GRAND AVENUE & AIRPORT BLVD
STREETSCAPE IMPROVEMENTS
PROJECT
May 25, 2022
2 IMPROVEMENTS
N
AIRPORT BLVD
3 VIEW FROM SE CORNER
( CALTRAIN PLAZA )
4 VIEW FROM SW CORNER
( GAS STATION )
5 VIEW FROM NW CORNER
( PEET’S COFFEE )
6 CONTRACTOR BASE BID RANKING
Engineer’s Estimate $2,750,000.00 X
CF Contracting, Inc. $3,188,285.00 1
Redgwick Construction, Co. $3,456,161.00 2
Interstate Grading & Paving, Inc. $3,641,027.80 3
Ghilotti Bros, Inc. $4,075,437.00 4
BID RESULTS
6 Competitive Bidding for Construction Projects
Cost is generally the sole determining factor
BUDGET AND SCHEDULE 7
Construction
Contract $3,188,285
Construction
Contingency (20%) $637,657
Total Project
Construction Budget* $3,825,942
Contract Award
Contract Executed
NTP & Construction Start
(Approx. Summer 2022)
Construction Complete
(Approx. Summer 2023) 7
8 OUTREACH
Spring
2021 01
NOTIFICATIONS
DURING DESIGN
Summer
2022 02 CONSTRUCTION ADVANCE
NOTIFICATIONS
Summer
2023 03 CONSTRUCTION
COMPLETE
Thank you!