New Park at Linden and Pine
City Council
CEQA
December 10, 2025
2 PROJECT FEATURES
• Play Area • Fitness & Game Area • Flexible Lawns • Plaza • Picnic & Seating Areas • Lighting • Bike Parking • Public Art 3 SCHEDULE
Bid/Award Winter 2026
Start Construction Spring 2026
Park Opening Early 2027
CEQA – INITIAL STUDY/MITIGATED NEGATIVE DECLARATION
• 30-day public review period, from September 22, 2025, through October 22, 2025.
• 4 Comments Received:
• Amah Mutsun Tribal Band of San Juan Bautista & AMTB: Standard comment letter with recommendations for investigation of and methods for work in soils with cultural and/or historic sensitivity with no comments on the IS/MND, dated September 22, 2025
• Muwekma Ohlone Tribe, Inc.: Advisement, offer for tribal consultation and monitoring services with no comments on the IS/MND, dated September 29, 2025 • Pacific Gas and Electric Company: Advisement to coordinate work around PG&E facilities, no comments on the IS/MND, dated September 24, 2025 • Pacific Gas and Electric Company: Advisement to coordinate work around PG&E facilities, and acknowledgement that project does not appear to interfere with PG&E facilities or impact PG&E’s Planning Service Department, no comments on the IS/MND, dated October 14, 2025
CEQA – MITIGATION MEASURES
• CEQA Review: Initial Study / Mitigated Negative Declaration (IS/MND) • The IS/MND identified the following mitigation measures which would reduce impacts to less-than-significant levels:
o MM BIO-1: Minimizes biological resources impacts to nesting birds. o MM CUL-1: Archaeological Monitoring Plan.
o MM-CUL-2: Avoid Impacts to Unknown Cultural Resources. o MM-CUL-3: Avoid Impacts to Unknown Human Remains.
o MM-GEO-1: Avoid and/or Redue Impacts from Unstable Soils. o MM-HAZ-1: Develop and Implement a Demolition Debris Management and Disposal Plan. o MM-HAZ 2: Develop a Hazardous Materials Contingency Plan. o MM-HAZ 3: Prepare a Site Manage Plan
o MM-NOI-1: Reduce Construction Noise Impacts.
o MM-TR-1: Develop and Implement a Construction Traffic Management Plan o MM-TCR-1: Avoid Impacts to Unknown Tribal Cultural Resources CEQA – SUMMARY
• Comments received have not raised any issues that would require recirculation of the IS/MND or preparation of an environmental impact report
• No new significant effects were identified
• No new mitigation measures were added and proposed revisions to the mitigation measures would result in measures that are equivalent or more effective,
• Significance of identified impacts remains unchanged, and • All impacts are either below significance levels or reduced to that level through application of identified mitigation.
Presentation
South San Francisco City Council
December 10, 2025
- Document
- Presentation
- Meeting
- December 10, 2025
- Body
- South San Francisco City Council
- Original file
- 555 KB
Text extracted from the city's file for reading and search. Open the original on ci-ssf-ca.legistar1.com. That file is the official record.