In-N-Out Burger Restaurant Project
November 12, 2025
City Council
Government Code Section 54957.5
SB 343 Item #17
11/12/2025 REG CC
• Approved by the Planning
Commission on July 17, 2025:
• CEQA Determination
• Design Review
• Conditional Use Permit
• Master Sign Program
Approved Entitlements
2 Project Site: 932 & 972 El Camino Real
3 New In-N-Out Burger Restaurant
with Drive-Through
• 3,887 sq. ft. building
• Indoor seating for 84 guests
• Outdoor seating for 28 guests
• Onsite drive-through queuing
for 39 cars
• Onsite parking for 51 cars
• 19,338 sq. ft. of new
landscaping
Approved Project
4 Circulation Amenities
• Pedestrian connection to
Centennial Way Trail
• New traffic signal at El Camino
Real & Southwood Dr/1st St
• Interim measures: No U-Turn
Signs
Approved Project
5 Approved Project
6 • Community Meeting, January 13,
2025 @LPR
• Approx. 70 community members, City staff,
Councilmembers, Planning Commissioners
& BPAC members
Public Comments & Concerns:
• Increased traffic in the surrounding area
• Drive-through queue flowing onto ECR
• Pedestrian & vehicular safety at ECR &
Southwood/1st
• Parking lot capacity & circulation
• Impact to Maltese American Social Club
• Access to/from Centennial Way Trail
• Open Discussions with neighboring
properties
• Mailer with Project Update
• Support from Maltese American
Social Club at PC Meeting
• Commitment to continued
communication with the
community
Community Outreach
7 Intersection of El Camino Real &
Southwood Drive / 1st Street
• Existing Conditions: Unsignalized
intersection operates below
acceptable standards
• Anticipated Conditions with
Project: New restaurant will
contribute additional traffic
volume, as well as introduce a
high volume of vehicles
performing U-Turns at
intersection
Traffic Signal
8 In-N-Out Responsibilities & Initial Investment
• Responsible for the design & construction of
traffic signal improvements.
• Cal Trans review & reasonable adjustments to
the design based on feedback or requirements
from Cal Trans will be considered as “generally
conforming.”
• The existing street on El Camino Real does not
currently meet ADA requirements; will work with
the City engineers to reasonably resolve the
street slopes.
• Cover the full upfront cost of the signal
installation, including payment of prevailing
wages.

Project Timeline & Contingencies
• The traffic signal must be installed within 2 years
of TCO
• Prior to the start of traffic signal construction and installation and before Final Occupancy of the
on-site improvements, In-N-Out will install No-U
Turn signs on El Camino Real at Southwood Drive
/ 1st Street.
• In-N-Out must submit complete traffic signal
plans for City review and approval prior to
submittal to Caltrans.
• If CalTrans denies the request for the permanent
traffic signal, In-N-Out and the City will engage
in good faith negotiations to determine
appropriate next steps.
• Caltrans denial of the traffic signal will not
relieve In-N-Out of all mitigation measures that
may be reasonable and appropriate.

Proposed Reimbursement Agreement
9 • Adopt Resolution approving a
Reimbursement Agreement for
installation of a new traffic
signal at the intersection of El
Camino Real and Southwood
Drive / 1st Street
Recommendation
10 In-N-Out Burger Restaurant Project
City of South San Francisco

THANK YOU

FOR JOINING US TODAY

← All documents from this meeting