New Park at Linden and Pine
Award of Construction Contract / Procurement / Amendment April 8, 2026
New Park at Linden & Pine
2 Bid Package Advertised: February 18, 2026
Pre-Bid Site Walk: February 25, 2026
Bids Opened: March 16, 2026
• Azul Works, Inc. $3,295,000
• Ronan Construction Inc. $3,532,478
• Minerva Construction, Inc. $3,674,000
• Suarez & Munoz Construction, Inc. $4,430,000
• Kerex Engineering $4,515,000
Procurement Process
3 Azul Works, Inc.
Base Bid $3,295,000
Construction Contingency (15%) $ 494,250
Total Project Construction Budget $3,789,250
Total Construction Budget
4 Sourcewell Cooperative Purchase Agreements
Greenfield Outdoor Fitness, Inc.
Fitness Equipment $22,407
Landscape Structures, Inc.
Playground Equipment $152,697
Equipment Procurement
5 MIG, Inc.
Original Agreement $526,920
1st Amendment $ 0
2nd Amendment $ 78,942
Total $605,862
Consultant Agreement Amendment #2
6 Project Budget
Soft Costs (design, permits, fees) $1,700,000
Hard Costs (including construction) $4,250,000
Total Project Costs $5,950,000
Funding Sources
Park Fees $1,450,000
State Parks Grant $3,200,000
Developer Contributions $1,300,000
Total $5,950,000
Project Budget & Funding Sources
7 Construction: Early 2026 – Early 2027
Park Opening: Early 2027
Project Schedule
8 New Park at Linden and Pine
Award of Construction Contract / Procurement / Amendment April 8, 2026
THANK YOU