Consolidated Fee Results City of South San Francisco, CA Proposed
Fee No.

Current
Fee No. Fee Title Unit Current Fee
Total Cost
(Adj to
FY2022)
Surplus /
(Deficit)
Current
Cost
Recovery
Rules &
Regs
Staff
Recommended
Fee
(Adj to FY2022)
Council
Recommended
Fee
Staff
Recommended
Cost Recovery
%
Council
Recommended
Cost Recovery
%

10. PUBLIC WORKS - ENGINEERING
Encroachment Permits
Sewer Improvements

10.01 Sewer Lateral Video Review Each $79 $102 ($23) 77% User Fee $102 100%

10.02 PW5 Sewer Lateral Certificate Each $78 $66 $12 118% User Fee $66 100%

10.03 Sewer Lateral Plan Review and Permit Each $332 $406 ($74) 82% User Fee $406 100% Minor Frontage Improvements

10.04 MFI Plan Review Each $332 $334 ($2) 99% User Fee $334 100% Small Cell Towers

10.05 Cell Phone Tower Review (City owned pole) Each $332 $2,174 ($1,842) 15% User Fee $2,174 100%

10.06 Cell Phone Tower Review (non-City pole) Each $332 $534 ($202) 62% User Fee $534 100% Utility Improvements

10.07 Utility / Outside Service Connection Review Each $332 $300 $32 111% User Fee $300 100%

10.08 Utility Access and TCP Only Review Each $332 $233 $99 142% User Fee $233 100% Dig Once

10.09 Dig Once Advertisement Each $332 $534 ($202) 62% User Fee $534 100%

10.10 Dig Once Policy Administration Each $5,000 Deposit $10,000 User Fee $10,000 100% Potholing

10.11 Potholing Permit Each $332 $712 ($380) 47% User Fee $712 100% Revocable Encroachment Permits

10.12 Revocable Encroachment Plan Review Each $332 $300 $32 111% User Fee $300 100%

10.13 Revocable Encroachment & Maintenance
Agreement
Each $332 $753 ($421) 44% User Fee $753 100%

10.14 Revocable Encroachment Annual Renewal Fee Annually $332 $200 $132 166% User Fee $200 100% Miscellaneous

10.15 No Parking Signs Each $3 $5 ($2) 60% User Fee $5 100%

10.16 Sidewalk Closure for Maintenance or
Construction - per day of sidewalk closure
Per Day $155 $102 $53 152% User Fee $102 100%
Public Improvement Plan Check (Cost of ROW Improvements)

10.17 PW1 Up to $49,999 Base $621.00 $1,836.00 ($1,215.00) 34% User Fee $1,836.00 100%

10.18 PW1 $50,000 - $99,999 Base $930.00 $1,836.00 ($906.00) 51% User Fee $1,836.00 100%

10.19 PW1 $50,000 - $99,999 Each $10,000 $62.00 $772.60 ($710.60) 8% User Fee $772.60 100%

10.20 PW1 $100,000 - $249,999 Base $1,240.00 $5,699.00 ($4,459.00) 22% User Fee $5,699.00 100%

10.21 PW1 $100,000 - $249,999 Each $10,000 $227.47 $342.27 ($114.80) 66% User Fee $342.27 100%

10.22 PW1 $250,000 - $499,999 Base $4,652.00 $10,833.00 ($6,181.00) 43% User Fee $10,833.00 100%

10.23 PW1 $250,000 - $499,999 Each $10,000 $62.08 $296.84 ($234.76) 21% User Fee $296.84 100%

10.24 PW1 $500,000 - $999,999 Base $6,204.00 $18,254.00 ($12,050.00) 34% User Fee $18,254.00 100%

10.25 PW1 $500,000 - $999,999 Each $10,000 $124.04 $139.06 ($15.02) 89% User Fee $139.06 100%

10.26 PW1 $1,000,000+ Base $12,406.00 $25,207 ($12,801.00) 49% User Fee $25,207.00 100%

10.27 PW1 $1,000,000+ Each $100,000 $1,224.00 $387.00 $837.00 316% User Fee $387.00 100%

10.28 PW1 4th and subsequent Plan Checks or revisions Each $155.00 $1,152.00 ($997.00) 13% User Fee $1,152.00 100% 1 of 4
Consolidated Fee Results PUBLIC WORKS - ENGINEERING DIVISION City of South San Francisco, CA Proposed
Fee No.

