE SOIL. CONCRETE WASTE SHALL BE PROPERLY DISPOSED OF.
W. PROPER APPLICATION, CLEANING, AND STORAGE OF POTENTIALLY HAZARDOUS MATERIALS,
SUCH AS PAINTS AND CHEMICALS, SHALL BE CONDUCTED TO PREVENT THE DISCHARGE OF POLLUTANTS.
X. TEMPORARY RESTROOMS AND SANITARY FACILITIES SHALL BE LOCATED AND MAINTAINED DURING CONSTRUCTION ACTIVITIES TO PREVENT THE DISCHARGE OF POLLUTANTS. SECONDARY CONTAINMENT, I.E., CATCHMENT PANS, ARE REQUIRED.
Y. APPROPRIATE VEHICLE STORAGE, FUELING, MAINTENANCE, AND CLEANING AREAS SHALL BE DESIGNATED AND MAINTAINED TO PREVENT THE DISCHARGE OF POLLUTANTS.
Z. SHOW DISCONNECTION FROM THE STORM DRAIN SYSTEM WITH DOWNSPOUTS REROUTED TO LANDSCAPING. CIVIL SHEETS (GENERAL, SEDIMENT AND EROSION, STANDARDS, OR
STORMWATER PLANS) SHOW A STANDARD DOWNSPOUT AND NOTES WHEN RELEVANT TO THE PROJECT SCOPE.
PRMD
PT
RCP
s
SC
SD
TD
TYP
TW
VERT
w/
PERMIT AND RESOURCE
MANAGEMENT DEPARTMENT
PRESSURE TREATED
REINFORCED CONCRETE PIPE
SLOPE
SONOMA COUNTY
STORM DRAIN
TRENCH DRAIN
TYPICAL
TOP OF WALL
VERTICAL
WITH
SLOPE AND FLOW DIRECTION
BEARING AND DISTANCE
PROPERTY LINE
PROPERTY LINE - ADJACENT
BUILDING ENVELOPE
EX FENCE
MAJOR CONTOUR (EX)
MINOR CONTOUR (EX)
TRENCH DRAIN
STORM DRAIN
PERF SUB-DRAIN
AREA DRAIN
RIP-RAP OUTLET
SECTION A-A', SHEET C6
2 UNITS HORIZ TO 1 UNIT VERT
AGGREGATE BASE
ASPHALT
AREA DRAIN
ASSESOR'S PARCEL NUMBER
BUILDING
BEST MANAGEMENT PRACTICE
CLASS
CONCRETE
CUBIC YARDS
DRIVEWAY
ELEVATION
EXISTING
FINISH GRADE
FLOW LINE
FINISH SURFACE
FEET
GRADE BREAK
GRATE
HIGH DENSITY POLYETHYLENE
HORIZONTAL
HIGH POINT
INVERT GRADE
LINEAL FEET
LANDSCAPE
MINIMUM
NOT TO SCALE
ON CENTER
PERFORATED
PROPERTY LINE
2:1
AB
AC
AD
APN
BLDG
BMP
CL
CONC
CY
DWY
ELEV
EX
FG
FL
FS
FT
GB
GR
HDPE
HORIZ
HP
IG
LF
LS
MIN
NTS
OC
PERF
PL
ABBREVIATIONS LEGEND
C1.0 COVER SHEET + NOTES
C1.1 SITE PLAN
C2.0 GRADING + DRAINAGE PLAN
C2.1 GRADING + DRAINAGE PLAN
C3.0 DETAILS
SHEET INDEX
1 AS-BUILT PLANS 6/29/2026 1 AS-BUILT PLANS Agenda Item #7.6:
FOUL LINE
FOUL LINE
300'
RADIUS
BACKSTOP
SCOREBOARD
ELECTRIC OUTLET
BENCHES
18"CMP
INV=99.86'
18'CMP
INV=102.23'
INV=101.26'
INV=101.05'
18"CMP
STREET LIGHT
CONCRETE
CONCRETE
FOUNTAIN
SIGN
SIGN
CURB CUT
DEPRESSED CURB 300'
CHAD S. MOLL DATE
RCE 79721 MDC MOLL DESIGN + CONSULTING PO BOX 9545 SANTA ROSA, CA 95405 (707) 481-9472 [email protected] 20 40 SCALE: 1" = 20' PRELIM SITE PLAN 0 10
N EXISTING GRASS OUTFIELD HOME PLATE EXISTING GRASS OUTFIELD PROPOSED OUTFIELD FENCE EXISTING CHAIN-LINK FENCE EXISTING CHAIN-LINK FENCE 2 ADA PORTA-POTTY 11 STANDARD PORTA-POTTY EXISTING CHAIN-LINK GATE PROPOSED 10-FOOT GRAVEL PATHWAY EXISTING CONCRETE CURB TO REMAIN EXISTING ASPHALT PARKING AREA PROPOSED VAN ACCESSIBLE PARKING STALL AND LOADING ZONE (BY OTHERS) TEMPORARY STAGE SEE SHEET C2.0 FOR GRADING AND DRAINAGE DESIGN 1 ADA PORTA-POTTY 1 STANDARD PORTA-POTTY PROPOSED BIO-RETENTION PLANTER, SEE SHEET C2.0
FIELDS OF DREAMS - SITE IMPROVEMENTS FOR DESIGN
1 AS-BUILT PLANS
1 1
6/29/2026 1 AS-BUILT PLANS
Agenda Item #7.6:
BATHROOMS
BACKSTOP
SCOREBOARD
ELECTRIC OUTLETBENCHES
18"CMP
INV=99.86'
18'CMP
INV=102.23'
INV=101.26'
INV=101.05'
18"CMP
STREET LIGHT
CONCRETE
CONCRETE
FOUNTAIN
SIGN
SIGN
CHAD S. MOLL DATE
RCE 79721 MDC MOLL DESIGN + CONSULTING PO BOX 9545 SANTA ROSA, CA 95405 (707) 481-9472 [email protected] 10 20 SCALE: 1" = 10' GRADING + DRAINAGE PLAN 0 5
N
EXISTING CHAIN-LINK FENCE EXISTING CONCRETE CURB TO REMAIN EXISTING ASPHALT PARKING AREA PROPOSED VAN ACCESSIBLE PARKING STALL AND LOADING ZONE (BY OTHERS) GRAVEL ACCESSIBLE SURFACE AREA = 13,540 SQUARE FEET TEMPORARY STAGE 1 ADA PORTA-POTTY 1 STANDARD PORTA-POTTY
EXISTING CHAIN-LINK FENCE
90LF 18"SD, s=0.5% EXISTING GRASS OUTFIELD EXISTING GRASS OUTFIELD JB-1 102.90 GR 100.14 IG DI-1 101.80 GR 101.05 SO (W) 99.86 IG JB-2 102.90 GR 100.59 IG 100.70 FL/IG 22LF 18"SD, s=0.5% EX 18" CULVERT 102.23 FL/IG 38LF 12" TRAPEZOIDAL SWALE, s=0.5% (MIN) 2 C3.0 102.70 FL/IG AD-1 103.50 GR 102.76 IG34LF SWALE, s=1.0% (MIN) 12LF 8"SD, s=0.5% 102.00 FS MATCH EP 5-FT EDGE GRIND AND OVERLAY CONFORM TO EXISTING GRADE GRADING/PAVING LEGEND NOTE: REFER TO SOILS REPORT (IF ANY) NOTES FOR SITE PREPARATION RECOMMENDATIONS 1. WORK DONE IN CITY RIGHT-OF-WAY SHALL BE PERFORMED UNDER AN ENCROACHMENT PERMIT. 2. PROPOSED STAGE AND ACCESSORY BUILDINGS ARE TEMPORARY AND ARE NOT COVERED UNDER THIS PLAN. 3. GRADING ACTIVITIES SHALL NOT COMMENCE UNTIL APPLICABLE SEDIMENT BMPs HAVE BEEN INSTALLED. NOTES DRAINAGE SCHEDULE NOTES: 1. ALL STORM DRAIN SHALL BE HDPE (w/ SMOOTH WALL), PVC OR APPROVED EQUAL. 