City of South San Francisco, DPW Engineering PF2210 Request for Cost Proposal 10/14/2025 Item Description UOM Est Qty Unit Cost Total Cost Unit Cost Total Cost 1 Mob & DeMob LS 1 $15,000.00 $15,000.00 $20,000.00 $20,000.00 2 Traffic Control and CAS LS 1 $20,000.00 $20,000.00 $45,000.00 $45,000.00 4 Furnish & Install 3-inch HDPE Conduit (No Innerduct) LF 700 $300.00 $210,000.00 $300.00 $210,000.00 8 Furnish & Install 12-strand SMFO Cable LF 100 $4.72 $472.00 $4.72 $472.00 6A Furnish & Install 144-strand SMFO Cable LF 1,500 $29.79 $44,685.00 $29.79 $44,685.00 7 Furnish & Install 48-strand SMFO Cable (Plenum-rated) LF 250 $12.54 $3,135.00 $12.54 $3,135.00 10 Furnish & Install No. 6E Pullbox EA 2 $6,000.00 $12,000.00 $6,000.00 $12,000.00 11 Furnish & Install No. N48 Pullbox EA 2 $13,750.00 $27,500.00 $13,750.00 $27,500.00 13 Furnish & Install Splice Closure EA 2 $3,500.00 $7,000.00 $3,500.00 $7,000.00 18 Mill and Overlay (HMA) SF 352 $22.00 $7,744.00 $22.00 $7,744.00 19 Minor Concrete (Sidewalk) SF 504 $52.00 $26,208.00 $52.00 $26,208.00 20 Minor Concrete (Curb & Gutter) LF 25 $85.00 $2,125.00 $85.00 $2,125.00 21 HMA Conform SF 50 $50.00 $2,500.00 $25.00 $1,250.00
22 Surface Seal (Type 2) SF 528 $35.00 $18,480.00 $25.00 $13,200.00 16 Make and Test Fiber Splices and Terminations EA 106 $350.00 $37,100.00 $350.00 $37,100.00 14 Furnish and Install 12-Port Fiber Termination Panel and Patch Cords EA 1 $3,500.00 $3,500.00 $3,500.00 $3,500.00 15 Furnish and Install 48-Port Fiber Termination Panel and Patch Cords EA 1 $6,260.00 $6,260.00 $6,260.00 $6,260.00 16 Permit Fees (Allowance - Pre Set at $5,000) LS 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00 Total Cost $448,709.00 Total Cost $472,179.00
Item Description UOM Est Qty Unit Cost Total Cost Unit Cost Total Cost 1 Mob & DeMob LS 1 $15,000.00 $15,000.00 $10,000.00 $10,000.00 2 Traffic Control and CAS LS 1 $20,000.00 $20,000.00 $31,500.00 $31,500.00 4 Furnish & Install 3-inch HDPE Conduit (No Innerduct) LF 450 $300.00 $135,000.00 $300.00 $135,000.00 6A Furnish & Install 48-strand SMFO Cable LF 2,250 $29.79 $67,027.50 $12.00 $27,000.00 7 Furnish & Install 48-strand SMFO Cable (Plenum-rated) LF 400 $12.54 $5,016.00 $12.54 $5,016.00 10 Furnish & Install No. N36 Pullbox EA 1 $6,000.00 $6,000.00 $6,000.00 $6,000.00 11 Furnish & Install No. N48 Pullbox EA 2 $13,750.00 $27,500.00 $13,750.00 $27,500.00 13 Furnish & Install Splice Closure EA 1 $3,500.00 $3,500.00 $3,500.00 $3,500.00 18 Mill and Overlay (HMA) SF 300 $22.00 $6,600.00 $22.00 $6,600.00 19 Minor Concrete (Sidewalk) SF 96 $52.00 $4,992.00 $52.00 $4,992.00 16 Make and Test Fiber Splices and Terminations EA 24 $350.00 $8,400.00 $350.00 $8,400.00 15 Furnish and Install 48-Port Fiber Termination Panel and Patch Cords EA 1 $6,260.00 $6,260.00 $6,260.00 $6,260.00 Total Cost $305,295.50 Total Cost $271,768.00
Total Costs for Westborough and Orange (Only) $754,004.50 Engr Estimate $743,947.00 BID SCHEDULE - 1 - WESTBOROUGH
BID SCHEDULE - 1 - WESTBOROUGH HP Communications Cost Proposal BID SCHEDULE - 2 - ORANGE HP Communications Cost Proposal BID SCHEDULE - 2 - ORANGE Page 1 of 1