FACILITY CONDITION

ASSESSMENT

FACILITY CONDITION ASSESSMENT
OF
Main Library
840 W Orange Ave
South San Francisco, California 94080
EMG Project #: 111948.15R 014.305
Date of Report: December 14, 2015
Onsite Date: May 17, 2015

CITY OF SOUTH SAN FRANCISCO
315 Maple Avenue
South San Francisco, California 94080
PREPARED BY:

EMG
222 Schilling Circle, Suite 275
Hunt Valley, Maryland 21031
800.733.0660
410.785.6220 (fax)
www.emgcorp.com
EMG CONTACT:

Matthew Anderson
Program Manager
800.733.0660, ext. 7613
[email protected]

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT www.emgcorp.com
111948.15R-014.305
.

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT

TABLE OF CONTENTS

1. Executive Summary....................................................................................................... 1

1.1 Project Narrative................................................................................................. 1

1.2 Summary of Findings.......................................................................................... 3

1.3 Facility Condition Index ..................................................................................... 4

1.4 Distribution of Immediate Needs by Building System ......................................... 6

1.5 Distribution of Capital Needs by Building System............................................... 7

1.6 Total Capital Needs By Priority........................................................................... 8

1.7 Total Capital Needs Sorted By Category.............................................................. 9

2. Purpose and Scope...................................................................................................... 12

2.1 Scope ............................................................................................................... 12

2.2 Purpose ............................................................................................................ 12

2.2.1 Probable Capital Needs - Immediate Repairs .................................................... 13

2.2.2 Probable Capital Needs - Capital Reserves........................................................ 13

2.2.3 Remaining Useful Life Estimate......................................................................... 13

2.2.4 Opinions Of Probable Cost............................................................................... 14

2.2.5 Priority Ranking................................................................................................ 14

3. Facility Condition Assessment..................................................................................... 15 A Substructure Systems............................................................................................ 15 A10 FOUNDATIONS............................................................................................. 15 B Shell Systems........................................................................................................ 15 B10 SUPERSTRUCTURE ..................................................................................... 15 B20 EXTERIOR ENCLOSURE ............................................................................. 16 B30 ROOFING ...................................................................................................... 17 C Interiors Systems................................................................................................... 19 C10 INTERIOR CONSTRUCTION ........................................................................ 20 C30 INTERIOR FINISHES ................................................................................... 21 D Services Systems .................................................................................................. 25 D10 CONVEYING SYSTEMS ............................................................................... 25 D20 PLUMBING ................................................................................................... 26 D30 HVAC........................................................................................................... 30 D40 FIRE PROTECTION Systems ........................................................................ 33 D50 ELECTRICAL SYSTEMS .............................................................................. 34 G Building Sitework Systems ................................................................................... 36 G20 SITE IMPROVEMENTS ................................................................................ 37 G40 SITE ELECTRICAL Utilities......................................................................... 44

4. Accessibility Issues...................................................................................................... 45

5. General Assessment Information................................................................................. 46

6. Certification................................................................................................................ 47

7. Appendices.................................................................................................................. 48 111948.15R-014.305
.

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT

1. EXECUTIVE S UMMARY

1.1 PROJECT NARRATIVE
Project Description
Item Description
Project Name Main Library
Building ID 14
Property Type LIBRARY
Year Built 1966
Number of Stories 2
Occupied Yes
Land Area (acres) 1.5
Gross Building Area (SF) 30,000
The library property has one, 2-story building containing 30,000 square feet. The site area is approximately

1.5 acres. Construction of the property was completed in 1966.

The building structural system is cast in place concrete. The basement floor is a concrete slab on grade. The roof is flat with a built-up membrane.

The exterior walls are finished with brick veneer.

The building interior has painted drywall walls. Floor finishes consist of commercial carpet tiles, commercial carpet, ceramic tile, vinyl composition tiles “VCT” and unfinished concrete. The interior ceiling is finished with acoustic ceiling tiles and painted drywall / plaster.

The facility is served by one hydraulic passenger elevator.

Domestic hot water is provided to the restrooms, breakroom areas, kitchens and showers by a commercial grade gas water heater located in the mechanical room.

Heating and cooling are provided by a hot water boiler and a pad mounted condenser. Life Safety Systems include fire sprinklers in the basement area, hydrants, smoke detectors, alarms and extinguishers.

The landscaping consists of trees, shrubs, and lawn areas. Flower beds are concentrated around near the building. Landscaped areas are irrigated by an in-ground overhead spray sprinkler system.

The parking areas are paved with asphalt. Based on a physical count parking is provided for 86 cars. All of the parking stalls are located in open lots.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
2 F ACILITY C ONDITION A SSESSMENT
The sidewalks throughout the property are constructed of cast-in-place concrete. Cast-in-place concrete steps and a ramp with metal handrails are located at grade changes.

The major issues contributing to the immediate Repair Needs are related to the following conditions:

Replace very old pad mounted condensing unit.

Various accessibility corrections
Replace wrought iron fence above exterior basement stairwell Elevator modernization
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
3 F ACILITY C ONDITION A SSESSMENT

1.2 SUMMARY OF FINDINGS
The below table represents summary-level findings for the Facility Condition Assessment. The deficiencies identified in this assessment can be combined with potential new construction requirements to develop an overall Long Term Capital Needs Plan that can be the basis for a facility wide capital improvement funding strategy. Key findings from the assessment include:

Key Finding Metric
Facility Condition Index 0.97 %
Current Replacement Value $7,280,625
Immediate Capital Needs (12 months) $70,344
1-5 Year Capital Needs $798,861
6-10 Year Capital Needs $919,426
Total Capital Needs $1,788,631
The chart below provides a summary of yearly anticipated expenditures over the ten-year study period for the building. Further detail on the specific costs that make up the summary can be found in Section 3 and the cost tables in the appendices.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
4 F ACILITY C ONDITION A SSESSMENT

1.3 FACILITY CONDITION INDEX
The Facility Condition Index (FCI) is a comparative industry indicator/benchmark used to indicate the relative physical condition of a facility, group of buildings, or entire portfolio “independent” of building type, construction type, location, or cost. The FCI is expressed as a ratio of the cost of remedying deficiencies/requirements and capital renewal requirements divided by the current building replacement value. The FCI provides a corresponding rule of thumb for the annual reinvestment rate (funding percentage) to prevent further accumulation of deferred maintenance deficiencies. The FCI value is a snapshot in time, calculated on an annual basis. The values are based on a 0-100%+ scale.

Condition Definition Percentage Value
Good In new or well-maintained condition,
with no visual evidence of wear,
soiling or other deficiencies
0% to 5%
Fair Subjected to wear and soiling but is
still in a serviceable and functioning
condition
Greater than 5% to 10%
Poor Subjected to hard or long-term wear.

Nearing the end of its useful or
serviceable life.

Greater than 10% to 60%
Very Poor Subjected to hard or long-term wear.

Has reached the end of its useful or
serviceable life. Renewal is now
necessary.

Greater than 60%
The Chart below indicates the cumulative effects of the FCI ratio over the study period assuming the required funds and expenditures are NOT provided to address the identified repairs and replacements for each year. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
5 F ACILITY C ONDITION A SSESSMENT
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
6 F ACILITY C ONDITION A SSESSMENT

1.4 DISTRIBUTION OF IMMEDIATE NEEDS BY BUILDING SYSTEM
Level Building System Estimated Cost
B3022 Roof Hatches $1,585
D2012 Urinals $4,592
D2014 Sinks $3,696
D3053 Split-Systems $28,144
G2012 Paving & Surfacing $29,230
G2041 Fences & Gates $3,098
Total $70,344
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
7 F ACILITY C ONDITION A SSESSMENT

1.5 DISTRIBUTION OF CAPITAL NEEDS BY BUILDING SYSTEM
Year Building System Estimated Cost
2015 B Shell $1,585
2015 D Services $36,431
2015 G Building Sitework $32,328
2017 C Interiors $117,276
2017 G Building Sitework $26,862
2018 C Interiors $159,683
2018 D Services $322,031
2018 G Building Sitework $44,640
2020 C Interiors $7,975
2020 D Services $91,164
2020 G Building Sitework $29,230
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
8 F ACILITY C ONDITION A SSESSMENT
2022 C Interiors $23,100
2022 D Services $9,434
2022 G Building Sitework $612
2023 C Interiors $33,469
2023 D Services $11,605
2023 G Building Sitework $10,878
2024 B Shell $426,393
2024 C Interiors $157,799
2024 D Services $21,312
2024 G Building Sitework $224,824
Total $1,788,631

1.6 TOTAL CAPITAL NEEDS BY PRIORITY
Another method to plan for replacement of building systems or components is by assigning a priority that is relative to the other systems and components in the building. The priority model used in the analysis takes into account the urgency of the repair, as well as the importance of the system, and the location of the system within the property. Repairs to mission critical systems may have a higher priority than back of house finishes that are in worse condition. The identified repairs or replacement have been prioritized according to the five levels identified in Section 2, with Priority 1 items being the most critical to address.