2. INLET INSTALLATION IN OR ADJACENT TO VEHICULAR DRIVE AREA SHALL REQUIRE A CONCRETE COLLAR AROUND INLET ASPHALT DRIVEWAY 3" AC OVER 6" CLIIAB OVER 18" ENGINEERED SUB-GRADE SEATING AREA AND PATHWAY 6" PARKTREAD SURFACE OR APPROVED EQUAL CONCRETE PARKING BY OTHERS ASPHALT PATH OVERLAY 2.5" AC OVERLAY OVER EXISTING AC PATH DI-1 OLDCASTLE 24"x24" CONC INLET MODEL DI2424 W/ 9-INCH SIDE OPENING (WEST) AND STEEL GRATE EARTHWORK CALCS CUT: 220 CUBIC YARD (CY) FILL: 30 CY NET: 190 CY (EXPORT/OFFHAUL)* *CONTRACTOR SHALL BE REQUIRED TO PERFORM THEIR OWN EARTHWORK VOLUME CALCULATIONS. THESE CALCULATIONS ARE AN ESTIMATE AND DO NOT INCLUDE: - EXPANSION OR CONTRACTION (SEE SOILS REPORT), - FOUNDATION OR UTILITY TRENCH SPOILS - CLEAR AND GRUB TOTAL DISTURBED AREA: 0.570 ACRES SLOPES 10% OR GREATER: 0.000 ACRES TOTAL NEW IMPERVIOUS AREA: 888 SF JB-1+ OLDCASTLE 24"x24" CONC INLET JB-2 MODEL DI2424 W/ CHECKERPLATE LID EXISTING BIKE PATH (2030 SF) 2.5-INCH AC OVERLAY ASPHALT DRIVEWAY (888 SF) 5-FT EDGE GRIND AND OVERLAY CONFORM TO EXISTING GRADE104.00 FG 103.60 FG 103.40 FG 102.20 FG 102.18 EP 101.70 FG GRADE GRADE BREAK, TYP BREAK, TYP BIO-RETENTION PLANTER (10'X24') 100.70 FG 98.20 BOTTOM 5 C3.0
1 C3.0
3 C3.0
3 C3.0 90LF CONC CAP
4 C3.0 26LF CONC CAP
4 C3.0 16LF CONC CAP
4 C3.0 100.70 FL/FG 25LF SWALE, s=4.0% (MIN) 1 C3.0 101.20 FG 101.20 FG 101.20 FG 101.20 FG 54LF 18"SD, s=0.5%
3 C3.0 102.22 FS 102.01 EG 102.92 FS 102.71 EG 102.88 EP 103.61 FS 103.40 EG 103.57 EP 104.12 TC/FS 104.60 TC 104.10 FS MATCH EG ASPHALT PATHWAY - TYPICAL SECTION C/L NOT TO SCALE 1% 3" AC OVER 6" CLIIAB (95% RC) 4:1 MIN 2.5" AC OVERLAY EX AC PATHWAY 4:1 MIN EG EG
101
103
102
104
104
103
102
103
6 C3.0 TYP
7 C3.0
7 C3.0 EX TREE TO REMAIN EX TREE TO REMAIN EX TREE TO REMAIN EX TREE TO REMAIN EX TREE TO REMAIN EX TREE TO REMAIN EX AC PATH EDGE OF PAVEMENT, TYP LIMITS OF DISTURBANCE, TYP LIMITS OF DISTURBANCE, TYP 9 C3.0 TYP
9 C3.0 TYP
FIELDS OF DREAMS - SITE IMPROVEMENTS
1 AS-BUILT PLANS
6/29/2026 1 AS-BUILT PLANS
1 1 24LF 2" ELEC CONDUIT
1 Agenda Item #7.6:
INV=102.23'
18"CMP
STREET LIGHT
SIGN
SIGN
CHAD S. MOLL DATE
RCE 79721 MDC MOLL DESIGN + CONSULTING PO BOX 9545 SANTA ROSA, CA 95405 (707) 481-9472 [email protected] 10 20 SCALE: 1" = 10' GRADING + DRAINAGE PLAN 0 5
N PROPOSED OUTFIELD FENCE EXISTING CONCRETE CURB TO REMAIN EXISTING ASPHALT PARKING AREA PROPOSED VAN ACCESSIBLE PARKING STALL AND LOADING ZONE (BY OTHERS)
EXISTING CHAIN-LINK FENCE
EXISTING 18" CULVERTEXISTING GRASS OUTFIELD 100.70 FL/IG 22LF 18"SD, s=0.5% EX 18" CULVERT 102.23 FL/IG 38LF 12" TRAPEZOIDAL SWALE, s=0.5% (MIN) 2C3 102.70 FL/IG AD-1 102.50 GR 101.76 IG 34LF SWALE, s=1.0% (MIN)12LF 8"SD, s=0.5% 104.00 FG MATCH EX TC MATCH EX TC MATCH EG MATCHEG EX GATE TO REMAIN FIELDS OF DREAMS - SITE IMPROVEMENTS LIMITS OF DISTURBANCE TYP GRADING/PAVING LEGEND NOTE: REFER TO SOILS REPORT (IF ANY) NOTES FOR SITE PREPARATION RECOMMENDATIONS 1. WORK DONE IN CITY RIGHT-OF-WAY SHALL BE PERFORMED UNDER AN ENCROACHMENT PERMIT. 2. PROPOSED STAGE AND ACCESSORY BUILDINGS ARE TEMPORARY AND ARE NOT COVERED UNDER THIS PLAN. 3. GRADING ACTIVITIES SHALL NOT COMMENCE UNTIL APPLICABLE SEDIMENT BMPs HAVE BEEN INSTALLED. NOTES ASPHALT DRIVEWAY 3" AC OVER 6" CLIIAB OVER 18" ENGINEERED SUB-GRADE SEATING AREA AND PATHWAY 6" PARKTREAD SURFACE OR APPROVED EQUAL CONCRETE PARKING BY OTHERS ASPHALT PATH OVERLAY 2.5" AC OVERLAY OVER EXISTING AC PATH EX 18" CULVERT TO REMAIN 9 C3.0 TYP 104.50 FG MATCH EG GRAVEL ACCESSIBLE SURFACE AREA = 13,540 SQUARE FEET 1 AS-BUILT PLANS
1 1
6/29/2026 1 AS-BUILT PLANS
1 Agenda Item #7.6:
CHAD S. MOLL DATE
RCE 79721 MDC MOLL DESIGN + CONSULTING PO BOX 9545 SANTA ROSA, CA 95405 (707) 481-9472 [email protected] 8 NOT TO SCALE CONCRETE WASHOUT DETAIL STRAW WATTLE CHECK DAM DETAIL NOTES: 1. STRAW WATTLE SHALL BE TRENCHED 2-INCHES INTO GROUND 2. USE 18" REBAR OR WOODEN STAKE 7 NOT TO SCALE TREE PROTECTION FENCE DETAIL NOTES: 1. ORANGE MESH FENCE SHALL BE MINIMUM 4-FEET ABOVE EXISTING GRADE 2. T-POSTS SHALL BE A MAXIMUM 10-FEET SEPARATION 3. PROTECTION FENCE SHALL BE INSTALLED PRIOR TO COMMENCEMENT OF GRADING WORK ON THE PROJECT SITE EXISTING GRADE 10 NOT TO SCALE TRAPEZOIDAL SWALE DETAIL 2 NOT TO SCALE 9" EXISTING GRADE UNDISTURBED EARTH
2:1
2:1 12"
3"
MIN
3"
MIN
DEPTH VARIES
15" MIN 12" MIN EXISTING GRADE NATIVE BACKFILL RECOMPACTED TO 90% RC BEDDING MATERIAL STORM DRAIN UNDISTURBED EARTH 3 NOT TO SCALE STORM DRAIN TRENCH DETAIL DRAINAGE SWALE DETAIL 1 NOT TO SCALE EXISTING 9" GRADE 12" MIN. 12" MIN.
