Construction Phase
CDBG Ramps and Paths
Project Overview
1. Identify Curb Ramps and Accessibility Issues
2. Complete Design
3. CDBG for Public Improvements
4. Construct Improvements
5. Operationalize and Monitor
Project Map
Eligible Areas in Pink
Ramp Locations
Path at Cypress
and Pine Park
N
N
Design Elements
Accessible Curb Ramps Accessible Path Crosswalk Enhancements Bid Summary & Recommendation
*Amount Shown is Sum of Base Bid and Bid Alternate
Budget Overview
Total Construction BudgetFund Source
$861,980.78CDBG PY 24-25
$172,319.00CDBY PY 25-26
$1,034,299.78Total
Projected CostExpense
$170,000.00Construction Engineering
$723,267.25Contract
$110,000.00Contingency
$1,003,000.00Total
Schedule and Impacts
20 WEEKS
TOTAL
Notice and
Barricades
Demo and
Grading
Forms and
Concrete
Asphalt
Paving
Signs and
Markings
Thank You!
Questions
Discussion
Motion