Based on the results of the ranking calculation derived from the analysis of the variables described above, the asset and component is assigned to one of the following Priority categories. The scale is 1-4 with 1=highest and 4=lowest priority.

Priority 1: Critical: Items under this classification require immediate attention to (a) return a facility to normal operation, (b) address non-functional systems (c) address a safety hazard.

Priority 2: Potentially Critical: Items under this classification require attention in order to prevent a deficiency from becoming critical. Situations include (a) intermittent interruptions to normal operation, (b) rapid deterioration of distressed systems (c) address a safety hazard.

Priority 3: Not Critical: Items under this classification require attention and planning in order to prevent future predictable deterioration or future interruptions to normal operations or items that may result in higher costs if deferred.

Priority 4: Recommended: Items under this classification are not required for normal function and operation of the facility, but would improve efficiency and functionality of the facility or reduce long-term maintenance. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
9 F ACILITY C ONDITION A SSESSMENT
Priority
Building System 1 2 3 4 Total
B Shell $1,585 $0 $0 $426,393 $427,979
C Interiors $0 $394,235 $7,975 $97,093 $499,303
D Services $36,431 $322,031 $91,164 $42,350 $491,976
G Building Sitework $61,558 $71,502 $0 $236,314 $369,373 Totals
$99,574 $787,768 $99,139 $802,150 $1,788,631

1.7 TOTAL CAPITAL NEEDS SORTED BY CATEGORY
In the chart below deficiencies are sorted by categories, which define briefly the reason the need exists. The chart and tables cover a 10-year period. A cost requirement may have more than one applicable category.

The category is selected based on the need priority, the most heavily impacted building system and the category with the greatest life safety significance.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
10 F ACILITY C ONDITION A SSESSMENT
The following is a list of the categories with a brief description:

Code Compliance (CC)
 Accessibility: Conditions that violate the American Disabilities Act guidelines  Building Code: Conditions that violate Building codes  Life Safety: Conditions that violate NFPA 101 Life Safety Code Operations (OP)
 Energy: Conditions that adversely affect energy use
 Maintenance: Components or systems that require routine maintenance  Security: Conditions that compromise the protection of the asset or its occupants Environmental (EN)
 Air/ Water Quality: Conditions that affect air or water quality  Asbestos: Visible observance of suspected asbestos-containing material(ACM)  Lead Visible Observance of suspected lead based paint  PCB: Observance of suspected PCB containing equipment Functionality (FN)
 Mission: Components which do not meet the mission of the organization  Modernization: Conditions that need to made modern in appearance or function  Plant Adaptation: Components or systems that must change to fit a new or adapted use  Obsolescence: Components or systems that are or are becoming obsolete  Capacity: Components or system which cannot meet demand load Integrity (IN)
 Appearance: Problems with the asset’s appearance that are not functional in nature  Reliability: Components or systems that cannot be depended on  Beyond Rated Life: A component or system that has exceeded its rated life 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
11 F ACILITY C ONDITION A SSESSMENT
Category Plan Type Total Cost
Code Compliance CC - Accessibility $322,031
Integrity IN - Beyond Rated Life $1,466,599
Total $1,788,631
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
12 F ACILITY C ONDITION A SSESSMENT

2. PURPOSE AND S COPE

2.1 SCOPE
The evaluation team visited Main Library to evaluate the general condition of the building(s) and site improvements, reviewed available construction documents in order to familiarize themselves with the physical conditions, setting and be able to comment on the in-place construction systems, life safety, mechanical, electrical and plumbing systems, and the general built environment. The evaluation team conducted a walk-through survey of the building(s) in order to observe building systems and components, identify physical deficiencies and formulate recommendations to remedy the physical deficiencies.  As a part of the walk-through survey, the evaluation team surveyed 100% of the facility’s interior. In addition, EMG surveyed the exterior of the properties including the building exterior and roofs.  The evaluation team interviewed the building maintenance staff to inquire about the subject property’s historical repairs and replacements and their costs, level of preventive maintenance exercised, pending repairs and improvements, and frequency of repairs and replacements.  The evaluation team developed opinions based on their site evaluation, interviews with relevant maintenance contractors, municipal authorities, and experience gained on similar properties previously evaluated. The evaluation team questioned others who are knowledgeable of the subject property’s physical condition and operation or knowledgeable of similar systems to gain comparative information to use in evaluation of the subject property.

The Client contracted with EMG to conduct a Facility Condition Assessment (FCA) consisting of field observations, document review and related due diligence tasks of the subject property. The Facility Assessment will:
 Determine the present condition and estimated life expectancy of various building systems and components.
 Result in strategic plan for capital repairs, lifecycle component replacement and building modernization.  Establish a standard operating procedure for the evaluation of facilities by establishing a standard facility assessment software platform. Establish anticipated renewal and replacement costs for the various systems and components.
 Identify and document present condition of all physical assets with recommended corrections for all deficiencies and provide cost estimates for corrections. Prioritize, categorize and classify deficient conditions, associated corrective actions and information concerning building systems and deficiency categories.
 Coordinate and consult with the updates to the master plan for prioritization of projects. The FCA will be a guide for future replacement, repairs and improvements and to assist DGS in prioritizing its capital budget and expenditures across its real estate portfolio.
 Calculate the Current Replacement Value (CRV) and Facility Condition Index (FCI) for each facility and extend that calculation over a 10-year period.

2.2 PURPOSE
The goal of the FCA is to gather the data necessary to understand the existing facility’s condition, identify strategies to meet the facility’s life cycle needs and create the foundation for an overall capital plan. The facility condition assessment includes the following:
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
13 F ACILITY C ONDITION A SSESSMENT
 Current conditions analyses - existing facility requirements including deferred maintenance, recommended discretionary improvements, and code noncompliance issues.  Anticipated facility reserve analyses - projections of ongoing degradation of facilities' components and costs associated with the reserve or replacement of these components as they reach the end of their useful lives
 Funding needs analysis - summary report of deferred maintenance and systems reserves funding needs.

The physical condition of building systems and related components are typically defined as being in one of three conditions: Good, Fair, or Poor, or a combination thereof. For the purposes of this report, the following definitions are used:

Good = In well-maintained condition. Requires only routine maintenance over the assessment period.

Repair or replacement may be required due to a system’s estimated useful life.

Fair = Satisfactory as-is. Repair or replacement is required due to current physical condition and/or estimated remaining useful life. Still in serviceable condition and functioning.

Poor = Immediate repair, replacement, or significant maintenance is required. Nearing the end of its useful life.

Very
Poor
= Non-working item requires immediate full replacement, repairs not possible.

EMG’s calculation of probable capital needs methodology involves identification and quantification of those systems or components requiring immediate actions or capital funding reserves over the lifecycle horizon of the facility key components. The component is segregated into two categories “Immediate Repairs” and “Capital Reserve” defined as follows:

2.2.1 Probable Capital Needs - Immediate Repairs
Immediate repairs are opinions of probable costs that require immediate action as a result of: (1) material existing or potential unsafe conditions, (2) material building or fire code violations, or (3) conditions that, if left un-remedied, have the potential to result in or contribute to critical element or system failure within one year, or will most probably result in a significant escalation of its remedial cost. Immediate repair costs are items which require action in year one.

2.2.2 Probable Capital Needs - Capital Reserves
Capital Reserves are for recurring probable expenditures that are not classified as operation or maintenance expenses. The modified capital reserves should be budgeted for in advance on an annual basis. Capital reserves are reasonably predictable both in terms of frequency and cost. However, capital reserves may also include components or systems that have an indeterminable life but nonetheless have a potential liability for failure within 10-year reserve period.

2.2.3 Remaining Useful Life Estimate
Based upon site observations, research, and judgment, along with referencing Expected Useful Life (EUL) tables from various industry sources, EMG opines as to when a system or component will most probably necessitate replacement. Exposure to the elements, initial quality and installation, extent of use, the quality and amount of preventive maintenance exercised, etc., are all factors that impact the effective age of a system or component. As a result, a system or component may have an effective age that is greater or less than its 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
14 F ACILITY C ONDITION A SSESSMENT
actual chronological age. The Remaining Useful Life (RUL) of a component or system equals the EUL less its effective age.