Current
Fee No. Fee Title Unit Current Fee
Total Cost
(Adj to
FY2022)
Surplus /
(Deficit)
Current
Cost
Recovery
Rules &
Regs
Staff
Recommended
Fee
(Adj to FY2022)
Council
Recommended
Fee
Staff
Recommended
Cost Recovery
%
Council
Recommended
Cost Recovery
%

10. PUBLIC WORKS - ENGINEERING
Public Improvement Permit / Inspection (Cost of ROW Improvements)

10.29 PW1.1 Up to $49,999 Base $465.00 $612.00 ($147.00) 76% User Fee $612.00 100%

10.30 PW1.1 $50,000 - $99,999 Base $465.00 $612.00 ($147.00) 76% User Fee $612.00 100%

10.31 PW1.1 $50,000 - $99,999 Each $5,000 $23.30 $346.80 ($323.50) 7% User Fee $346.80 100%

10.32 PW1.1 $100,000 - $249,999 Base $698.00 $4,080.00 ($3,382.00) 17% User Fee $4,080.00 100%

10.33 PW1.1 $100,000 - $249,999 Each $5,000 $7.73 $136.03 ($128.30) 6% User Fee $136.03 100%

10.34 PW1.1 $250,000 - $499,999 Base $930.00 $8,161.00 ($7,231.00) 11% User Fee $8,161.00 100%

10.35 PW1.1 $250,000 - $499,999 Each $5,000 $12.40 $81.62 ($69.22) 15% User Fee $81.62 100%

10.36 PW1.1 $500,000+ Base $1,550.00 $12,242.00 ($10,692.00) 13% User Fee $12,242.00 100%

10.37 PW1.1 $500,000+ Each $25,000 $79.25 $204.00 ($124.75) 39% User Fee $204.00 100%

10.38 PW1.1 Additional Inspections Each $155.00 $204.00 ($49) 76% User Fee $204.00 100% Other Fees

10.39 Work without a permit (after the fact permit)
Permit Fee + Plan Check Fee
Each 2x Permit Fee Penalty 2x Permit Fee

10.40 Engineering Staff Construction Coordination
Committee (CCC)
Per Meeting $155 $183 ($28) 85% User Fee $183 100%
Permit Work Deposit