2:1
2:1 UNDISTURBED EARTH
4 NOT TO SCALE STORM DRAIN WITH CONC CAP DETAIL 6" MIN 6" MIN 18" SD HDPE OR EQUAL 6"
MIN #4 REBAR PLACED 18" ON CENTER EACH WAY FINSISH SURFACE SEE GRADING/PAVING LEGEND 8" MIN OVERLAP INSTALL WATTLE AROUND INLET USE REBAR OR PERIMETER WOODEN STAKE TO SECURE WATTLE NOTES: 1. SILT FENCE MAY BE INSTALLED IN LIEU OF STRAW WATTLE 2. INSTALL FILTER FABRIC UNDER GRATE STRAW WATTLE INLET PROTECTION DETAIL 6 NOT TO SCALE BIO-RETENTION PLANTER
5 NOT TO SCALE STRAW WATTLE FIBER ROLL DETAIL NOT TO SCALE
FIELDS OF DREAMS - SITE IMPROVEMENTS
1 AS-BUILT PLANS
6/29/2026 1 AS-BUILT PLANS
Agenda Item #7.6:
FIRST AMENDMENT TO
RESTATED LEASE
THIS FIRST AMENDMENT TO RESTATED LEASE ("First Amendment"), dated as of 9&4:[g ,2009 ("Effective Date"), is entered into between the CITY OF SONOMA, a California municipal corporation ("City" or "Lessor") and SONOMA VALLEY FIELD OF DREAMSa California corporation ("Lessee").
RECITALS
A. Lessor and Lessee are parties to that certain Restated Lease entered into on April 17, 2007 ("Restated Lease") for that certain real property of approximately 665 feet by 730 feet located on First Street West as described in the Restated Lease ("Premises").
The Premises are being leased by Lessor to Lessee for the purposes described in the Restated Lease.
B. In 2005, Lessee caused the construction of certain storm drainage facilities on the Premises ("Improvements"). The Improvements are described in the of?cial building permit records of the City, which records are incorporated herein and made a part hereof for the purpose of describing the location and extent of the Improvements.
C. Lessor and Lessee desire to enter into this First Amendment to provide for Lessor's acquisition and acceptance, and Lessee's ongoing operation and maintenance, of the Improvements.
AGREEMENT
NOW, THEREFORE, in considerationof the foregoing recitals and the mutual covenants contained herein, the parties hereto agree as follows:
1. Lessor's Acceptance of Improvements; Ownership. The City Public Works Department has determined that the installation of the Improvements was performed in accordance with the applicable City standards and guidelines. Lessor hereby accepts the Improvements installed on the Premises by the Lessee. The Improvements shall be considered part of the real property of the Premises and shall remain the property of Lessor in accordance with Section 12 of the Lease.
2. Payment by Lessor to Lessee for Acquisition of the Improvements.
Within thirty (30) days following the full execution of this First Amendment by the parties, Lessor shall pay Lessee the sum of thirty-three thousand dollars ($33,000) as full consideration for Lessor’s acquisition of the Improvements.
3. Operation and Maintenance of Improvements. Lessee shall be responsible for all ongoing operation and maintenance of Improvements during the term of the Lease, in accordance with Section 13 of the Restated Lease and as may otherwise may be directed by Lessor. Lessee shall be solely responsible for determining and effectuating compliance with local, state, and federal law concerning the maintenance of the 1202442v3 21419/0005
Agenda Item #7.6:
Improvements, including but not limitedto, if applicable,state prevailing wage laws and regulations. City makes no representation as to the applicability or non-applicability of any of local, state, or federal prevailing wage laws or regulations to the maintenance of the Improvements or any part thereof. Lessee hereby expressly acknowledges and agrees that the City has not previously af?rmatively represented to Lessee that maintenance of the Improvements is not a “public work,” as de?ned in California Labor Code Section 1720. Lessee shall indemnify, defend and hold harmlessthe City and its of?cers, employees, contractors and agents, with counsel reasonably acceptable to City, from and against any and all loss, liability, damage, claim, cost, expense, “increased costs" as that term is de?ned in California Labor Code Section 1781, court and litigation costs, fees of expert witnesses, and reasonable attorneys’ fees, which, in connection with the maintenanceof the Improvements, results or arises in any way from any noncompliance by Lessee of any applicable local, state, or federal law, including, without limitation, any applicable local, state, or federal prevailing wage law or regulation. It is agreed by the parties hereto that in connection with the maintenance of the Improvements Lessee shall bear all risks of the applicability of prevailing wage laws and regulations and compliance or noncompliance thereof. The foregoing indemnity shall survive the expiration or earlier termination of the Restated Lease as amended by this First Amendment.
4. Possessory Interest. Lessee acknowledges, agrees, and con?rms, that Section 4 of the Restated Lease constitutednotice by Lessor to Lessee, pursuant to California Revenue & Taxation Code §lO7.6, that Lessee°s leaseholdinterest may create a possessory interest that is subject to property taxation and that Lessee shall be responsible to pay any and all property taxes levied on such possessory interest.
5. No Relocation. Lessee, on behalf of itself and its successors and assigns, acknowledges, agrees, and con?rmsthat at the time Lessee entered into the Restated Lease that Lessee was a “post—acquisitiontenant with notice” pursuant to California law, including but not limited to Title 25 California Code of Regulations §6034(b), and that Lessee shall not be entitled to relocation bene?ts or assistancefrom City or from the Sonoma Community Development Agency upon expiration of the RestatedLease or upon the earlier termination of the Restated Lease for any reason. Lessee further, in acknowledgment of the foregoing, and in considerationof City’s payment set forth in Section 2 above, knowingly and expressly waives and relinquishes any and all claims to relocation bene?ts or assistance from City or from the Sonoma Community Development Agency under any law, including but not limited to California Government Code §7260 et seq. and Title 25 California Code of Regulations §6000 et seq., upon expiration of the Restated Lease or upon the earlier termination of the Restated Lease for any reason. The Sonoma Community Development Agency is an express third party bene?ciary of this Section 5 with the right to enforce the terms of this Section 5 but with no obligations under the Restated Lease or this First Amendment.
6. Rati?cation. Except as amended hereby, the Restated Lease remains in full force and effect.
l202442v3 21419/0005
Agenda Item #7.6:
7. Counterparts. This First Amendment may be executed in counterparts, each of which shall be deemed to be an original, but which together shall constitute a single document.
NOW THEREFORE, Lessor and Lessee have entered into this First Amendment as of the Effective Date.
' LESSOR LESSEE
CITY OF SONOMA, a municipal
corporation
Junta.Kelly
Title: Oil?WHO—3e11—
SONOMA VALLEY FIELD OFDREAMS, a California corporation By: Ric 6i yi/i QC“?V4410“
1202442v3 21419/0005
Agenda Item #7.6:
RESTATED LEASE
This restated Lease entered into at the City of Sonoma, Sonoma County, State of California, on �PfZ-lL. l7 _, 2007, between the CITY OF SONOMA, a municipal corporation, as Lessor, and THE SONOMA VALLEY FIELD OF DREAMS, a California corporation, as Lessee is the successor to the Lease originally entered into between CITY and Lessee on April 7, 1993.
For convenience, the parties will be referred to in this lease respectively as the "CITY" and the "LESSEE."
RECITALS
On April 7, 1993, CITY and LESSEE entered into an agreement whereby LESSEE leased from CITY a parcel of real property approximately 665 feet by 730 feet located on First Street West.