2.2.4 Opinions Of Probable Cost
Estimates for individual repair and replacements are a key part of this engagement. These estimates are based on invoice or bid documents provided by the Owner/facility or construction cost estimates developed by construction resources such as R.S. Means, EMG's experience with past costs for similar properties, city cost indexes, and assumptions regarding future economic conditions. Where quantities could not be derived from an actual take-off, lump sum costs or allowances are utilized.

Opinions of probable costs should only be construed as preliminary, order of magnitude budgets. Actual costs most probably will vary from the consultant’s opinions of probable costs depending on such matters as type and design of suggested remedy, quality of materials and installation, manufacturer and type of equipment or system selected, field conditions, whether a physical deficiency is repaired or replaced in whole, phasing of the work (if applicable), quality of contractor, market conditions, and whether competitive pricing is solicited, etc. ASTM E2018-08 recognizes that certain opinions of probable costs cannot be developed within the scope of this guide without further study. Opinions of probable cost for further study should be included in the PCR.

2.2.5 Priority Ranking
EMG recorded existing conditions, identified problems and deficiencies, documented corrective action and quantities of recommended repairs and/or replacements. During the assessment the collected data is entered directly into the EMG assessment and capital planning database using tablet computers. Based on the analysis of the collected data a Priority Ranking is calculated for each item observed. The Priority Ranking calculation is a function of four key facility variables to include:

1. Building Mission Ranking – if the building is one of multiple buildings at the facility, each building is ranked on a scale of 1-10 based on conversations with the client. This rank helps defines the importance of each building to the overall mission of the facility. For example the building containing the administrative and executive offices for the subject property will carry a higher ranked importance than the building than the parking garage. However, if the parking garage is used for Mission Critical or emergency services vehicles than it will have a higher priority than the office building. Both are required for the operation of the facility but ranking is adjusted based on the use of the buildings and the mission of the overall facility.

2. Remaining Useful Life Ranking – the estimated useful life (EUL) projection of the component is calibrated against the remaining useful life (RUL) as estimated by EMG field assessor. This ratio is then utilized as a factor in the priority ranking.

3. Asset Component Category – each material or system (asset) evaluated is assigned a unique Uniformat code. The Uniformat designation is then associated with a ranking based on the overall importance to the operation of the facility. An asset that is a related to building envelope, e.g. roof, window, exterior siding, is assigned a higher ranking than a component such a flooring, carpeting or other finish material.

4. Functional Asset Categories – the cost associated with each asset or component evaluated is assigned to a category to include; Code Compliance, Facility Operations, Environmental Factors, Facility Functionality and Integrity of the Facility.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
15 F ACILITY C ONDITION A SSESSMENT

3. FACILITY C ONDITION ASSESSMENT

A SUBSTRUCTURE SYSTEMS
A10 FOUNDATIONS
Item Description
A1031 Standard Slab on Grade A1032 Concrete Slab On Grade Condition Fair
Qty / UOM 13700 / SF
RUL (years) 16
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

B SHELL SYSTEMS
B10 SUPERSTRUCTURE
Item Description
B1012 Upper Floors Construction B1012 Post tensioned concrete Condition Fair
Qty / UOM 14800 / SF
RUL (years) 16
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
16 F ACILITY C ONDITION A SSESSMENT
B20 EXTERIOR ENCLOSURE
Item Description
B2011 Exterior Wall Construction B2011 Brick Veneer
Condition Fair
Qty / UOM 9600 / SF
RUL (years) 16
Location Exterior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
B2021 Windows B2021 Aluminum Window 4' X 6'
Condition Fair
Qty / UOM 93 / EA
RUL (years) 13
Location Exterior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
B2021 Windows B2021 Aluminum Window (+20 Sf)
Condition Fair
Qty / UOM 93 / EA
RUL (years) 12
Location Exterior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
17 F ACILITY C ONDITION A SSESSMENT
Item Description
B2031 Glazed Doors & Entrances B2031 Glazed Entrance Doors Condition Fair
Qty / UOM 6 / EA
RUL (years) 16
Location Exterior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
B2032 Solid Exterior Doors B2022 3’-0” X 7’-0” Steel, Insulated Core, Ptd.

Door
Condition Fair
Qty / UOM 6 / EA
RUL (years) 16
Location Exterior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

B30 ROOFING
Item Description
B3011 Roof Finishes B3011 Built-Up Roofing
Condition Fair
Qty / UOM 184 / SQ
RUL (years) 9
Location Rooftop
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
18 F ACILITY C ONDITION A SSESSMENT
Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) B3011 Replace B3011
Built-Up Roofing
184.0 - SQ 2277.7 IN - Beyond
Rated Life
Priority 4 2024 419,100
Item Description
B3016 Gutters and Downspouts B3016 Roof Drains And Interior Leaders Condition Fair
Qty / UOM 160 / LF
RUL (years) 9
Location Rooftop
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) B3016 Replace B3016
Roof Drains And
Interior Leaders
160.0 - LF 17.4 IN - Beyond
Rated Life
Priority 4 2024 2,790
Item Description
B3021 Glazed Roof Openings B3021 Plexi-Glass Skylight 20 To 30 Sf Condition Fair
Qty / UOM 90 / SF
RUL (years) 9
Location Rooftop
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
19 F ACILITY C ONDITION A SSESSMENT
Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) B3021 Replace B3021
Plexi-Glass
Skylight 20 To 30
Sf

90.0 - SF 50.0 IN - Beyond
Rated Life
Priority 4 2024 4,503
Item Description
B3022 Roof Hatches B3022 Galvanized Steel Hatch
Condition Fair
Qty / UOM 1 / EA
RUL (years) 0
Location Rooftop
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) B3022 Replace B3022
Galvanized Steel
Hatch

1.0 - EA 1585.1 IN - Beyond
Rated Life
Priority 1 2015 1,585
Cost Summary:

Year Total Expenditures
2015 $1,585
2024 $426,393

C INTERIORS SYSTEMS
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
20 F ACILITY C ONDITION A SSESSMENT
C10 INTERIOR CONSTRUCTION
Item Description
C1011 Fixed Partitions C1011 Toilet Room Partitions Overhead Braced Condition Fair
Qty / UOM 6 / EA
RUL (years) 5
Location Interior, restrooms
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C1011 Replace C1011
Toilet Room
Partitions Overhea
d Braced

6.0 - EA 1329.2 IN - Beyond
Rated Life
Priority 3 2020 7,975
Item Description
C1013 Retractable Partitions C1011 Folding Accordian Partition Condition Fair
Qty / UOM 600 / SF
RUL (years) 8
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C1013 Replace C1011
Folding Accordian
Partition
600.0 - SF 55.8 IN - Beyond
Rated Life
Priority 4 2023 33,469
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
21 F ACILITY C ONDITION A SSESSMENT
Item Description
C1021 Interior Doors C1021 Interior Door
Condition Fair
Qty / UOM 43 / EA
RUL (years) 16
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Cost Summary:

Year Total Expenditures
2020 $7,975
2023 $33,469
C30 INTERIOR FINISHES
Item Description
C3012 Wall Finishes to Interior Walls C3012 Paint Interior Walls, Drywall Condition Fair
Qty / UOM 92140 / SF
RUL (years) 2
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C3012 Replace C3012
Paint Interior
Walls, Drywall
92,140.0 -
SF

1.3 IN - Beyond
Rated Life
Priority 2 2017 117,276
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
22 F ACILITY C ONDITION A SSESSMENT
C3012 Replace C3012
Paint Interior
Walls, Drywall
92,140.0 -
SF

1.3 IN - Beyond
Rated Life
Priority 2 2024 117,276
Item Description
C3012 Wall Finishes to Interior Walls C3012 Ceramic Tile, Low Walls Condition Fair
Qty / UOM 2000 / SF
RUL (years) 16
Location Interior, restrooms
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
C3024 Flooring C3024 2X2 Ceramic Tile
Condition Fair
Qty / UOM 1900 / SF
RUL (years) 9
Location Interior, restrooms
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C3024 Replace C3024
2X2 Ceramic Tile
1,900.0 - SF 21.3 IN - Beyond
Rated Life
Priority 4 2024 40,524
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
23 F ACILITY C ONDITION A SSESSMENT
Item Description
C3024 Flooring C3024 Vinyl Tile
Condition Fair
Qty / UOM 670 / SY
RUL (years) 3
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Site staff reports that this flooring ins Asbestos Containing Material.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C3024 Replace C3024
Vinyl Tile
670.0 - SY 85.0 IN - Beyond
Rated Life
Priority 2 2018 56,954
Item Description
C3024 Flooring C3024 Sheet Vinyl
Condition Fair
Qty / UOM 167 / SY
RUL (years) 7
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Site staff reports that this flooring ins Asbestos Containing Material.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C3024 Replace C3024
Sheet Vinyl
167.0 - SY 138.3 IN - Beyond
Rated Life
Priority 4 2022 23,100
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
24 F ACILITY C ONDITION A SSESSMENT
Item Description
C3025 Carpeting C3025 Carpeting
Condition Fair
Qty / UOM 2000 / SY
RUL (years) 3
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) C3025 Replace C3025
Carpeting
2,000.0 -
SY

