City Council Visual Report - Acceptance of Pump Station No. 2 Improvement Project.pdf

South San Francisco City Council
January 12, 2022

Document
City Council Visual Report - Acceptance of Pump Station No. 2 Improvement Project.pdf
Meeting
January 12, 2022
Body
South San Francisco City Council
Original file
350 KB
Text extracted from the city's file for reading and search. Open the original on ci-ssf-ca.legistar1.com. That file is the official record.

WATER QUALITY CONTROL PLANT DIVISION

SANITARY
SEWER
PUMP

STATION
N
O. 2 UPGRADE

PROJECT (PROJECT
N
O. SS1702) ACCEPTANCE
JANUARY 12, 2022

CONTENTS
•Project Overview•Before and After Photos •Cost Summary

PROJECT OVERVIEW
•Increase the pump station capacity, operational control, and reliability•Bring the pump station up to current technological standards, such as remote monitoring•Revamp the exterior of the pump station building with new steel cladding for a modern look •Install a motorized gate to provide additional infrastructure security •System start-up, testing and staff training BEFORE
AFTER

CONSTRUCTION COST
The total construction cost incurred :

Projected Actual
JMB Construction Inc. Contract $4,505,000 $4,505,000Construction Contingency $1,395,000 $477,829Total Project Budget $5,900,000 $4,982,829