Junipero Serra Blvd Buffered Bike Lane Enhancement Project January 28, 2026
Engineering Division
Background and History
2 Original
•Dedicated bike lanes
2022
•Painted buffer zones
2025
•Protected bike lanes
2 Improvements
BEFORE

AFTER AFTER
3 Bike
Protection
Improvements
BEFORE

AFTER AFTER
4 Bike
Protection +
Buffer Space
Improvements
BEFORE

AFTER AFTER
5 Improve Median
Visibility at Clay Ave
Improvements
BEFORE

AFTER AFTER
6 Bike Lane
Extension
Advance
Bike Box
N
N
Construction Costs
Tri-Valley Contracting, Inc.

Construction Contract $ 370,295.50
Construction Contingency $ 2,654.00
Total Construction Costs* $ 372,949.50
*$345,717.00 of Transportation Development Act (TDA) funds 7 JSB Buffered Bike Lane Enhancement