51.4 IN - Beyond
Rated Life
Priority 2 2018 102,730
Item Description
C3031 Ceiling Finishes C3031 Drywall – Painted Finished Ceilings Condition Fair
Qty / UOM 19500 / SF
RUL (years) 16
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
25 F ACILITY C ONDITION A SSESSMENT
Item Description
C3032 Suspended Ceilings C3032 Acoustical Ceiling Tile
Condition Fair
Qty / UOM 10500 / SF
RUL (years) 10
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Cost Summary:

Year Total Expenditures
2017 $117,276
2018 $159,683
2022 $23,100
2024 $157,799

D SERVICES SYSTEMS
D10 CONVEYING SYSTEMS
Item Description
D1011 Passenger Elevators D1011 Elevator Hydraulic System 1,500 Lb Condition Poor
Qty / UOM 2 / EA
RUL (years) 3
Location Mechanical Room
Observations/Comments:

Based on its current condition of inadequate turning area for wheelchairs and other accessibility deficiencies, this asset is recommended to be replaced in the near term. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
26 F ACILITY C ONDITION A SSESSMENT
Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D1011 Replace D1011
Elevator Hydraulic
System 1,500 Lb

2.0 - EA 161015
.7
CC -
Accessibility
Priority 2 2018 322,031
Item Description
D1094 Conveyors D1094 Conveyors
Condition Good
Qty / UOM 75 / LF
RUL (years) 10
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Summary:

Year Total Expenditures
2018 $322,031
D20 PLUMBING
Item Description
D2011 Water Closets D2011 Commercial Grade Water Closet With 1.6 Gpf Unit
Condition Fair
Qty / UOM 9 / EA
RUL (years) 11
Location Interior, restrooms
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
27 F ACILITY C ONDITION A SSESSMENT
Item Description
D2012 Urinals D2012 Urinal
Condition Fair
Qty / UOM 3 / EA
RUL (years) 0
Location Interior, restrooms
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D2012 Replace D2012
Urinal

3.0 - EA 1530.6 IN - Beyond
Rated Life
Priority 1 2015 4,592
Item Description
D2013 Lavatories D2013 China Wall Hung Lavatory And Faucet Condition Fair
Qty / UOM 12 / EA
RUL (years) 8
Location Interior, restrooms
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D2013 Replace D2013
China Wall Hung
Lavatory And
Faucet

12.0 - EA 967.0 IN - Beyond
Rated Life
Priority 4 2023 11,605
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
28 F ACILITY C ONDITION A SSESSMENT
Item Description
D2014 Sinks D2014 Kitchen Sink
Condition Fair
Qty / UOM 2 / EA
RUL (years) 0
Location Interior, kitchen
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D2014 Replace D2014
Kitchen Sink

2.0 - EA 1847.8 IN - Beyond
Rated Life
Priority 1 2015 3,696
Item Description
D2014 Sinks D2014 Janitorial Sink
Condition Fair
Qty / UOM 2 / EA
RUL (years) 11
Location Utility closet
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
29 F ACILITY C ONDITION A SSESSMENT
Item Description
D2017 Showers D2017 Stall Shower And Faucet
Condition Fair
Qty / UOM 4 / EA
RUL (years) 16
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Showers not in use. No action recommended.

Item Description
D2018 Drinking Fountains and Coolers D2018 Drinking Fountain Condition Fair
Qty / UOM 2 / EA
RUL (years) 7
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D2018 Replace D2018
Drinking Fountain

2.0 - EA 1768.6 IN - Beyond
Rated Life
Priority 4 2022 3,537
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
30 F ACILITY C ONDITION A SSESSMENT
Item Description
D2022 Hot Water Service D2022 Commercial Gas Water Heater 74-Gallon Condition Good
Qty / UOM 1 / EA
RUL (years) 13
Location Mechanical Room
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Cost Summary:

Year Total Expenditures
2015 $8,287
2022 $3,537
2023 $11,605
D30 HVAC
Item Description
D3011 Oil Supply System D3011 Fuel Tank, Above Ground - Concrete and Steel - 1,000 Gal
Condition Fair
Qty / UOM 1 / EA
RUL (years) 5
Location Site
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
31 F ACILITY C ONDITION A SSESSMENT
Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D3011 Replace D3011
Fuel Tank, Above
Ground - Concrete
and Steel - 1,000
Gal

1.0 - EA 7843.7 IN - Beyond
Rated Life
Priority 3 2020 7,844
Item Description
D3021 Boilers D3021 High Efficiency Water Boiler, Gas 750 Mbh
Condition Good
Qty / UOM 1 / EA
RUL (years) 29
Location Mechanical Room
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
D3041.1 Air Handling Units D3041.1 AHU, 7.5 Hp Fan Motor Condition Fair
Qty / UOM 2 / EA
RUL (years) 9
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D3041 Replace D3041.1
AHU, 7.5 Hp Fan
Motor

2.0 - EA 10656.
0 IN - Beyond
Rated Life
Priority 4 2024 21,312
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
32 F ACILITY C ONDITION A SSESSMENT
Item Description
D3053 Split-Systems D3053 Split System Unit, 12-Ton, Condenser And Fan Coil
Condition Poor
Qty / UOM 1 / EA
RUL (years) 0
Location Exterior
Observations/Comments:

Based on its current condition of well beyond its expected useful life and site contact comments about the poor quality of cooling climate control in the facility, this asset is recommended to be replaced at this time.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D3053 Replace D3053
Split System Unit,
12-Ton, Condenser
And Fan Coil

1.0 - EA 28143.
8 IN - Beyond
Rated Life
Priority 1 2015 28,144
Cost Summary:

Year Total Expenditures
2015 $28,144
2020 $7,844
2024 $21,312
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
33 F ACILITY C ONDITION A SSESSMENT
D40 FIRE PROTECTION Systems
Item Description
D4015 FIRE PROTECTION D4015 Extinguishing System, Dry Pipe Condition Fair
Qty / UOM 12300 / SF
RUL (years) 11
Location Interior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
D4095 Hood & Duct Fire Protection D4095 Hood & Duct Fire Protection Condition Fair
Qty / UOM 1 / EA
RUL (years) 5
Location Interior, kitchen
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D4095 Replace D4095
Hood & Duct Fire
Protection

1.0 - EA 38449.
5 IN - Beyond
Rated Life
Priority 3 2020 38,450
Cost Summary:

Year Total Expenditures
2020 $38,450
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
34 F ACILITY C ONDITION A SSESSMENT
D50 ELECTRICAL SYSTEMS
Item Description
D5012 Low Tension Service & Dist. D5012 Switchgear, Mainframe <600 Amps Condition Fair
Qty / UOM 1 / EA
RUL (years) 11
Location Mechanical Room
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
D5012 Low Tension Service & Dist. D5012 Breaker Panel 225 Amps, 30 Circuits Condition Fair
Qty / UOM 6 / EA
RUL (years) 11
Location Mechanical Room
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
D5037 Fire Alarm Systems D5037 Fire Alarm Panel
Condition Fair
Qty / UOM 1 / EA
RUL (years) 7
Location Interior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
35 F ACILITY C ONDITION A SSESSMENT
Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D5037 Replace D5037
Fire Alarm Panel

1.0 - EA 5896.5 IN - Beyond
Rated Life
Priority 4 2022 5,896
Item Description
D5092 Emergency Light & Power Systems D5092 Diesel Generator 10 Kw Condition Fair
Qty / UOM 1 / EA
RUL (years) 5
Location Mechanical Room
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D5092 Replace D5092
Diesel Generator
10 Kw

1.0 - EA 31820.
0 IN - Beyond
Rated Life
Priority 3 2020 31,820
Item Description
D5092 Emergency Light & Power Systems D5092 Transfer Switch Condition Fair
Qty / UOM 2 / EA
RUL (years) 5
Location Mechanical Room
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
36 F ACILITY C ONDITION A SSESSMENT
Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D5092 Replace D5092
Transfer Switch