On June 8, 1994, and on March 16, 2005, the Indemnification provision of said lease was amended.
On October 7, 1998, the area of the leased premises was amended to include additional undeveloped property.
On April 7, 2003 and at all times thereafter, LESSEE was and remains a private, non-profit corporation organized under· the law of California and qualified for exemption · from federal income tax and State of California franchise tax. Its sole purpose is the creation and operation of a facility consisting of turfed areas and playfields in the City of Sonoma to be operated on a long-term basis for the benefit of young people who reside in and in the environs of the City of Sonoma.
On April 7, 2003 and at all times thereafter, the CITY made and continues to make no representation as to the suitability of the property described in Exhibit A for the purposes intended.
T ditibCJ Page I ofl6
Agenda Item #7.6:
Prior to and since April 7, 1993, LES SEE raised, and continues to raise substantial funds and obtained commitments for the payment to it of substantial funds and proceeded with the establishment of the intended playfield use in the City of Sonoma, and the City of Sonoma continues to deem the establishment and operation of such a facility as an activity partaking of the nature of a public use. Notwithstanding funding which may have been contributed by CITY to the construction of planned improvements on the premises or which may have been granted on a one-time basis in support of programs administered by LESSEE, there is absolutely no commitment from the City of Sonoma or any other public agency to fund any aspects of the creation or maintenance of said playfield, any improvements thereto or any associated uses and the LESSEE has not relied on any expectation of such funding.
The planned construction in 2007 of restroom facilities on a portion of the leased premises has caused the LESSEE and the CITY to restate the lease to incorporate all previous amendments and to incorporate provisions regarding the new restroom facility.
The CITY is willing to restate the lease for the property described in Exhibit A in consideration of the promises and the undertaking of the LESSEE, as stated in this lease, and upon the reservation of a nominal monetary rent, according to the terms and conditions stated below.
The parties therefore agree as follows:
1. Term of Lease. The CITY hereby leases to the LESSEE the real property described in Exhibits A and B attached hereto for a term of 55 years from and after April 7, 1993 through April 6, 2048, and the LESSEE, by execution of a copy of this restated lease and receipt of this lease executed by the Mayor or other authorized officer of the City of Sonoma, pursuant to resolution of its City Council, hereby takes the said property for the said term and will enter into possession thereof and will faithfully perform all of the terms, conditions, promises and undertakings stated as obligations of the LESSEE in the following paragraphs of this instrument.
Agenda Item #7.6:
2. Use of the Property The premises are leased to LESSEE for the following purpose or purposes, and for none other:
1. Construction and operation of playing fields primarily for the not for profit use of young persons in organized and adult supervised team sports. n. Such other uses which are incident and directly related to the uses permitted herein, incl�ding operation and maintenance of a restroom facility, as may be approved in writing after resolution of the City Council, which may be granted or withheld in the absolute discretion of the City Council. 111. Except in such times where LESSEE has expressly scheduled the use of the fields and associated property for team sports permitted herein or as otherwise provided in paragraph 16, hereof, with respect to the operation and maintenance of a restroom facility, the property shall remain open to the use of other members of the public without fee or charge.
1v. Pursuant to paragraph 31 of this lease, the City Council may promulgate such other reasonable rules and regulations as it may deem fit with regard to the uses permitted by this paragraph.
Any other use of the premises than as set forth herein shall be a breach of the covenants and conditions of this lease.
In addition to any other act prohibited by this lease, LESSEE shall not do, commit, suffer, permit, nor allow upon the premises any act or thing which:
a. Will increase the existing rates of insurance on the premises. b. Will cause a cancellation of any policy of insurance covering the premises. c. Might be prohibited by the standard form of fire insurance policy. d. Will constitute waste upon the premises.
e. Will create a nuisance upon the premises.
f. Will disturb the quiet enjoyment of other tenants or the CITY upon the· premises retained by the CITY or leased to other tenants by the CITY. g. Will cause the claims of mechanics, artisans, or material men to become a lien upon the premises.
Agenda Item #7.6:
3. All Uses must be Lawful. No use other than that described in the paragraph above may be made of the property without the prior written consent of the CITY, and every use of the property must in all respects be lawful and not in violation of any valid law, ordinance or regulation of any federal, state, county, city or other governmental agency having jurisdiction. The LESSEE shall not at any time maintain, commit or permit the maintenance or commission of any nuisance, as now or hereafter defined by any statutory or decisional law, on the premises or any part of it. LESSEE shall not illegally discriminate against any person or class of persons in a manner that would be prohibited to the City of Sonoma were it operating the property.
4. Property Taxes; Responsibility of LESSEE. At the date of this lease, the premises are exempt from ad valorem real property taxation as being held for municipal purposes within the corporate limits of the City of Sonoma. The CITY makes no representation and gives no assurance that the LESSEE's interest will be similarly exempt whether under Section 214 of the Revenue and Taxation Code or otherwise. Real property taxes, if any, which may be assessed against the interest of LESSEE shall be paid by LESSEE when due, and LESSEE agrees that any transfer of its title, or threatened transfer of its title, for delinquent taxes shall constitute grounds for the immediate termination of this lease by the CITY and forfeiture of its interest.
5. Right to Contest Tax. No provision in the foregoing paragraph is intended to deprive LESSEE of its right to contest, oppose or object to the amount or validity of any tax, assessment or other charge levied upon or assessed against the premises or any part of the premises. In any such contest, it shall be the LESSEE's sole responsibility to obtain and maintain stay of all proceedings for enforcement and collection of such tax, assessment or other charge.
6. Utilities. Except as provided in paragraph 16, hereof, with respect to the operation and maintenance of a restroom facility, the LESSEE shall pay for all utilities and services delivered to or for the benefit of the premises and shall hold the CITY free and harmless from all utility and service charges of every kind whatsoever.
Agenda Item #7.6:
7. Construction of Improvements Except as provided in paragraph 16, hereof, with respect to the operation and maintenance of a restroom facility, all structural improvements to the property shall be considered temporary. The facilities to be constructed on the premises shall be at the sole cost and expense of LESSEE, and the CITY shall not be called upon to make any contribution to the improvements other than the transfer of the leasehold interest at nominal monetary consideration as provided for in the terms of this instrument. The parties recognize that an initiative measure of the people of the City of Sonoma prohibits the construction of permanent structures on this property.
Therefore no permanent structures shall be constructed on the property and LESSEE shall remove all structures from the property upon termination of this lease for whatever cause unless the retention of the structure is permitted by the City of Sonoma.
8. CITY Approval of Plans. Before any improvement is commenced upon the property, the LESSEE shall submit to the CITY for its review and approval all plans, specifications, drawings and other instruments prepared for construction purposes which shall show the proposed location of improvements upon the property. No improvements shall be placed upon or maintained on the premises that do not comply with plans, specifications and locations approved by the CITY, and following placement, no material additions to or alternations of any structure or improvement shall be made without the further consent of the CITY. All plans and specifications must be prepared by licensed architects or engineers. Plans for any structural work shall be checked by the CITY' s building official and inspected during construction utilizing the City's normal building permit process.
9. Nonresponsiblity of CITY for Liens. LESSEE will allow no new construction work of any kind to be commenced upon the property and.will allow no construction materials to be delivered to the property until at least 10 days after written notice has been given to the CITY, care of the City Manager, of the intended commencement of work or intended delivery of materials. The CITY shall at all times have the right to post and maintain on the said premises, and to record as provided by law, notice or notices of nonresponsiblity under the Mechanics Lien laws of California. The work prohibited by this paragraph until proper notice has been given includes construction work, any work
Agenda Item #7.6:
done for site preparation, utilities installation, street or sidewalk construction or any grading or filling on the said premises.