10.41 Sewer Lateral Deposit Security Deposit $1,000 $1,000 $0 100% SecDeposit $1,000 100%

10.42 Minor Frontage Improvements Security Deposit $2,000 $2,000 $0 100% SecDeposit $2,000 100%

10.43 Utility Trenching Security Deposit $2,000 $2,000 $0 100% SecDeposit $2,000 100%

10.44 Pothole Projects Security Deposit $2,000 $2,000 $0 100% SecDeposit $2,000 100%

10.45 All other ROW improvement projects Security Deposit $5,000 $5,000 $0 100% SecDeposit $5,000 100% Mapping

10.46 Map Extensions Each $332 $969 ($637) 34% User Fee $969 100%

10.47 Final / Parcel Map Review and Processing Each $332 $5,603 ($5,271) 6% User Fee $5,603 100%

10.48 Property Merger / Notice Each $332 $2,549 ($2,217) 13% User Fee $2,549 100%

10.49 PW11 Lot Line Adjustment / Certificate of Compliance Each $332 $2,433 ($2,101) 14% User Fee $2,433 100%

10.50 Lot Conformance / Certificate of Compliance Each $332 $1,934 ($1,602) 17% User Fee $1,934 100%

10.51 PW14 Grant of Easement / Easement Abandonment
Request
Each $3,878 $3,170 $708 122% User Fee $3,170 100%

10.52 Subsequent Engineering Mapping Reviews Each $310 $702 ($392) 44% User Fee $702 100%

10.53 Engineering Agreements Each $1,107 $3,505 ($2,398) 32% User Fee $3,505 100%

10.54 Outside Sewer Service Agreement Each $1,107 $5,818 ($4,711) 19% User Fee $5,818 100%

10.55 Benchmark Maintenance Fee Each $155 $233 ($78) 67% User Fee $233 100% Subdivision Tentative Map

10.56 PW9 Minor Tentative Map Each $155 $2,877 ($2,722) 5% User Fee $2,877 100%

10.57 PW7 Major Tentative Map Each $332 $4,197 ($3,865) 8% User Fee $4,197 100%

10.58 Each Additional Lot Over 5 Each $27 $58 ($31) 47% User Fee $58 100% Transportation

10.59 PW16 Transportation - Single trip, or a modification of on original permit
Each $16 $31 ($15) 52% 21 CCR 1411.3 $16 52%

10.60 PW17 Transportation - Annual or repetitive permit Annually $90 $94 ($4) 96% 21 CCR 1411.3 $90 96% 2 of 4
Consolidated Fee Results PUBLIC WORKS - ENGINEERING DIVISION City of South San Francisco, CA Proposed
Fee No.

Current
Fee No. Fee Title Unit Current Fee
Total Cost
(Adj to
FY2022)
Surplus /
(Deficit)
Current
Cost
Recovery
Rules &
Regs
Staff
Recommended
Fee
(Adj to FY2022)
Council
Recommended
Fee
Staff
Recommended
Cost Recovery
%
Council
Recommended
Cost Recovery
%

10. PUBLIC WORKS - ENGINEERING
Grading
Hauling Permit

10.61 Hauling Permit Fee Each $190 $237 ($47) 80% User Fee $237 100%

10.62 Hauling Permit Deposit Security Deposit $2,000 $2,000 $0 100% SecDeposit $2,000 100% Grading Plan Check and Permit

10.63 PW22 51 - 9,999 Cubic Yards Base $1,240.00 $3,826.00 ($2,586.00) 32% User Fee $3,826.00 100%

10.64 PW22 10,000 - 49,999 Cubic Yards Base $1,550.00 $3,826.00 ($2,276.00) 41% User Fee $3,826.00 100%

10.65 PW22 10,000 - 49,999 Cubic Yards Each 10,000 c.y. $8.45 $527.00 ($518.55) 2% User Fee $527.00 100%

10.66 PW22 50,000 - 99,999 Cubic Yards Base $1,583.80 $5,934.00 ($4,350.20) 27% User Fee $5,934.00 100%

10.67 PW22 50,000 - 99,999 Cubic Yards Each 10,000 c.y. $8.84 $234.00 ($225.16) 4% User Fee $234.00 100%

10.68 PW22 100,000 + Cubic Yards Base $1,628.00 $7,104.00 ($5,476.00) 23% User Fee $7,104.00 100%

10.69 PW22 100,000 + Cubic Yards Each 10,000 c.y. $7.40 $351.00 ($343.60) 2% User Fee $351.00 100%

10.70 PW23 4th and subsequent Plan Checks or Revisions Each $310.00 $936.00 ($626) 33% User Fee $936.00 100%

10.71 Grading Permit Deposit Security Deposit $50,000 $50,000 $0 100% SecDeposit $50,000 100% Erosion Control Compliance

10.72 Base Base $150.00 $204.00 ($54.00) 74% User Fee $204 100%

10.73 Per 250 cubic yards (round to the nearest 250) Each 250 c.y. $15.00 $17.00 ($2.00) 88% User Fee $17 100% Miscellaneous