2.0 - EA 6525.1 IN - Beyond
Rated Life
Priority 3 2020 13,050
Cost Summary:

Year Total Expenditures
2020 $44,870
2022 $5,896

G BUILDING SITEWORK SYSTEMS
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
37 F ACILITY C ONDITION A SSESSMENT
G20 SITE IMPROVEMENTS
Site Information
Item Description
Main Ingress and Egress West Orange Avenue
Access from E
Additional Entrances N/A
Access from N/A
Parking Count: Open lot 86
Parking Count: Sheltered by carports 0
Parking Count: Private garages 0
Parking Count: Subterranean garage 0
Parking Count: Freestanding parking structure 0
Number of ADA Compliant Spaces 4
Number of ADA Compliant Spaces for Vans 1
Method of obtaining parking count Physical count
Property Identification Sign-Primary N/A
Property Identification Sign- Secondary N/A
Illuminated Identification Signage N/A
Building Identification Sign Yes
Illuminated Sign No
Location of Property ID Sign N/A
Trees Present N/A
Shrubs Present Yes
Grasses Present Yes
Flower beds Present Yes
Decorative Rocks Present No
Lava Rocks Present No
Ponds Present No
Fountains Present No
Topography Gently sloping
Item Description
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
38 F ACILITY C ONDITION A SSESSMENT
Item Description
G2012 Paving & Surfacing G2012 Asphalt Crack Seal, Seal and Stripe Condition Fair
Qty / UOM 39500 / SF
RUL (years) 0
Location Site
Observations/Comments:

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2012 Replace G2012
Asphalt Crack Seal,
Seal and Stripe
39,500.0 -
SF

0.7 IN - Beyond
Rated Life
Priority 1 2015 29,230
G2012 Replace G2012
Asphalt Crack Seal,
Seal and Stripe
39,500.0 -
SF

0.7 IN - Beyond
Rated Life
Priority 1 2020 29,230
Item Description
G2012 Paving & Surfacing G2012 Asphalt Pavement
Condition Fair
Qty / UOM 39600 / SF
RUL (years) 9
Location Site
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2012 Replace G2012
Asphalt Pavement
39,600.0 -
SF

4.9 IN - Beyond
Rated Life
Priority 4 2024 192,234
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
39 F ACILITY C ONDITION A SSESSMENT
Item Description
G2012 Paving & Surfacing G2012 Concrete Pavement
Condition Fair
Qty / UOM 2200 / SF
RUL (years) 2
Location Site
Observations/Comments:

Based on its current condition of cracking and normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2012 Replace G2012
Concrete
Pavement
2,200.0 - SF 12.2 IN - Beyond
Rated Life
Priority 2 2017 26,862
Item Description
G2031 Paving & Surfacing G2031 Concrete Sidewalk, 3’ To 5’ Wide Condition Fair
Qty / UOM 3300 / SF
RUL (years) 3
Location Site
Observations/Comments:

Based on its current condition of cracking and normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2031 Replace G2031
Concrete Sidewalk,
3’ To 5’ Wide
3,300.0 - SF 13.5 IN - Beyond
Rated Life
Priority 2 2018 44,640
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
40 F ACILITY C ONDITION A SSESSMENT
Item Description
G2035 Exterior Steps & Ramps G2035 Exterior Cast in Place Ramp with handrails Condition Fair
Qty / UOM 110 / LF
RUL (years) 20
Location Site
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
G2035 Exterior Steps & Ramps G2036 Cast-In-Place Concrete Stair Condition Fair
Qty / UOM 60 / LF
RUL (years) 7
Location Site
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2035 Replace G2036
Cast-In-Place
Concrete Stair

60.0 - LF 10.2 IN - Beyond
Rated Life
Priority 4 2022 612
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
41 F ACILITY C ONDITION A SSESSMENT
Item Description
G2041 Fences & Gates G2041 Wrought Iron Fence 3’ High
Condition Poor
Qty / UOM 72 / LF
RUL (years) 0
Location Site
Observations/Comments:

The asset is is a safety railing above a pathway to a basement door. the asset is damaged, improperly secured and has too wide of spacing between uprights. It should be replaced immediately.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2041 Replace G2041
Wrought Iron
Fence 3’ High

72.0 - LF 43.0 IN - Beyond
Rated Life
Priority 1 2015 3,098
Item Description
G2041 Fences & Gates G2041 Masonry Wall
Condition Fair
Qty / UOM 600 / SF
RUL (years) 16
Location Site
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended. However, the west end of wall is damaged. Should be repaired in the near term. 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
42 F ACILITY C ONDITION A SSESSMENT
Item Description
G2042 Retaining Walls G2042 Retaining Wall, Cast In Place Concrete, Reinforced, Up To 6’ High, No Shoring Or
Protection
Condition Fair
Qty / UOM 170 / LF
RUL (years) 16
Location Exterior
Observations/Comments:

Based on its current condition and Remaining Useful Life, no further action is recommended.

Item Description
G2045 SITE GATES G2045 Wrought Iron Manual Swing Gate, double Condition Fair
Qty / UOM 2 / EA
RUL (years) 8
Location Exterior
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2045 Replace G2045
Wrought Iron
Manual Swing
Gate, double

2.0 - EA 5439.0 IN - Beyond
Rated Life
Priority 4 2023 10,878
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
43 F ACILITY C ONDITION A SSESSMENT
Item Description
G2048 Flagpoles G2048 Flag Pole, Fiberglass - 45’ High
Condition Fair
Qty / UOM 2 / EA
RUL (years) 9
Location Site
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G2048 Replace G2048
Flag Pole,
Fiberglass - 45’
High

2.0 - EA 7539.3 IN - Beyond
Rated Life
Priority 4 2024 15,079
Cost Summary:

Year Total Expenditures
2015 $32,328
2017 $26,862
2018 $44,640
2020 $29,230
2022 $612
2023 $10,878
2024 $207,313
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
44 F ACILITY C ONDITION A SSESSMENT
G40 SITE ELECTRICAL Utilities
Item Description
G4022 Poles G4022 Aluminum Light Pole, Over 15 Ft. And
Double Fixture
Condition Fair
Qty / UOM 4 / EA
RUL (years) 9
Location Site
Observations/Comments:

Based on its current condition of normal deterioration due to age and use, this asset should be anticipated to be replaced during the assessment term.

Cost Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) G4022 Replace G4022
Aluminum Light
Pole, Over 15 Ft.

And Double
Fixture

4.0 - EA 4377.8 IN - Beyond
Rated Life
Priority 4 2024 17,511
Cost Summary:

Year Total Expenditures
2024 $17,511
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
45 F ACILITY C ONDITION A SSESSMENT

4. ACCESSIBILITY ISSUES
Item Description
D1011 Passenger Elevators D1011 Elevator Hydraulic System 1,500 Lb Condition Poor
Qty / UOM 2 / EA
RUL (years) 3
Location Mechanical Room
Recommendations:

Type Component
Description Qty / UOM Unit Cost($) Plan Type Priority Year Expenditures($) D1011 Replace D1011
Elevator Hydraulic
System 1,500 Lb

2.0 - EA 161015.
7 CC -
Accessibility
Priority 2 2018 322,031
Cost Summary:

Year Total Expenditures
2018 $322,031
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
46 F ACILITY C ONDITION A SSESSMENT

5. GENERAL ASSESSMENT I NFORMATION
The weather at the time of the assessment was:

The documentation provided at the time of the assessment is as:

Item Description
Site Plan Reviewed Yes
Floor Plan Reviewed Yes
Construction Drawings
Reviewed
No
Boiler Certificates Reviewed No
Document Year Built
Information Obtained From
South San Francisco Website
Item Description
Approximate Outdoor
Temperature (degrees F)
60 Weather Conditions Cloudy
Snow Covering Ground No
Wind Conditions Light Winds
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
47 F ACILITY C ONDITION A SSESSMENT

6. CERTIFICATION
EMG has completed a Facility Condition Assessment (FCA) of the subject property listed on the cover page.

The FCA was performed at the Client's request using methods and procedures consistent with good commercial and customary practice conforming with ASTM E2018-08, Standard Guide for Property Condition Assessments: Baseline Property Condition Assessment Process. Within this Property Condition Report (PCR), EMG's reference to the Client follows the ASTM guide's definition of User, that is, the party that retains EMG for the preparation of a baseline PCA of the subject property.

