Centennial Trail Access Improvements
- Construction Contract
Project No. TR2413, Bid No. 2714March 11, 2026, Engineering Division Project Locations
2 Future Signal (by developer)
Informal Connections
Desire Paths
Access Issue at 2nd St
4 Stairs
Bid Results
5 BidContractorRank
iDrill Engineering Inc1 $141,100.00 Terocons Inc2 $145,000.00 Bay Area Paving3 $154,500.00 QA Constructors4 $158,467.00 John Boylan Engineering, Inc.5 $162,450.00 O’Connor Pipelines Inc6 $170,000.00 Inder Design Build LLC.7 $189,740.00 Galeb Paving Inc8 $222,195.00 Norgo Engineering9 $235,900.00
R and M Paving Contractors Inc10 $238,951.00 Golden Bay Construction Inc11 $243,240.00 Raposo Engineering Inc12 $245,360.00 $160,000.00Engineers Estimate
Construction Budget
6 Construction Contract $141,100.00 Construction Contingency (~%20) $28,900.00 Total Construction Contract Authority Budget $170,000.00 Schedule
7 Stage 1
STAGING, NOTICES•April 2026
Stage 2
CONSTRUCTION•May-June 2026