10. Contractors Bonds. Each general contractor employed by LESSEE to perform any construction services in or about the premises shall be required to deliver surety bonds in amounts equal to the contract price to secure faithful performance of the contract and to secure the payment of all claims for the performance of labor or services on, or for the furnishing of materials for, the performance of the contract. Labor for which there is no remuneration shall be exempt from this requirement. 11 Compliance with Law. All work performed upon the premises shall be done in accordance with all valid laws, ordinance, regulations and orders of all governmental agencies having jurisdiction. No buildings or improvements on the premises shall be occupied or utilized until the City of Sonoma has issued a final certificate of occupancy. No provision of this lease shall be deemed to imply or expressly allow the construction of structures on the property contrary to paragraphs 7 and 8.
12. Improvements are Part of the Realty. Any and all buildings and improvements placed or erected upon the premises, together with alterations, additions, improvements and fixtures, except movable furniture and furnishings, shall be considered part of the real property of the premises and upon expiration or sooner termination of the lease, shall remain on the premises and become the property of the CITY, unless required to be removed under paragraph 7.
13. Maintenance of Improvements by LESSEE Except as provided in paragraph 16, hereof, with respect to the operation and operation of a restroom facility, the LESSEE at its own cost and expense will keep and maintain the said premises and all improvements on them in safe and sanitary condition and in good order and repair. All landscaping installed upon the premises shall be kept in clean and attractive condition, properly watered and cultivated.
14. Damage or Destruction oflmprovements; LESSEE's Duty to Restore. Except as provided in paragraph 16, if during the term of this lease any buildings or
Agenda Item #7.6:
improvements on the premises are destroyed in whole or in part by fire, theft, the elements or other cause not the fault of the CITY, this lease shall continue in full force and effect provided the LESSEE at its own cost and expense shall repair and restore the damaged or destroyed improvements according to the original plan thereof or according to such modified plans as shall be approved in writing by the CITY. The work of repair or restoration shall be commenced within a reasonable time after damage or destruction occurs and shall be completed with due diligence after the work is commenced.
15. LESSEE's Election Not to Restore Damaged Improvements. Except as provided in paragraph 16, if improvements on the property are destroyed to an extent that makes replacement impossible or difficult, for lack of sufficient insurance proceeds or other good reason, LESSEE shall have the option of terminating this lease provided that it will remove at its own costs and expense all debris and remains of damaged improvements from the premises and if demanded by the CITY, will remove at its own cost and expense all other improvements and structures on the premises and restore possession of the premises to the CITY with all buildings removed, including foundations thereof, clean of all debris and rubble and in safe and sanitary condition.
16. Restrooms. Subject to the conditions set forth below, CITY shall at its sole expense construct a restroom, kennel and storage building, hereinafter "RESTROOM BUILDING," as described in Exhibit Bat the location depicted in Exhibit A.
1. LESSEE maintenance and repair obligations
a. LESSEE, at its sole expense, shall be responsible for the operation and maintenance of that portion of the RESTROOM BUILDING (restroom and ancillary storage room) that is accessible from the leased premises, including the following:
b. LESSEE shall maintain in an operable condition all interior electrical and plumbing, including fixtures, wiring, receptacles, switches, lighting, overcurrent protection, piping and conduits, serving the restroom portion of the RESTROOM FACILITIES. LESSEE shall maintain in an operable condition the exterior lighting and drinking fountains serving the restroom portion of the RESTROOM FACILITIES ..
c. LESSEE shall maintain and repair all interior finishes including flooring, wall finishes, doors, screened vent openings, ceilings, toilet partitions, mirrors, hardware, dispensers, shelving, signage, vandalism repairs and graffiti removal and all
Agenda Item #7.6:
other permanently installed equipment or items within the interior of the restrooms and the ancillary storage room.
d. LESSEE is responsible for operation of the restrooms including regular janitorial service, restroom paper supplies, cleaning supplies and cleaning equipment.
e. LESSEE is responsible for locking and unlocking the restrooms.
Except as set forth herein with respect to City-authorized events, restrooms shall be open only during those times when LESSEE has expressly scheduled the use of the fields and associated property for team sports as permitted herein. Restrooms shall be locked during non-daylight hours except when CITY-authorized special night-time events are held, during which times LESSEE agrees to make restrooms available to the general public at no cost to the CITY or the general public. LESSEE shall be responsible for maintaining and programming all locking mechanisms. LESSEE shall provide to the CITY access codes and keys for locking mechanisms to the restrooms and ancillary storage room.
f. LESSEE shall at all times maintain the restrooms, the restroom storage and the exterior areas west of the attached fence located between the Police Station and the Field of Dreams in a clean and sanitary condition. CITY shall provide sufficient trash receptacles and shall provide trash removal and disposal as needed to maintain clean and sanitary conditions within and in the exterior vicinity of the restrooms on the leased premises.
g. LESSEE shall maintain the area surrounding the building located to the west of the attached fence located between the Police Station and the Field of Dreams in a clean condition, free of storage of materials, items or debris.
11. CITY maintenance and repair obligations
a. CITY, at its sole expense, shall be responsible for the maintenance of the roof and structural framework of the RESTROOM FACILITIES. b. CITY at its sole expense, shall maintain and repair exterior walls, signage, roof vent openings, gutters, downspouts, skylights, walkways and other exterior finishes, including but not limited to vandalism repairs and graffiti removal of the RESTROOM FACILITIES.
c. CITY shall be responsible for the maintenance of the utility lines and fire sprinkler system serving the building, including the sewage pump. 111. Utility expenses
a. CITY shall pay all electric utility charges for the building.
Agenda Item #7.6:
b. LESSEE shall pay all sanitary sewer use fees for the building. c. LESSEE shall be responsible for paying 75% of the water use fees billed to the building and CITY shall be responsible for paying 25% of the water use fees billed to the building.
1v. Damage or destruction of improvements. If during the term of this lease the RESTROOM FACILITIES is destroyed in whole or in part by fire, theft, the elements or other cause, neither the CITY nor the LESSEE shall be obligated to repair or restore the damaged or destroyed improvements. Failure by either party to repair or restore the damage or destroyed improvements, or any part thereof, shall not constitute a breach or default. If LESSEE chooses to repair or restore the restroom facilities, LESSEE shall adhere to the provisions of Sections 7, 8, 9, 10 and 11 of this lease. If neither party chooses to repair or restore the damaged or destroyed improvements, CITY shall have the obligation to clean the area of all debris and rubble so that the area within the leased premises is returned to a safe and sanitary condition.
17. Liability Insurance. All organized groups, including but not limited to, Little League, Babe Ruth, Pop Warner Football or American Soccer Organization who apply or reserve use of the Field of Dreams facility shall provide, to the City Clerk, at least five ( 5) days before the event, proof of insurance naming, the City of Sonoma as an insured, and. shall comply with all REMIF requirements, This insurance and compliance with REMIF, at a minimum, shall consist of .a comprehensive policy of public liability insurance issued by an insurance company or companies acceptable to the CITY, insuring both the organization as well as the CITY against loss and liability caused by or connected with the organization's use of the premises. The amount shall be initially not less than one million dollars ($1,000,000.00) for injury or death to one or more persons and two hundred fifty thousand dollars ($250,000.00) for damage to or destruction of any property of other persons. The coverage thus provided shall be primary insurance and in the event of loss, shall be exhausted before any other carrier may be called upon to share in such loss. The amount of insurance shall be reviewed and may be increased by order of the City Council as provided in paragraph 30. Additionally, LESSEE shall obtain and
Agenda Item #7.6:
keep in force Worker's Compensation Insurance as required by law during the entire period covered by this lease.
18. Notice of Cancellation of Insurance. Any organization reserving or utilizing the Field of Dreams shall keep on deposit with the CITY at all times certificates of required insurance, and every insurance policy required by this lease shall contain a provision that it may not be canceled for any reason on less than 30 days prior written notice to the City of Sonoma, In the event that insurance has been canceled or otherwise is unavailable, any group not insured operating under the auspices of LESSEE shall make no further use of the premises until such time as insurance and compliance with the terms of this lease has been obtained.
