Project Scope
Soft Cost (design, permits, fees) $1,200,000
Hard Costs (construction) $4,500,000
Total $5,700,000
Project Budget
Design Winter 2022 - Spring 2023
Bid & Award Summer - Fall 2023
Construction Winter 2023 - Fall 2024
Opening Fall 2024
Project Schedule
12 15 14
2 5
10 11
Bay Trail Tree Mounds 13 Existing Restroom
21 Dog Park Ornamental Planting 14 Future Pump Station
Repaved Parking Lot Native Grasses 15 Future Hotel
Picnic Area 10 Lawn 16 Yacht Club
5 Fitness Area 11 Windsurf Launch 17 Maintenance Yard
Inch 5 500 frie
Median Planting 12 Existing Pier 18 Ferry Terminal
SOUTH SAN OYSTER POINT IIC PHASE 2 CONSTRUCTION PLAN
Bools MAY - AUGUST 2024
FRANCISCO
Construction Questions: Srushti Vaghela at (415) 481-2805 BAY TRAIL OPEN DURING CONSTRUCTION CALIFORNTA Project Information: www.ssf.net/parkprojects TEMPORARY BAY TRAIL DETOUR Dismount and walk bikes while using temporary detour trail
PARKING
PUBLIC PARKING
DOMINIC'S AT
OYSTER POINT
OPEN DURING
CONSTRUCTION
TRAILER PARKING
OPEN DURING
CONSTRUCTION
AREA CLOSED FOR CONSTRUCTION
FISHING PIER
OPEN DURING
CONSTRUCTION
DOG AREA ENTRANCE DOG AREA
BAY TRAIL ART PEDESTAL
PICNIC AREA PATHWAY
UPPER PARKING LOT PATHWAY
THANK YOU
11