LINDEN AVENUE PHASE 2 AND SPRUCE
AVENUE TRAFFIC CALMING
IMPROVEMENTS- ATP
ACCEPTANCE OF THE CONSTRUCTION IMPROVEMENTS
APRIL 13, 2022
Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP
PROJECT OVERVIEW
Improvements on Linden & Spruce Ave:
Phase 1 (Intersections)
• Aspen Ave & Linden Ave
• Pine Ave & Linden Ave
Phase 2 (Intersections)
• California Ave & Linden Ave
• Lux Ave & Linden Ave
• Miller Ave & Linden Ave
• Lux Ave & Spruce Ave
• Park Way & Spruce Ave
• Maple Ave & Spruce Ave
2 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP Linden & California – Curb Extension and Bus Stop, Bio-Filtration / Planter Area, High Visibility Crosswalks & Sharrows 3 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP Linden & Lux – Curb Extensions, Bio-Filtration/Planter Area, High Visibility Crosswalks & New Stop Legends 4 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP Linden & Miller – Curb Extensions, Bio-Filtration/Planter Area & High Visibility Crosswalks 5 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP Spruce & Lux – New High Visibility School Crosswalks, Stop Legends & Curb Extensions 6 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP Spruce & Park – New High Visibility School Crosswalks, Stop Legends & Curb Extensions 7 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP Spruce & Maple – New Rectangular Rapid Flashing Beacon, High Visibility Crosswalk, & School Legends 8 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP
CONSTRUCTION COST
The total construction cost incurred to date for the project is summarized as follows:
Project
Budget
Actual
Costs
(to-date)
Golden Bay Construction, Inc. – Construction Contract $1,094,883.00 $1,094,883.00 Original Construction Contingency (~20%)
Contingency Increase of $50K (~4.5%)
$219,000.00
$50,000.00
$219,000.00
$40,892.12
Total Construction Budget / Costs $1,363,883.00 $1,354,775.12 9 Linden Avenue Phase 2 and Spruce Avenue Traffic Calming Improvements – ATP QUESTIONS?