19. Indemnity. The City of Sonoma shall hold the LESSEE harmless from and against any and all claims for personal injury (including death) or property damage, except that the CITY shall not indemnify the LESSEE for any claims arising out of any conditions of the property attributable to the use of the premises by Sonoma Jazz Plus.
20. Condemnation by Eminent Domain. If the property or any part of it shall be condemned for public use by any agency having the power of eminent domain, the award made for such taking shall be divided between the parties according to their agreement and if they cannot agree, shall be apportioned by a court of competent jurisdiction according to the respective interests of the parties,
21. Restriction on Assignment or Subletting. LESSEE may not assign, sublet, or otherwise transfer this lease or any interest in it without the prior written consent of the CITY, and any attempt to so transfer in violation of this restriction shall be null and void.
This lease has been negotiated and entered into for the express purposes stated in its recitals and paragraphs on use (paragraphs 2 and 3) and no assignment for any other purpose or use shall be permitted. Any involuntary transfer of the LESSEE's interest, by operation of law or otherwise, shall be void at the option of the CITY and if voided, shall terminate this lease. Consent, by the CITY to one assignment shall not be deemed consent to any subsequent assignment. In addition to their legal meanings, "assignment"
Agenda Item #7.6:
or "subletting" shall be deemed to include any and every contract or agreement whereby management and control of the day to day operations of the LESSEE's business is entrusted to anyone or entity other than LESSEE personally.
22. Temporary Uses. LESSEE shall not permit other persons or organizations to utilize the premises contrary to paragraphs 2 and 3. However, short term uses in the nature of licenses, but not tenancies, may be permitted with the prior approval of the City Council. LESSEE may submit a list of types of such uses which, if approved, may thereafter occur without prior specific approval of the City Council provided that approval is gained from the City Managers office before such temporary uses by a licensee. The City Council ( or the City Manager after prior approval of the City Council) may condition such uses on such reasonable terms and conditions as it may deem appropriate.
23. Default and Termination. Upon breach and default as provided herein or according to California law, and in addition to any other remedy or remedies given under this lease or by law, CITY, at its option, may declare a forfeiture of this lease, and may thereupon, without further notice enter and retake the premises and remove all persons and goods therefrom.
LESSEE shall not commit waste, create a nuisance, use the premises in violation of law, assign or sublet this lease of the premises in violation of LESSEE's covenants herein, CITY may treat each and every covenant of LESSEE as a condition and each breach is a breach of condition. All covenants and agreements contained in this lease are declared to be conditions of this lease. The insolvency of the LESSEE, if such results in or threatens to result in violation of the covenants or conditions of this lease shall be considered a breach of this lease.
In addition to any other method of termination permitted under this lease or California law, either party may at any time by written twelve (12) month notice terminate this lease with or without cause.
Agenda Item #7.6:
24. Waiver of Breach. The waiver by either party of any breach of any provisions of this lease by the other party shall not constitute a continuing waiver or the waiver of any subsequent breach either of the same or of a different provision.
25. Remedies Cumulative. No remedy afforded the CITY for breach shall be exclusive, whether given by the terms for this lease or by law but shall be cumulative with and in addition to all remedies which at the date of this lease and hereafter are allowed by law and provided for in this lease.
26. Non-discrimination. In utilizing the premises, in operating improvements, including the restroom facility, upon the premises, in providing services to persons upon the premises and in any activity which utilizes in any manner of the premises, the LESSEE shall act at all times without discrimination against any person or persons on account of race or racial origin, physical condition, national origin, sex,.religious or political affiliation or otherwise in any manner contrary to law or public policy.
27. Attorneys Fees on Litigation. In any litigation commenced between the parties to this lease concerning the premises, or the interpretation of this lease, or for the enforcement of rights and duties of either in relation thereto, the prevailing party in such litigation shall be entitled, in additional to its other relief, to a reasonable sum for attorney's fees to be determined by the court in such litigation or in a separate action brought for that purpose.
28. Binding on Successors and Assigns. This lease is binding on and shall inure to the benefit of the successors an assigns of each party.
29. Monetary Consideration. LESSEE shall pay to the CITY during the second calendar quarter of each year, beginning in April 1, 1993, and thereafter until termination, the sum of one dollar ($1.00) in cash, in legal tender, to be presented to the City Council at open public meeting with written report on its operations to the preceding April 1st.
30. Review and Revision of Liability Insurance Coverage. With reference to paragraph 17 concerning liability insurance by LESSEE, the minimum coverages and
Agenda Item #7.6:
policy form specified in paragraph 17 are subject to review at the end of every two (2) year period this lease remains in effect. On such review, the City of Sonoma shall preliminarily determine whether it considers the coverage adequate in light of the value of money, the cost of coverage, the experience of the parties during the preceding two (2) years with respect to claims, actions, settlements, judgments and other matters relevant to the question of adequate insurance coverage. If the City of Sonoma determines that the coverage is not adequate, it shall specify the coverage requested, and the LESSEE shall continue to satisfy the requirements of paragraph 17 by procuring and filing proof of such additional coverage as requested by the CITY. If the LESSEE does not agree, the parties shall attempt to settle the question by negotiation and appropriate modification of paragraph 17. However, if the parties are unable to agree after hearing before the City Council, the decision of the City Council shall be final.
31. Rules and Regulations. CITY may from time to time promulgate such reasonable rules and regulations for the use of the premises as CITY may determine are appropriate.
32. Entry by CITY. CITY reserves the right to enter the premises including the restroom facility at any time, without notice, for the purposes of inspection and posting notices of nonresponsibility. CITY need not give notice of exercise of this right. Nothing herein shall affect the ability of the City of Sonoma to enforce all appropriate laws and ordinances with regard to the use of this property, which shall generally be deemed a public place subject to the limited controls permitted under this lease
33. Prohibitions of Certain Uses. Except as provided in paragraph 16, hereof, with respect to the operation and maintenance of a restroom facility, no lights, fences, or permanent structures of any kind, except baseball backstops, shall be erected or permitted to exist on the premises unless first approved by the City Council.
34. Holding Over. Any holding over by LESSEE, after any term, extension, or renewal, with the consent of the CITY, shall be construed as a year to-year tenancy,
Agenda Item #7.6:
subject to all other terms and conditions of this lease, so far as applicable, except that any rental then reserved hereunder may be increased upon thirty (30) days notice in writing.
35. Notices. All notices to either party shall be in writing and shall be served upon the person being notified by personal service or by depositing such notice in the United States mail, certified, postage prepaid addressed to the party at the address given below, or by later notice:
CITY's address:
LESSEE' s address:
City Manager
City of Sonoma
#1 The Plaza
Sonoma, California 95476
Sonoma Valley Field of Dreams,
C./o C.�l!=t (\11,J).-&a.T\t,.I a California Co oration 'f.o. � q-z.c.,·
Sonoma, California 95476
36. Time is the essence of this lease,
37. Captions. The titles or headings to the various paragraphs are for convenience only and are not a part of this lease,
IN WITNESS WHEREOF, the parties have executed this lease by their officers duly authorized as of �\l-- \ 1..,2007.
CITY OF SONOMA, a municipal corporation,
CITY By:'1¼��
SONOMA VALLEY FIELD OF DREAMS, a
:
f
:;;;;�
Agenda Item #7.6:
a· D @]3397
EXHIBIT A
I
I
I ,. � I
I �!1
I
I
L
Agenda Item #7.6:
:Si
-�
u..
'ts
i:::
1$1 .r � :Si 0 ·-
8 c:i..� � � E
c'2 ,._ 0
1$1 � g
E f �
ll.t � ii.::: f
D � �
'ti «I � -,;:; f � § D
.$1 u.. Js 'E
E
A.iC:. El&il I £3 bi
EXHIBITB
' � .. ,.! ........ -�-{:)
�!
ii E QC
!
