2020 PAVEMENT

REHABILITATION PROJECT

ACCEPTANCE OF THE CONSTRUCTION

IMPROVEMENTS
APRIL 27, 2022
Attachment 3
2020 Pavement Rehabilitation Project

PROJECT OVERVIEW
Street Segments
2 - Alta Mesa Drive
- Ash Avenue
- Camaritas Avenue
- Cuesta Drive
- Escanyo Drive
- Hazelwood Drive
- Northwood Drive
- Southwood Center
- Emeral Court,
- Forestview Drive
- Iris Court
- Sunnyside Drive
- Keats Ave
- Ryan Way
2020 Pavement Rehabilitation Project
2020 Pavement Rehabilitation Project
Emerald Dr and Sunnyside Dr – Hot Mix Asphalt Overlay
3 2020 Pavement Rehabilitation Project
2020 Pavement Rehabilitation Project
Holly Ave and Sunnyside Dr – Hot Mix Asphalt Overlay / High Visibility Crosswalks 4 2020 Pavement Rehabilitation Project
2020 Pavement Rehabilitation Project
Los Flores Ave and Camaritas Ave – Valley Gutter Repair / Hot Mix Asphalt Overlay 5 2020 Pavement Rehabilitation Project
2020 Pavement Rehabilitation Project
Hazelwood Dr – ADA Compliant Ramps / Hot Mix Asphalt Overlay / High Visibility Markings 6 2020 Pavement Rehabilitation Project
2020 Pavement Rehabilitation Project

CONSTRUCTION COST
The total construction cost incurred for the project is summarized as follows:

Project
Budget
Actual
Costs
Bay Cities Paving & Grading Inc – Construction Contract $2,541,450.00 $2,541,450.00 Construction Contingency (20% projected versus 3% actual) $508,290.00 $79,290.90 Total Construction Budget / Costs $3,049,740.00 $2,620,750.90 7 2020 Pavement Rehabilitation Project
QUESTIONS?
8