Cities Index.
Attachment 2 - Presentation by SSF Staff

South San Francisco City Council
November 8, 2023

Document
Attachment 2 - Presentation by SSF Staff
Meeting
November 8, 2023
Body
South San Francisco City Council
Original file
1.2 MB
Text extracted from the city's file for reading and search. Open the original on ci-ssf-ca.legistar1.com. That file is the official record.

SOUTH SAN FRANCISCO

SMART CORRIDOR EXPANSION

CONTINGENCY INCREASES FOR

DESIGN SUPPORT, CONSTRUCTION MANAGEMENT

AND CONSTRUCTION
NOVEMBER 8, 2023
1 SSF Smart Corridor Expansion
2 PROJECT LOCATION MAP
2 SSF Smart Corridor Expansion
3 SYSTEM INTEGRATION (ADDITIONAL SCOPE)
Resulted in Cost & Time Impacts pushing out the Completion Date 2 Months Coordination/Testing + 3 Months System Monitoring/Training SSF Smart Corridor Expansion
4 MATERIAL PROCUREMENT IMPACTS
4 Contract Only Allocated 80 WD’s
(16 Weeks) for Material Procurement
Required 36 Weeks for Procurement
Required 40 Weeks for Procurement
Required 65 Weeks for Procurement
SSF Smart Corridor Expansion
5 OVERHEAD & UNDERGROUND UTILITY CONFLICTS
Resulted in Cost & Time Impacts pushing out the Completion Date SSF Smart Corridor Expansion
6 BURIED MANMADE OBJECTS AND UTILITY CONFLICTS
Resulted in Cost & Time Impacts pushing out the Completion Date SSF Smart Corridor Expansion
7 KIMLEY-HORN AND ASSOCIATES, INC.
7 DESIGN CONSULTANT
Current CSA Contract Budget $ 500,000
+ CSA Amendment No. 04
(Increased Contingency) $ 80,000
Amended CSA Contract Budget $ 580,000
SSF Smart Corridor Expansion
8 ZOON ENGINEERING, INC.
8 CONSTRUCTION MANAGEMENT & INSPECTION
Current CSA Contract Budget $ 633,305
+ CSA Amendment No. 01
(Increased Contingency) $ 180,000
Amended CSA Contract Budget $ 813,305
SSF Smart Corridor Expansion
9 ECONOLITE SYSTEMS, INC.
9 PROCUREMENT OF MATERIALS AND CONSTRUCTION OF PROJECT
Current Contract Budget $ 5,372,702
+ Original Construction Contingency $ 537,270
+ Increased Construction Contingency $ 500,000
Amended Contract Budget $ 6,409,972
SSF Smart Corridor Expansion
10 PROJECT BUDGET CHECK
10 Current Overall Project Budget $ 8,519,000
Current Total Contract Authority $ 7,374,087
+ Total Increased Contingency Amount $ 760,000
Amended Total Contract Authority $ 8,134,087
Project is fully funded by C/CAG
SSF Smart Corridor Expansion
11 SSF SMART CORRIDOR EXPANSION TIMELINE
11 • Construction Began: March 2022
• Original Project Completion: December 2022
• Anticipated Project Completion: May 2024
New Timeline
• Authorize increases in Construction Contingencies
Recommendation
SSF Smart Corridor Expansion
12 Thank You

← All documents from this meeting