OJ
<(
(II
0 E
(II
f
0 ....
0 �
.!
LL.
'
m
:!::
.a
. Page 16 ofl6
Agenda Item #7.6:
Field of Dreams Restrooms
Areas of Responsibility- Based on Draft Restated Lease Dated 1-23-07 Updated Januarv 24, 2007
ITEM
Initial Construction
Initial Building Construction Costs
Initial Grading and Site Drainage Improvements Around Building Utility Connection Fees
Maintenance
Exterior - Maintenance and repairs of Restroom/Kennel structure including:
• Structural building elements anq masonry
• Skylights
■ Roofing
■ Exterior caulking & sealants
■ Canopies and roof overhangs
■ Gutters & downspouts
■ Exterior flashing & sheet metal
■ Exterior siding and trim
■ Exterior doors, windows, screens and associated frames ■ Exterior graffiti removal and painting
■ Exterior signage
■ Exterior drinking fountains and hose bibs attciched to building ■ Exterior railings
• Exterior light fixtures.and electrical
■ Building water and electrical service laterals
■ Building sewer and sewage ejector system
■ Fire sprinkler system riser and building supply line
■ Fire sprinkler system, including fire sprinkler piping and heads located within the interior of the Restrooms.
■ Exterior ·louvers & vents
■ Exterior walkways.
• Maintenance of permanent fencing East of the Bike Path ■ Exterior vandalism.
City
✓
✓
✓
✓
Field of
Dreams
Agenda Item #7.6:
ITEM City Field of
Dreams
Interior -- Maintenance and Repair of Restrooms including:
■ Interior wall, floor and ceiling finishes, exposed trusses and trim ■ Door hardware and locking mechanisms
■ Interior flooring
■ Interior plumbing and plumbing fixtures,
•
Interior electrical ·fixtures, switches, lamps and branch circuit wiring . ■ Counter tops, cabi11ets, shelving and casework.
• Interior caulking & sealants ✓
■ Interior graffiti removal and painting
•
Interior specialties such as toilet partitions, mirrors, grab bars, paper dispensers, soap dispensers and other interior fixtures and accessories'. •
Interior signage
■ Interior water heater, equipment (if any).
■ Exterior light fixtures and electrical
• Interior vandalism to finishes and fixtures •
• Exterior site drainage
Ongoing Operational Items
Ongoing regular janitorial service. ✓
Restroom paper goods, cleaning supplies and other ongoing operational and maintenance ✓ supplies Trash and debris removal in restrooms and around Field of Dreams of side of building including ✓ regular trash pickup service.
Landscaping and irrigation around Restroom building (none currently proposed) ✓ Opening _and closing Restrooms (locking & unlocking) for Field of Dreams users and during City specified events (i.e. 41h of July, Jazz+, etc.) [Note that City is anticipating installing computer ✓ managed and programmable door locking mechanisms on the Field of Dreams Restroom entry doors for use by the Field of Dreams.]
Property Insurance ✓
Liability Insurance ✓ ✓
Water Usage Fees for the Restroom Building [Field of Dreams and City each pay their direct costs for water based on actual metered use.] ✓ ✓
Sewer Usage Fees for the Building ✓
Electrical Usage Fees for the Building ✓
All Other Utility Usage Fees for the Field of Dreams Site ✓ Property Taxes, If any. [The premises are currently exempt from property taxation since the property is being held for municipal purposes within the City of Sonoma. -EndAgenda Item #7.6:
City of Sonoma
Agenda Item Summary
Meeting: City Council - 15 Jul 2026
Department
Police
Staff Contact
Brandon Cutting, Police Chief
Agenda Item Title
An Ordinance Amending Section 10.74.011 of the Sonoma Municipal Code Summary
This is an amendment to the Sonoma Municipal Code regarding motor-driven vehicles prohibited on bicycle paths to meet current California State Law for electric motor size and class of e-bicycle.
Recommended Council Action
Introduce the ordinance.
Alternative Actions
Council discretion.
Financial Impact
There is no financial impact related to this action.
Environmental Review Status
Environmental Impact Report
Negative Declaration
Exempt
Not Applicable
Approved/Certified
No Action Required
Action Requested
Attachments
Ordinance - Pathway E-Bikes
Agenda Item #9.1:
1 City of Sonoma
ORDINANCE # ___ - 2026
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF SONOMA
AMENDING SECTION 10.74.011 OF TITLE 10 OF THE SONOMA MUNICIPAL
CODE REGARDING MOTOR-DRIVEN VEHICLES PROHIBITED ON BICYCLE
PATHS AND FINDING THIS ORDINANCE EXEMPT UNDER THE GENERAL
RULE OF THE CALIFORNIA ENVIRONMENTAL QUALITY ACT
THE CITY COUNCIL OF THE CITY OF SONOMA HEREBY ORDAINS AS FOLLOWS:
SECTION 1. Municipal Code Amendment. Section 10.74.011 of Chapter 10.74 of Title 10 of the Sonoma Municipal Code is amended in to read as follows, with additions noted by underlined text and deletions by strikethrough:
Chapter 10.74.011 Motor-driven vehicles prohibited bicycle paths.
Except for authorized city personnel, no person shall operate any motor-driven vehicle, including a motor-driven bicycle, scooter, skateboard or similar device onto or along any city bicycle path, except those defined as follows:
A. A “motorized bicycle,” which is a device that has fully operative pedals for propulsion by human power and electric motor that meets all of the following requirements: has a power output of not more than 750 1,000 watts; is incapable of propelling the device at a speed of more than 20 miles per hour on level ground; is incapable of further increasing the speed of the device when human power is used to propel the motorized bicycle faster than 20 miles per hour.
Motorized bicycles that comply with this chapter meet the California Vehicle Code definition for a class 1 or class 2 electric bicycle.
B. A “motorized scooter,” which is any two-wheeled device that has handlebars, is designed to be stood or sat upon by the operator, and is powered by human propulsion and electrical energy with a motor that has a power output of not more than 1,000 watts and that is capable of propelling the device at a maximum speed of not more than 15 miles per hour on level ground.
SECTION 2. CEQA. The adoption of this Ordinance is exempt from the provisions of the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15061(b)(3), which provides that CEQA only applies to projects which have the potential for causing a significant effect on the environment. Where it can be determined that the proposed project will not have a significant adverse effect on the environment, the project is not subject to CEQA. This Ordinance better defines qualifying e-bicycles that are authorized to be operated on bicycle paths only and does not propose nor authorize any action or specific project that would have the potential to cause a significant adverse effect on the environment.
SECTION 3. Severability. If any section, subsection, subdivision, sentence, clause, phrase, or portion of this Ordinance for any reason is held to be invalid or unconstitutional by the decision of any court of competent jurisdiction, such decision shall not affect the validity of the remaining portions of this Ordinance. The City Council hereby declares that it would have adopted this Ordinance, and each section, subsections, subdivision, sentence, clause, phrase, or portion thereof, irrespective of the cat that any one or more sections, subsections, subdivisions, sentences, clauses, phrases, or portions thereof be declared invalid or unconstitutional.
Agenda Item #9.1:
2 SECTION 4. Effective Date. This ordinance shall take effect thirty (30) days after passage thereof.
SECTION 5. Publication. This ordinance shall be published in accordance with the provisions of Government Code section 36933, subdivision (c)(1).
SECTION 6. This Ordinance Prevails Where There is Conflict. To the extent that this Ordinance conflicts with any other provision in the Sonoma Municipal Code or City ordinance (urgency or otherwise), policy or regulation, this Ordinance will control.
