OYSTER POINT SANITARY SEWER PUMP

STATION REPLACEMENT
PROJECT # SS2202
JANUARY 25, 2023
Oyster Point Pump Station

WHY ARE WE DOING THIS PROJECT
Existing Pump Station Proposed Hotel Development
The existing pump station must be relocated to accommodate the proposed Hotel Development.

Oyster Point Pump Station

PROPOSED NEXT STEPS
Anticipated Schedule:
• City Council Approval of Contract Amendment with Wilsey Ham January 25, 2023 • 9 months to complete bid documents Complete by October 2023 • Public Bidding for Construction Bids November –December 2023 • City Council Awards Construction Contract Jan 2024
• Complete Construction Jan 2025
Oyster Point Pump Station

PROPOSED DESIGN BUDGET
• Wilsey Ham Fee $ 760,000
• Design Contingency (10%) $76,000
Required Total Project Design Funding $836,000
Available Project Budget in CIP : Successor Agency Funds $4,830,000 The Grand Boulevard Initiative
QUESTIONS?