Westborough Preschool
May 13, 2026
Site Context
2 Inspiration Imagery
3 Aerial View
4 Procurement Process
5 Bid Package Advertised: February 23, 2026
Pre-Bid Site Walk: March 4, 2026
Bids Opened: April 7, 2026
• CLW Builders $10,816,168
• Bana Builders $11,082,000
• DL Faulk $11,912,000
• Foundry Construction $12,215,000
• Buhler Construction $12,330,319
• EF Brett $13,400,000
• Arana Group $14,454,543
Total Construction Budget
6 CLW Builders
Base Contract $11,564,296
Construction Contingency $1,156,704
Total Project Construction Budget $12,721,000
Project Budget & Funding Sources
7 Project Budget
Soft Costs (design, permits, fees) $3,679,000
Hard Costs (including construction) $12,721,000
Total Project Costs $16,400,000
Funding Sources
Childcare Impact Fees $15,550,000
CPF Grant $850,000
Total $16,400,000
Next Steps
8 1. Study Potential Cost Reductions

2. Communicate Construction Impacts To Park Users

3. Finalize Construction Contract

4. Groundbreaking Event

5. Sign Grant Agreement Contract
Project Schedule
9 Construction Spring 2026-Summer 2027
Opening Early Fall 2027
Westborough Preschool
City of South San Francisco

THANK YOU