PASSED AND ADOPTED at a regular Council Meeting of the City Council of the City of Sonoma held on the _______________ by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
APPROVED:
___________________________
Ron Wellender, Mayor
ATTEST:
_________________________
Rebekah Barr, MMC, City Clerk
Date: ____________________
******
I HEREBY CERTIFY the foregoing ordinance was introduced in a Regular Meeting of the City Council of the City of Sonoma held on the ________, 2026, and was duly adopted at a Regular Meeting of the City Council of the City of Sonoma held on the ______, 2026 by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
___________________________
Rebekah Barr, MMC, City Clerk
Agenda Item #9.1:
449497.1
City of Sonoma
Agenda Item Summary
Meeting: City Council - 15 Jul 2026
Department
Administration
Staff Contact
Cristine Alilovich, City Manager
Rebekah Barr, MMC, City Clerk
David Ruderman, City Attorney
Agenda Item Title
Receive Informational Report Regarding Council Compensation Summary
The current compensation for Sonoma City Council Members is $300 per month, as established by ordinance and effective in 2008. Although Government Code section 36516 has long authorized annual increases of up to five percent, the City has not adopted any adjustments since that time. As a result, Council Member compensation has remained unchanged for approximately 18 years.
In 2023, the California Legislature adopted Senate Bill (SB) 329, which amended Government Code section 36516 to increase the maximum compensation authorized for council members serving in general law cities. For cities with populations of 35,000 or fewer, including the City of Sonoma (estimated population 10,739), the maximum authorized compensation is now $950 per month, subject to adoption of a local ordinance.
SB 329 also authorizes the Council to approve future annual adjustments based on inflation, subject to statutory limits. The legislation does not require a city to increase compensation or adopt future adjustments; rather, it provides local agencies with additional flexibility to establish compensation at a level determined appropriate by the legislative body. Cities may not enact an ordinance that provides for automatic future salary increases.
The enactment of SB 329 reflects the legislature's recognition that compensation for local elected officials in many California communities has not kept pace with the increasing responsibilities of serving as an elected official or the effects of inflation. This legislation provides local agencies with greater flexibility to establish compensation levels that reflect local priorities and circumstances.
Prior to the enactment of SB 329, Government Code section 36516 authorized cities to increase council member compensation by up to five percent annually. Although the City of Sonoma was authorized to adopt those increases, no adjustments were made following the establishment of the current $300 monthly compensation in 2008.
During the same period, inflation has reduced the purchasing power of the current stipend while the responsibilities associated with serving on the City Council have continued to increase.
Had the City Council adopted the maximum allowable increase each year since 2008, their compensation could have increased as follows:
Current council member compensation: $300 per month
Maximum annual increase: 5%
Agenda Item #9.2:
449497.1
Cumulative allowable increase: $270 per month
Maximum 2026 compensation under the previous statutory methodology would have been: $570 per month
This calculation is provided for historical context only and does not establish or limit the Council's authority under current law.
Government Code section 36516 authorizes, but does not require, the City Council to increase council member compensation up to the statutory maximum established by SB 329. For the City of Sonoma, that maximum is currently $950 per month.
Following adoption of a new base compensation amount, Government Code section 36516(a)(4) provides two methods for future adjustments:
1. Government Code section 36516(a)(4)(A): An amount equal to five percent for each calendar year from the operative date of the last adjustment of the salary in effect when the ordinance or amendment is enacted. Interest under this provision is not compounded.
2. Government Code section 36516(a)(4)(B): An amount equal to inflation since January 1, 2024, the California Consumer Price Index, not to exceed ten percent for each calendar year.
These statutory provisions provide flexibility for the Council to either adopt periodic incremental adjustments or authorize less frequent adjustments that reflect cumulative allowable increases over time.
Council compensation varies among California cities based on population, governance structure, and local policy decisions. Since the enactment of SB 329, a number of neighboring and comparable jurisdictions have reviewed and increased council compensation. The majority of neighboring jurisdictions have chosen to increase council compensation to the maximum amount of $950 per month. The following examples are provided for general policy context.
Government Code section 36516(d) further provides that employer contributions toward retirement or health insurance benefits are not considered salary, and reimbursement of authorized expenses is excluded from the statutory definition of salary.
Agenda Item #9.2:
449497.1
Council Policy Considerations
Council member compensation can affect who is realistically able to serve as an elected official.
Although City Council service is often described as part-time, it can require many hours each month for agenda packet review, Council meetings, committee assignments, regional meetings, community events, constituent communication, and preparation. These responsibilities often occur during evenings, weekends, or regular work hours, which can create real financial impacts for residents who are not retired, or self-employed with flexible schedules, or supported by an employer.
For many potential candidates, serving on the City Council may mean taking unpaid time off work, reducing work hours, arranging transportation, or paying for childcare, elder care, or other household support. These costs can be especially burdensome for working parents, hourly workers, renters, younger residents, small business owners, caregivers, and people with lower or moderate incomes. As a result, lower levels of council compensation may unintentionally limit the pool of people who can afford to serve, even if they have the experience, commitment, and community perspective needed for the role.
Increasing compensation would not eliminate all barriers to public elected service, and it is not the only factor in a person’s decision to run for office. However, a more meaningful stipend can help offset some of the real costs of serving and make elected office more accessible to a broader range of residents. This, in turn, may encourage a more diverse candidate pool that may better reflects the community’s range of income levels, professions, family responsibilities, ages, and lived experiences.
SB 329 provides the City Council with greater flexibility to establish compensation at a level it determines appropriate. The Council is not required to adopt the statutory maximum and may establish compensation at any amount up to that limit.
In considering whether to adjust compensation, the Council may evaluate a variety of policy considerations, including:
The length of time since the last adjustment;
The increased responsibilities and time commitments associated with Council service; The purchasing power of the current stipend;
Compensation provided by comparable jurisdictions;
The City's fiscal condition and budget priorities; and Whether Council compensation appropriately reflects the responsibilities and public service expectations associated with elected office;
The extent to which compensation may reduce financial barriers to public service and encourage a broader pool of candidates representing a wider range of income levels, professions, and lived experiences; and
Whether increased accessibility to public office may contribute to broader representation on the City Council over time.
Voluntary Donation of Council Compensation
In 2022, the City Council of Sonoma adopted Resolution 04-2022, a policy permitting council members to voluntarily donate some or all of their council compensation to qualified nonprofit organizations or governmental entities, if they so choose. Accordingly, any adjustment to council compensation would not require an individual council member to personally retain the additional compensation.
Agenda Item #9.2:
449497.1
Implementation Requirements
Should the City Council elect to adjust council compensation, Government Code sections 36516 and 36516.5 establish the following requirements:
The increase must be adopted by ordinance.
The ordinance must be considered at two separate City Council meetings held at least seven days apart.
The proposed ordinance and supporting findings must be presented in open session before adoption.
Because the City of Sonoma conducts staggered Council elections, any increase would not become effective until at least one Council Member begins a new term of office. Under the current election schedule, this would occur following the 2026 General Municipal Election.
Any future compensation adjustment must be separately authorized by ordinance. The Council may not adopt an ordinance providing for automatic future salary increases.
Recommended Council Action
Provide feedback and direction to staff.
Alternative Actions
This is an informational item. However, the City Council could provide direction to staff regarding interest in adjusting the salary amount, amount of increase, and timing of increase.
Financial Impact
Any increase in council member compensation will result in additional General Fund expenses.
Pursuant to Government Code section 36516.5, any increase would become effective only after at least one council member begins a new term of office following the 2026 General Municipal Election.
For reference, the approximate annual General Fund cost of several compensation levels is shown below:
Monthly Compensation Increase Approximate Annual Cost
Current - $300 N/A N/A
$625 +$325 Approximately $19,500
$950 +$650 Approximately $39,000
For additional context, each $100 increase in monthly council member compensation represents approximately $6,000 in annual General Fund expenditures for all five Council Members.
The City has sufficient General Fund reserves to absorb the cost of a compensation adjustment, should the City Council determine that an increase is appropriate. Adoption of an increase remains a policy decision balancing fiscal priorities with the Council's goals regarding compensation, recruitment, and public service.
Agenda Item #9.2:
449497.1