WATER QUALITY CONTROL PLANT
WQCP AND
PUMP
STATION
COATING AND
CORROSION
PROTECTION
PROJECT
PHASE - 2 AND
3 (PROJECT
N
O.’S SS1307 & SS1901)
ATTACHMENT 1
WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3
PROJECT
OVERVIEW
•Sand blasting and recoating four Primary Clarifiers •Surface preparation and recoating various metal assets in WQCP
•Recoating exterior surfaces for Pump Station No. 4•Recoating piping, metal surfaces & electrical panel at Pump Station No.’s 4,5,6,7,8 &10
•Coating inspection by third party inspectors and staff WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3 BEFORE
WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3 DURING
WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3 DURING
WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3 AFTER
WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3 AFTER
WQCP and Pump Station Coating and Anti-Corrosion Project Phase 2&3
CONSTRUCTION
COST
The total construction cost incurred to date for the project is summarized as follows:
Projected Actual
Murphy Industrial Coating Inc. $865,537.00 $865,537.00Construction Contingency (20%) $173,107.40 $113,718.17Total Project Budget $1,038,644.40 $979,255.17