Oyster Point IIC
Improvement Project
South San Francisco
City Council Meeting
October 11, 2023
Project Location
Project Budget
Soft Cost (design, permits, fees) $1,200,000
Hard Costs (construction) $4,500,000
Total $5,700,000
Bid Information
Contractor Base Bid
GECMS, Inc. dba Giron Construction $3,716,501.51
Redgwick Construction $4,255,863.90
Minerva Construction, Inc. $4,272,822.00
McGuire and Hester $4,281,083.55
Robert A. Bothman Construction $4,503,099.00
Interstate Grading & Paving, Inc. $5,089,704.25
Ground Control, Inc. $5,242,750.15
Suarez & Munoz Construction, Inc. $5,642,123.50
Teichert & Son, Inc. dba Teichert Construction $5,736,097.70 Contract Award
GECMS, Inc. $3,716,501.51
Construction Contingence (15%) $ 557,475.23
Total Construction Contract $4,273,976.74
Project Schedule
Design Winter 2022 – Spring 2023
Bid & Award Summer – Fall 2023
Construction Winter 2023 – Spring 2024
Opening Summer 2024
Staff Recommendation
Staff recommends that the City Council of the City of South San Francisco adopt a resolution awarding the construction contract to GECMS Inc., dba Giron Construction of San Francisco, California for the Oyster Point Phase IIC Improvement project.