This report is exclusively for the use and benefit of the Client identified on the first page of this report. The purpose for which this report shall be used shall be limited to the use as stated in the contract between the client and EMG.

The opinions EMG expresses in this report were formed utilizing the degree of skill and care ordinarily exercised by any prudent architect or engineer in the same community under similar circumstances. EMG assumes no responsibility or liability for the accuracy of information contained within this report that has been obtained from the Client or the Client's representatives, from other interested parties, or from the public domain. The conclusions presented represent EMG's professional judgment based on information obtained during the course of this assignment. EMG's evaluations, analyses, and opinions are not representations regarding the building design, structural soundness, or actual value of the property. Factual information regarding operations, conditions, and test data provided by the Client or the Client's representative has been assumed to be correct and complete. The conclusions presented within this report are based on the data provided, observations made, and conditions that existed specifically on the date of the assessment. EMG certifies that EMG has no undisclosed interest in the subject property, that EMG's relationship with the Client is at arms-length, and that EMG's employment and compensation are not contingent upon the findings or estimated costs to remedy any noted deficiencies due to deferred maintenance and/or any noted component or system replacements.

EMG's FCA cannot wholly eliminate the uncertainty regarding the presence of physical deficiencies and/or the performance of a subject property's building systems. Preparation of a FCA in accordance with ASTM E2018-08 is intended to reduce, but not eliminate, the uncertainty regarding the potential for component or system failure and to reduce the potential that such component or system failure may not be initially observed. This FCA was prepared recognizing the inherent subjective nature of EMG's opinions as to such issues as workmanship, quality of original installation, and estimating the remaining useful life of any given component or system. It should be understood that EMG's suggested remedy may be determined under time constraints or may be formed without the aid of engineering calculations, testing, exploratory probing, the removal of materials, or design. Furthermore, there may be other alternate or more appropriate schemes or methods to remedy the noted physical deficiencies. EMG's opinions are generally formed without detailed knowledge from individuals familiar with the performance of noted components or systems.

Any questions regarding this report should be directed to the Program Manager listed on the cover page of this report.

Prepared By: Butch Butcher, Field Observer
Reviewed By: __________________________
Mark Surdam, Reviewer for
Matthew Anderson, Program Manager
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
48 F ACILITY C ONDITION A SSESSMENT

7. APPENDICES
APPENDIX A: Photographic Record
APPENDIX B: Site Plan
APPENDIX C: Cost Tables
APPENDIX D: Supporting Documentation
APPENDIX E: Pre-Survey Questionnaire
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com
49 F ACILITY C ONDITION A SSESSMENT
APPENDIX A:

PHOTOGRAPHIC RECORD
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
A1031 Standard Slab on Grade.1 B1012 Upper Floors Construction.1 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
B2011 Exterior Wall Construction.1 B2021 Windows.1
B2021 Windows.1 B2031 Glazed Doors & Entrances.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
B2032 Solid Exterior Doors.1 B3011 Roof Finishes.1
B3016 Gutters and Downspouts.1 B3021 Glazed Roof Openings.1 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
B3022 Roof Hatches.1 C1011 Fixed Partitions.1
C1013 Retractable Partitions.1 C1021 Interior Doors.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
C3012 Wall Finishes to Interior Walls.1 C3012 Wall Finishes to Interior Walls.1 C3024 Flooring.1 C3024 Flooring.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
C3024 Flooring.1 C3025 Carpeting.1
C3025 Carpeting.2 C3031 Ceiling Finishes.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
C3032 Suspended Ceilings.1 D1011 Passenger Elevators.1
D1011 Passenger Elevators.2 D1094 Conveyors.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
D2011 Water Closets.1 D2012 Urinals.1
D2013 Lavatories.1 D2014 Sinks.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
D2014 Sinks.1 D2017 Showers.1
D2018 Drinking Fountains and Coolers.1 D2022 Hot Water Service.1 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
D3011 Oil Supply System.1 D3021 Boilers.1
D3041.1 Air Handling Units.1 D3053 Split-Systems.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
D4015 FIRE PROTECTION.1 D4095 Hood & Duct Fire Protection.1 D5012 Low Tension Service & Dist..1 D5012 Low Tension Service & Dist..1 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
D5037 Fire Alarm Systems.1 D5037 Fire Alarm Systems.2
D5092 Emergency Light & Power Systems.1 D5092 Emergency Light & Power Systems.1 111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
G2012 Paving & Surfacing.1 G2012 Paving & Surfacing.1
G2012 Paving & Surfacing.1 G2031 Paving & Surfacing.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
G2031 Paving & Surfacing.2 G2035 Exterior Steps & Ramps.1 G2035 Exterior Steps & Ramps.1 G2041 Fences & Gates.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
G2041 Fences & Gates.1 G2041 Fences & Gates.2
G2042 Retaining Walls.1 G2045 SITE GATES.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
G2048 Flagpoles.1 G4022 Poles.1
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
APPENDIX B:

SITE PLAN
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
Source:

The north arrow indicator is an
approximation of 0° North.

Project Number:
111948.15R 014.305
Project Name:

Main Library
On-Site Date:
5/27/15
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
APPENDIX C:

