Curb Ramps & Street Intersection
Improvements
Project ST2401, Bid No. 2705
December 10, 2025
Vicinity Map
2 3
Status Contractor Bid Amount
1 Responsive Spektren Engineering, Inc. $412,907.54
2 Responsive CF Contracting, Inc. $449,889.55
3 Responsive Altor Construction $476,505.00
4 Responsive Golden Bay Construction, Inc. $504,658.00
5 Responsive FBD Vanguard Construction, Inc. $504,990.00 6 Responsive Sposeto Engineering, Inc. $540,998.00
7 Responsive Modernscapes Innovations $575,045.00
8 Responsive Granite Rock Company $598,992.50
9 Responsive QLM-Inc. $620,054.00
10 Responsive JPB Designs Inc. $639,169.00
11 Responsive Kerex Engineering $645,024.00
12 Responsive Buildcorp Inc. $654,380.00
13 Responsive Zara Construction, Inc. $679,669.00
14 Responsive Redgwick Construction Co. $881,149.00
Engineers Estimate (EE) $452,908.00
Bid Results
Procurement Method
4 1. Competitive Bidding for Construction Projects
 Cost is generally the sole determining factor

2. Open Market Procedures for Vendors (Supplies and Equipment)  Cost > $25,000, required to solicit the project through an RFP  Cost can be only one factor in selection (SSFMC § 4.04.080)  Federally Funded, do not include state or local geographical preferences.  Nondiscrimination and equal opportunity for all vendors.

3. Open Market Procedures for Architectural and Engineering (A&E) Professional Services
 Consultant is selected through a qualifications based selection (Gov. Code § 4526.) Construction Budget
5 Construction Contract $412,907.54
Construction Contingency (25%) $100,000.00
Total Construction Contract Authority Budget $512,907.54 6 Stage 1

LIMITED NOTICE TO PROCEED
•Material Procurement
Stage 2

WINTER SUSPENSION
•Commence by March 1, 2026
Stage 3

NOTICE TO PROCEED
•Drainage Improvements
•Curb Ramp Improvements
Jan – Mar 2026
Jan – Mar 2026
Mar – June 2026
Thank you!