10.74 PW25 Inspections Outside of Normal Business Hours Per Hour $233 $241 ($9) 96% User Fee $241 100%

10.75 PW26 Re-inspection Assessed Under Provisions of
Section 305(h)
Per Hour $155 $204 ($49) 76% User Fee $204 100%

10.76 PW27 Inspections for which a fee is not specifically indicated
Per Hour $155 $204 ($49) 76% User Fee $204 100%

10.77 Permit reinstatement fee Each $78 $66 $12 117% User Fee $66 100%

10.78 Research for Non-Permit Application Inquires Each $66 User Fee $66 100%

10.79 Engineering Staff Time for Services not
Specifically Indicated
Per Hour $233 User Fee $233 100%
Planning Support

10.80 Engineering Staffing TAGs Per Meeting $155 $183 ($28) 85% User Fee $183 100%

10.81 Geotechnical Peer Review Per Review $5,000 Deposit $702 N / A N / A User Fee $702 100% Engineering Design and Conditions Review $0

10.82 Single Family Res / new or additions
(1-3 units)
Each $5,000 Deposit $702 N / A N / A User Fee $702 100%

10.83 Multi-Family Res / new or modifications
(4 or more units)
Each $5,000 Deposit $1,873 N / A N / A User Fee $1,873 100%

10.84 Commercial / Industrial Each $5,000 Deposit $2,341 N / A N / A User Fee $2,341 100%

10.85 Projects requiring City Council Approval Each $5,000 Deposit $3,044 N / A N / A User Fee $3,044 100%

10.86 3rd and subsequent resubmittals Each $5,000 Deposit $585 N / A N / A User Fee $585 100% 3 of 4
Consolidated Fee Results PUBLIC WORKS - ENGINEERING DIVISION City of South San Francisco, CA Proposed
Fee No.

Current
Fee No. Fee Title Unit Current Fee
Total Cost
(Adj to
FY2022)
Surplus /
(Deficit)
Current
Cost
Recovery
Rules &
Regs
Staff
Recommended
Fee
(Adj to FY2022)
Council
Recommended
Fee
Staff
Recommended
Cost Recovery
%
Council
Recommended
Cost Recovery
%

10. PUBLIC WORKS - ENGINEERING
Building Support
Engineering Site Review (Cost of Site Improvements)

10.87 Up to $49,999 Base $310.00 $836.00 ($526.00) 37% User Fee $836.00 100%

10.88 $50,000 - $99,999 Base $930.00 $836.00 $94.00 111% User Fee $836.00 100%

10.89 $50,000 - $99,999 Each $10,000 $186.00 $562.00 ($376.00) 33% User Fee $562.00 100%

10.90 $100,000 - $249,999 Base $1,860.00 $3,646.00 ($1,786.00) 51% User Fee $3,646.00 100%

10.91 $100,000 - $249,999 Each $10,000 $113.67 $187.33 ($73.67) 61% User Fee $187.33 100%

10.92 $250,000 - $499,999 Base $3,565.00 $6,456.00 ($2,891.00) 55% User Fee $6,456.00 100%

10.93 $250,000 - $499,999 Each $10,000 $111.64 $177.92 ($66.28) 63% User Fee $177.92 100%

10.94 $500,000 - $999,999 Base $6,356.00 $10,904.00 ($4,548.00) 58% User Fee $10,904.00 100%

10.95 $500,000 - $999,999 Each $10,000 $55.82 $112.40 ($56.58) 50% User Fee $112.40 100%

10.96 $1,000,000+ Base $9,147.00 $16,524.00 ($7,377.00) 55% User Fee $16,524.00 100%

10.97 $1,000,000+ Each $100,000 $27.00 $351.00 ($324.00) 8% User Fee $351.00 100%

10.98 4th and subsequent Plan Checks or revisions Each $1,122.00 $936.00 $186.00 120% User Fee $936.00 100% 4 of 4