Orange Memorial Park
Aquatic Center
City Council Meeting
May 24, 2023
Design Development Presentation
o Construct a new 24,000 sf facility
o Two pools
• Outdoor, 10-lane cool-water lap pool
• Indoor, 7-lane warm-water teaching/recreation pool
o Activity Room
o Swimmer's Lounge
o Wind Screen
o Maintain operation of existing pool throughout construction of the new pool facility
PROJECT SCOPE
3 ENGAGEMENT, PRESENTATIONS AND COORDINATION
• South San Francisco Aquatics Club
• Design Review Board
• Cultural Arts Commission
• Veterans Memorial Stakeholders
• Peninsula Clean Energy
4 PROJECT BUDGET
Soft Costs (design, permits, fees) $9M
Hard Costs (construction) $40M ($36M + $4M Contingency) Total Project Budget $49M
Measure W Bond Sale Projects – Round 3
Total Project Budget Bond Sale Park In Lieu Fees
New Aquatic Center $49M $49M
Colma Creek Bridge Replacement $3M $1.5M $1.5M
All-Abilities Playground Replacement $6M $2.2M $3.8M
5 DESIGN DEVELOPMENT
BUILDING LAYOUT
PROPOSED MATERIALS
Innowood Composite Wood Weathered Steel Metal Panel
OPTION A – Bigger and Wrapping the corner
OPTION B – Bigger, on one side…..and letters are sitting on a blue shelf
VETERANS MEMORIAL
• Honor and Respect Veterans
• Preserve Eternal Flame Sculpture, Plaques & Flagpole
• Provide High Visibility
• Offer Opportunities for Reflection
• Serve Annual Events
• Include Accessible Surface
• Located within Aquatic Center project boundary
• Opportunity to expand the story/recognition
VETERANS MEMORIAL
VETERANS MEMORIAL
VETERANS MEMORIAL
• Incorporate feedback into Veteran Memorial Design
• Share updated design at upcoming City Council Meeting • Engage Cultural Arts Commission in restoration or
resurfacing the Eternal Flame Sculpture
• Identify content of dedication inscription/plaque
• Identify, if any, additional plaques
• Sign-up for updates [email protected]
• Design update at www.ssf.net/newpool
VETERANS MEMORIAL NEXT STEPS
20 SCHEDULE
City Council Meeting - Design Development Update May
Design Review Board Update July
Planning Commission TBD
Design Documents Complete Summer 2023
Bid/Award December 2023
Start Construction January 2024
Pool Opening Spring 2025
Full Project Completion (Demo/Sitework Complete) Summer 2025