Junipero Serra Blvd Buffered Bike Lane Enhancement Project May 14, 2025
Engineering Division
Background and History
2 Original
•Dedicated bike lanes
2022
•Painted buffer zones
2025
•Protected bike lanes
Background and History
3 Original
•Dedicated bike lanes
2022
•Painted buffer zones
2025
•Protected bike lanes
Background and History
4 Original
•Dedicated bike lanes
2022
•Painted buffer zones
2025
•Protected bike lanes
Project Necessity
Project Benefits
Bid Results
CONTRACTOR BASE BID RANKING
Engineer’s Estimate $ 430,000.00 X
Tri-Valley Contracting, Inc. $ 370,295.50 1
Bayside Stripe & Seal, Inc. $ 419,052.00 2
Chrisp Company $ 548,753.00 3
Zara Construction Inc. $ 366,638.00** Disqualified
Competitive Bidding for Construction Projects
– Cost is generally the sole determining factor
** Zara’s bid was determined to be unresponsive as it did meet all the bid proposal requirements.
Budget and Schedule
Tri-Valley Contracting, Inc. Base Bid $ 370,295.50
Construction Contingency (20%) $ 74,704.50
Total Estimated Construction Costs* $ 445,000.00
Construction Commences
( ~Summer 2025 )
Bid Opening
City Council
Award
Ongoing Public Outreach
Construction Complete
( ~Fall 2025 )
Design
Completed
Award of TDA
Grant Funds
*$345,717.00 of Transportation
Development Act (TDA) funds
Budget Amendment
Purpose Estimated Costs
Design Budget $ 29,500.00
Construction Budget $ 445,000.00
Construction Management
and Inspection $ 33,000.00
Misc. Project Costs and
Contingency $ 8,217.00
Total Estimated Expenses $ 515,717.00
Funding Source Amount
Citywide Traffic Impact Fee $ 50,000.00
TDA Grant Funds $ 345,717.00
*Additional Citywide Traffic
Impact Fees
$ 120,000.00
Total Project Budget $ 515,717.00
* Additional funds requested to cover construction, construction contingency, construction management and inspection, as well as miscellaneous project costs.
Project Support
Bicycle &
Pedestrian
Advisory
Committee
JSB Buffered Bike Lane Enhancement Project
City of South San Francisco
THANK YOU