COST TABLES
Element No. Component Description Asset Location Action Estimated Useful
Life or
Replacement Cycle
(Yrs)
Remaining Useful
Life (Yrs) Quantity Unit of Measurement Unit Cost Plan Type Priority 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Total Total 0123456789
Deferred Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Deferred Scheduled $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
B30 ROOFINGB3011 Built-Up Roofing, Total Roof B3011 Built-Up Roofing Rooftop Replace B3011 Built-Up Roofing 20 9 184.00 SQ $2,277.72 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $419,100 $0 $419,100B3016 Roof Drains And Interior Leaders B3016 Roof Drains And Interior Leaders Rooftop Replace B3016 Roof Drains And Interior Leaders 20 9 160.00 LF $17.43 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,790 $0 $2,790B3021 Plexi-Glass Skylight 20 To 30 Sf B3021 Plexi-Glass Skylight 20 To 30 Sf Rooftop Replace B3021 Plexi-Glass Skylight 20 To 30 Sf 20 9 90.00 SF $50.04 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,503 $0 $4,503B3022 Galvanized Steel Hatch B3022 Galvanized Steel Hatch Rooftop Replace B3022 Galvanized Steel Hatch 30 0 1.00 EA $1,585.08 IN - Beyond Rated Life Priority 1 $1,585 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,585 $0 $1,585 $0 $0 $0 $0 $0 $0 $0 $0 $426,393 $1,585 $426,393 C10 INTERIOR CONSTRUCTIONC1011 Toilet Room Partitions Overhead Braced C1011 Toilet Room Partitions Overhead Braced Interior, restrooms Replace C1011 Toilet Room Partitions Overhead Braced 10 5 6.00 EA $1,329.20 IN - Beyond Rated Life Priority 3 $0 $0 $0 $0 $0 $7,975 $0 $0 $0 $0 $0 $7,975C1013 Folding Accordian Partition C1011 Folding Accordian Partition Interior Replace C1011 Folding Accordian Partition 15 8 600.00 SF $55.78 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $33,469 $0 $0 $33,469C30 INTERIOR FINISHESC3012 Paint Interior Walls, Drywall C3012 Paint Interior Walls, Drywall Interior Replace C3012 Paint Interior Walls, Drywall 7 2 92,140.00 SF $1.27 IN - Beyond Rated Life Priority 2 $0 $0 $117,276 $0 $0 $0 $0 $0 $0 $117,276 $0 $234,552C3024 Sheet Vinyl C3024 Sheet Vinyl Interior Replace C3024 Sheet Vinyl 15 7 167.00 SY $138.33 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $23,100 $0 $0 $0 $23,100C3024 2X2 Ceramic Tile C3024 2X2 Ceramic Tile Interior, restrooms Replace C3024 2X2 Ceramic Tile 30 9 1,900.00 SF $21.33 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $40,524 $0 $40,524C3024 Vinyl Tile C3024 Vinyl Tile Interior Replace C3024 Vinyl Tile 18 3 670.00 SY $85.01 IN - Beyond Rated Life Priority 2 $0 $0 $0 $56,954 $0 $0 $0 $0 $0 $0 $0 $56,954C3025 Carpet, Standard Commercial, Medium Traffic C3025 Carpeting Interior Replace C3025 Carpeting 8 3 2,000.00 SY $51.36 IN - Beyond Rated Life Priority 2 $0 $0 $0 $102,730 $0 $0 $0 $0 $0 $0 $0 $102,730 $0 $0 $117,276 $159,683 $0 $7,975 $0 $23,100 $33,469 $157,799 $0 $499,303 D10 CONVEYING SYSTEMSD1011 Elevator Hydraulic System 2,500 Lb D1011 Elevator Hydraulic System 1,500 Lb Mechanical Room Replace D1011 Elevator Hydraulic System 1,500 Lb 30 3 2.00 EA $161,015.71 CC - Accessibility Priority 2 $0 $0 $0 $322,031 $0 $0 $0 $0 $0 $0 $0 $322,031D20 PLUMBINGD2012 Urinal D2012 Urinal Interior, restrooms Replace D2012 Urinal 35 0 3.00 EA $1,530.59 IN - Beyond Rated Life Priority 1 $4,592 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,592 $0D2013 China Wall Hung Lavatory And Faucet D2013 China Wall Hung Lavatory And Faucet Interior, restrooms Replace D2013 China Wall Hung Lavatory And Faucet 35 8 12.00 EA $967.05 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $11,605 $0 $0 $11,605D2014 Kitchen Sink And Faucet D2014 Kitchen Sink Interior, kitchen Replace D2014 Kitchen Sink 20 0 2.00 EA $1,847.75 IN - Beyond Rated Life Priority 1 $3,696 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,696 $0D2018 Drinking Fountain D2018 Drinking Fountain Interior Replace D2018 Drinking Fountain 15 7 2.00 EA $1,768.60 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $3,537 $0 $0 $0 $3,537D30 HVACD3011 Fuel Tank, Above Ground - Steel - 2,000 Gal D3011 Fuel Tank, Above Ground - Concrete and Steel - 1,000 Gal Site Replace D3011 Fuel Tank, Above Ground - Concrete and Steel - 1,000 Gal 30 5 1.00 EA $7,843.70 IN - Beyond Rated Life Priority 3 $0 $0 $0 $0 $0 $7,844 $0 $0 $0 $0 $0 $7,844 D3041.1 Fan Motor 7.5 Hp D3041.1 AHU, 7.5 Hp Fan Motor Interior Replace D3041.1 AHU, 7.5 Hp Fan Motor 20 9 2.00 EA $10,656.00 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $21,312 $0 $21,312D3053 Split System Unit, 5-Ton, Condenser And Fan Coil D3053 Split System Unit, 12-Ton, Condenser And Fan Coil Exterior Replace D3053 Split System Unit, 12-Ton, Condenser And Fan Coil 15 0 1.00 EA $28,143.81 IN - Beyond Rated Life Priority 1 $28,144 $0 $0 $0 $0 $0 $0 $0 $0 $0 $28,144 $0 D40 FIRE PROTECTION SYSTEMSD4095 Hood & Duct Fire Protection D4095 Hood & Duct Fire Protection Interior, kitchen Replace D4095 Hood & Duct Fire Protection 10 5 1.00 EA $38,449.51 IN - Beyond Rated Life Priority 3 $0 $0 $0 $0 $0 $38,450 $0 $0 $0 $0 $0 $38,450D50 ELECTRICAL SYSTEMSD5037 Fire Alarm Panel D5037 Fire Alarm Panel Interior Replace D5037 Fire Alarm Panel 15 7 1.00 EA $5,896.50 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $5,896 $0 $0 $0 $5,896D5092 Diesel Generator 25 Kw D5092 Diesel Generator 10 Kw Mechanical Room Replace D5092 Diesel Generator 10 Kw 25 5 1.00 EA $31,820.00 IN - Beyond Rated Life Priority 3 $0 $0 $0 $0 $0 $31,820 $0 $0 $0 $0 $0 $31,820D5092 Transfer Switch D5092 Transfer Switch Mechanical Room Replace D5092 Transfer Switch 25 5 2.00 EA $6,525.14 IN - Beyond Rated Life Priority 3 $0 $0 $0 $0 $0 $13,050 $0 $0 $0 $0 $0 $13,050 $36,431 $0 $0 $322,031 $0 $91,164 $0 $9,434 $11,605 $21,312 $36,431 $455,545 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 G20 SITE IMPROVEMENTSG2012 Asphalt, Mill 1.5” / Resurface 2.0” - Roadways G2012 Asphalt Pavement Site Replace G2012 Asphalt Pavement 25 9 39,600.00 SF $4.85 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $192,234 $0 $192,234G2012 Concrete Pavement G2012 Concrete Pavement Site Replace G2012 Concrete Pavement 30 2 2,200.00 SF $12.21 IN - Beyond Rated Life Priority 2 $0 $0 $26,862 $0 $0 $0 $0 $0 $0 $0 $0 $26,862G2012 Asphalt- Seal Coat- Roadways G2012 Asphalt Crack Seal, Seal and Stripe Site Replace G2012 Asphalt Crack Seal, Seal and Stripe 5 0 39,500.00 SF $0.74 IN - Beyond Rated Life Priority 1 $29,230 $0 $0 $0 $0 $29,230 $0 $0 $0 $0 $29,230 $29,230 G2031 Concrete Sidewalk, 3’ To 5’ Wide G2031 Concrete Sidewalk, 3’ To 5’ Wide Site Replace G2031 Concrete Sidewalk, 3’ To 5’ Wide 30 3 3,300.00 SF $13.53 IN - Beyond Rated Life Priority 2 $0 $0 $0 $44,640 $0 $0 $0 $0 $0 $0 $0 $44,640G2035 Cast-In-Place Concrete Stair G2036 Cast-In-Place Concrete Stair Site Replace G2036 Cast-In-Place Concrete Stair 40 7 60.00 LF $10.20 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $612 $0 $0 $0 $612G2041 Wrought Iron Fence 3’ High G2041 Wrought Iron Fence 3’ High Site Replace G2041 Wrought Iron Fence 3’ High 30 0 72.00 LF $43.02 IN - Beyond Rated Life Priority 1 $3,098 $0 $0 $0 $0 $0 $0 $0 $0 $0 $3,098 $0G2045 Manual Swing Gate G2045 Wrought Iron Manual Swing Gate, double Exterior Replace G2045 Wrought Iron Manual Swing Gate, double 15 8 2.00 EA $5,439.00 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $10,878 $0 $0 $10,878G2048 Flag Pole, Fiberglass - 59’ High G2048 Flag Pole, Fiberglass - 45’ High Site Replace G2048 Flag Pole, Fiberglass - 45’ High 20 9 2.00 EA $7,539.27 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $15,079 $0 $15,079G40 SITE ELECTRICAL UTILITIESG4022 Aluminum Light Pole, Over 15 Ft. And Double Fixture G4022 Aluminum Light Pole, Over 15 Ft. And Double Fixture Site Replace G4022 Aluminum Light Pole, Over 15 Ft. And Double Fixture 20 9 4.00 EA $4,377.84 IN - Beyond Rated Life Priority 4 $0 $0 $0 $0 $0 $0 $0 $0 $0 $17,511 $0 $17,511 10 YEAR EXPENDITURE FORECAST
Main Library840 West Orange AvenueSouth San Francisco, CaA. SUBSTRUCTURE A. SUBSTRUCTURE SUB-TOTALS
B. SHELL
B. SHELL SUB-TOTALS
C. INTERIORS
C. INTERIORS SUB-TOTALS
D. SERVICES
D. SERVICES SUB-TOTALS
E. EQUIPMENT & FURNISHING
E. EQUIPMENT & FURNISHING SUB-TOTALS
F. SPECIAL CONSTRUCTION AND DEMOLITION
F. SPECIAL CONSTRUCTION AND DEMOLITION SUB-TOTALS
G. BUILDING SITEWORK
Powered by iPlan™
iPlan Capital Expenditure Report ‐ Version 4.3
1 12/8/2015 7:09 PM
Element No. Component Description Asset Location Action Estimated Useful
Life or
Replacement Cycle
(Yrs)
Remaining Useful
Life (Yrs) Quantity Unit of Measurement Unit Cost Plan Type Priority 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Total Total 0123456789
Deferred Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Scheduled Deferred Scheduled A. SUBSTRUCTURE
$32,328 $0 $26,862 $44,640 $0 $29,230 $0 $612 $10,878 $224,824 $32,328 $337,046 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$70,344 $0 $144,138 $526,354 $0 $128,369 $0 $33,146 $55,951 $830,329 $70,344 $1,718,287$70,344 $0 $155,899 $592,077 $0 $156,180 $0 $43,618 $76,573 $1,181,817 Total * $1,788,631 Current Replacement Value $7,280,625
G. BUILDING SITEWORK SUB-TOTALS
Z. GENERAL
Z. GENERAL SUB-TOTALS
Expenditure Totals per YearTotal Cost (Inflated @ 4% per Yr.) * - Present Value Currency
Powered by iPlan™
iPlan Capital Expenditure Report ‐ Version 4.3
2 12/8/2015 7:09 PM
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
APPENDIX D:

SUPPORTING DOCUMENTATION
Floodplain Map
Source:

FEMA
Map Number 06081C0043E
Date: 2012
The north arrow indicator is an approximation
of 0° North.

