• Project Background
• Project Location
• Existing Conditions
• Skate Space Relocation
• Implementation Efforts
• Acoustic Report
• Concept Plan
• Community Outreach and
P&R Commission Feedback
• Design Refinements
• Construction Budget
• Next Steps
Project Location
Orange
Memorial Park
Project
Location
Existing Conditions
Existing Conditions
wind direction
(west)
Skate Space Relocation • Skate park relocation was
identified in 2021 Orange
Memorial Park Master Plan
(decided on during
community outreach efforts)
• Proposed location was
identified in 2023 Centennial
Way Master Plan
Acoustic Report
• Current Site Noise: 56-59 dBA avg.
• City of South San Francisco Noise
Ordinance:
• (7am-10pm): 60 dBA
• (10pm-7am):50-55 dBA
• With Pickleball (With mitigation):
49-50 dBA avg. pickleball noise
(57 dBA when ball hits paddle)
• We anticipate that these
improvements will not result
in increased noise levels.
Sound Reducing Materials
Opaque Panels Alternating Opaque and Transparent Panels Concept Plan
Community Outreach
• Support concept plan and court
location; appreciated acoustic study
• Requests for more courts and programs
(beginner classes, leagues, events)
• Add seating inside courts, paddle racks,
and hooks for bags
• Include windscreens and a paddle
queue/reservation system
• Concerns about lighting; suggest timers
and resident-priority reservations
• Improve access with accessible paths
and nearby restroom upgrades
Feedback Received:
Parks & Recreation Commission
• Suggest layout reconfiguration and
elimination of parking stalls to allow for
additional court on east side towards
Eucalyptus Ave.
• Add bullpen area with spectator
seating, separated from court area with
low fence
• Concerns about wind direction and
impacts on user experience in seating
area
• Add paddle racks to courts for queuing
system
Feedback Received:
Design Refinements – 6 Courts
Construction Budget
Subtotal Construction Cost
Construction + Redesign Contingency
Total Estimated Construction Cost & Contingency
Bid Alternate: replace wind screen with alternating sound reducing panels $770,850.00
$85,090.00
$855,940.00
+$33,800.00
Next Steps
Questions?