Safe Routes to School 2025
(ST2507)
Project Overview
Alta Loma & Buri Buri
Neighborhood
Traffic Circle
School
XWalk
Bulb-out
Raised
XWalk
Green Bike
Symbols
Bike Path
Bulb-out
School
XWalk
Wider Sidewalk
Parkway
Heights
Ponderosa
Bulb-out
Curb Extension
and
Corner Island
Bulb-outs
Del Monte: Raised Crosswalk
Chestnut Bike Path
Neighborhood
Traffic Circle
Del Monte / San Felipe
Project Schedule
Budget Overview
Funding Sources:

Citywide Traffic Impact Fees $500,000
SMCTA Ped/Bike Grant $4,897,000
Expenditures:

Planning & Design $675,000
Construction Engineering $845,000
Construction $3,377,000
Contingencies $500,000
Total Estimated Costs: $5,397,000
Thank You!
Questions
Discussion