Project Number:
111948.15R-014.305
Project Name:

Main Library
On-Site Date:

May 27, 2015
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Nearest airport to South San Francisco, CA. See history from more local stations Get Current Weather Weather History for KSFO
Monthly Calendar Detailed History
Next Day »
May 27 2015
Change the Weather History Date:

Wednesday, May 27, 2015
« Previous Day
Actual Average Record
Temperature
Mean Temperature 59 °F 60 °F
View
Daily Weekly Monthly Custom
Maps & Radar Severe Weather Search Locations
News & Blogs Photos & Video Activities
More  
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Max Temperature 64 °F 69 °F 97 °F (1984)
Min Temperature 53 °F 53 °F 42 °F (1954)
Degree Days
Heating Degree Days 6 5
Month to date heating degree days 166 161
Since 1 July heating degree days 1444 2529
Cooling Degree Days 0 0
Month to date cooling degree days 0 0
Year to date cooling degree days 13 6
Growing Degree Days 9 (Base 50)
Moisture
Dew Point 49 °F
Average Humidity 73
Maximum Humidity 89
Minimum Humidity 56
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Precipitation
Precipitation 0.00 in 0.01 in 0.92 in (1990)
Month to date precipitation 0.02 0.43
Year to date precipitation 3.37 12.93
Sea Level Pressure
Sea Level Pressure 30.02 in
Wind
Wind Speed 13 mph (West)
Max Wind Speed 26 mph
Max Gust Speed 36 mph
Visibility 10 miles
Events
T = Trace of Precipitation, MM = Missing Value Source: NWS Daily Summary Daily Weather History Graph
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Certify This Report
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Search for Another Location
Airport or City:

KSFO
Trip Planner
Search our weather history database for the weather conditions in past years. The results will help you decide how hot, cold, wet, or windy it might be!
Date:

Submit
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com May 27
Astronomy
May. 27, 2015 Rise Set
Actual Time 5:51 AM PDT 8:21 PM PDT
Civil Twilight 5:21 AM PDT 8:52 PM PDT
Nautical Twilight 4:44 AM PDT 9:29 PM PDT
Submit
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Astronomical Twilight 4:02 AM PDT 10:11 PM PDT
Moon 2:50 PM PDT (5/27) 2:29 AM PDT (5/27)
Length of Visible Light 15h 30m
Length of Day 14h 29m
Waxing Gibbous, 69% of the Moon is Illuminated
May 27
Waxing Gibbous
Jun 2
Full
Jun 9
Last Quarter
Jun 16
New
Jun 24
First Quarter
Visit Astronomy
Hourly Weather History & Observations
Time
(PDT) Temp. DewPoint Humidity Pressure Visibility WindDir Wind
Speed
Gust
Speed Precip Events Conditions
12:56
AM 55.9 °F 48.0 °F 75% 30.01 in 10.0 mi SSW 10.4 mph - N/A Overcast 1:56
AM 57.0 °F 48.9 °F 74% 30.01 in 10.0 mi WSW 5.8 mph - N/A Overcast 2:56
AM 55.9 °F 48.9 °F 77% 30.01 in 10.0 mi SW 6.9 mph - N/A Overcast 3:56
open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com 3:56
AM 55.9 °F 48.0 °F 75% 30.01 in 10.0 mi WSW 9.2 mph - N/A Overcast 4:56
AM 55.0 °F 48.0 °F 77% 30.00 in 10.0 mi WSW 9.2 mph - N/A MostlyCloudy 5:56
AM 54.0 °F 48.0 °F 80% 30.01 in 10.0 mi West 8.1 mph - N/A Overcast 6:56
AM 54.0 °F 48.0 °F 80% 30.02 in 10.0 mi West 10.4 mph - N/A Overcast 7:56
AM 55.0 °F 46.9 °F 74% 30.03 in 10.0 mi WSW 10.4 mph - N/A MostlyCloudy 8:31
AM 57.2 °F 48.2 °F 72% 30.03 in 10.0 mi WSW 8.1 mph - N/A MostlyCloudy 8:56
AM 57.9 °F 48.0 °F 70% 30.03 in 10.0 mi West 9.2 mph - N/A MostlyCloudy 9:56
AM 59.0 °F 48.9 °F 69% 30.04 in 10.0 mi WSW 10.4 mph - N/A MostlyCloudy 10:56
AM 60.1 °F 50.0 °F 69% 30.03 in 10.0 mi WNW 15.0 mph - N/A MostlyCloudy 11:03
AM 60.8 °F 50.0 °F 68% 30.03 in 10.0 mi WNW 16.1 mph - N/A ScatteredClouds 11:56
AM 63.0 °F 50.0 °F 63% 30.02 in 10.0 mi West 16.1 mph 23.0 mph N/A PartlyCloudy 12:56 63.0 °F 50.0 °F 63% 30.02 in 10.0 mi WNW 19.6 mph - N/A Partly open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com PM 63.0 °F 50.0 °F 63% 30.02 in 10.0 mi WNW 19.6 mph - N/A Cloudy 1:56
PM 64.0 °F 48.9 °F 58% 30.02 in 10.0 mi West 18.4 mph - N/A PartlyCloudy 2:56
PM 62.1 °F 48.0 °F 60% 30.03 in 10.0 mi West 20.7 mph 25.3 mph N/A PartlyCloudy 3:40
PM 60.8 °F 48.2 °F 63% 30.03 in 10.0 mi West 23.0 mph 28.8 mph N/A MostlyCloudy 3:56
PM 61.0 °F 48.9 °F 64% 30.03 in 10.0 mi West 18.4 mph 27.6 mph N/A MostlyCloudy 4:20
PM 60.8 °F 50.0 °F 68% 30.03 in 10.0 mi West 20.7 mph 27.6 mph N/A MostlyCloudy 4:56
PM 59.0 °F 50.0 °F 72% 30.03 in 10.0 mi West 19.6 mph 31.1 mph N/A MostlyCloudy 5:56
PM 57.9 °F 51.1 °F 78% 30.02 in 10.0 mi West 12.7 mph - N/A MostlyCloudy 6:56
PM 57.2 °F 51.8 °F 82% 30.01 in 10.0 mi West 13.8 mph - N/A MostlyCloudy 7:56
PM 57.0 °F 51.1 °F 81% 30.02 in 10.0 mi WSW 12.7 mph 24.2 mph N/A MostlyCloudy 8:56
PM 55.9 °F 50.0 °F 80% 30.03 in 10.0 mi West 17.3 mph - N/A MostlyCloudy 9:56
PM 55.0 °F 50.0 °F 83% 30.04 in 10.0 mi West 10.4 mph 18.4 mph N/A Overcast open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com Buy These 10 Stocks Now
investmentu.com/Under-$15
These 10 stocks are not only under $15, they also pay high dividends.
10:56
PM 55.0 °F 50.0 °F 83% 30.04 in 10.0 mi WSW 9.2 mph - N/A Overcast 11:56
PM 54.0 °F 50.0 °F 86% 30.04 in 10.0 mi West 13.8 mph 19.6 mph N/A Overcast Show full METARS | METAR FAQ | Comma Delimited File
 Like
 +1
 Tweet
 Pin
 Follow
About Us
About Our Data
Employment
Contact Us
Press Center
Advertising
Forecast Factor
Self-Service Advertising
Our Company Our Community
Personal Weather Station
Network
Register a Weather
Station
Upload Photos
Post a Blog
Our Products
Mobile Applications
Full Screen Weather
The Weather API
Download Widgets
Weather Underground for
Roku
Copyright © 2015 The Weather Channel, Contact Support & Feedback Terms of Service Privacy Statement open in browser PRO version Are you a developer? Try out the HTML to PDF API pdfcrowd.com LLC AdChoices
111948.15R-014.305

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT 800.733.0660 • www.emgcorp.com

F ACILITY C ONDITION A SSESSMENT
APPENDIX E:

PRE-SURVEY QUESTIONNAIRE

YOUR PARTNER IN REAL ESTATE LIFECYCLE PLANNING & MANAGEMENT www.emgcorp.com

T HE P RE-S URVE Y Q UES TI ONNAI RE WAS NOT

RE TURNE D TO EMG