Safe Routes to School 2026
Project No. ST2507, Bid No. 2709
June 10, 2026, Engineering Division
Starting with School Walk Audits
Types of Improvements
3 Curb Extensions Corner Islands Raised Crosswalks
Traffic Circle Protected Bike Lanes Bus Platforms
Project Location
Project Location
Project Location
Project Location
Bid Results
8 BidContractorRank
1 $2,837,985.75R&S Construction Management, Inc.
2 $2,846,215.75Golden Bay Construction, Inc.
3 $3,039,185.75Interstate Grading & Paving, Inc.
4 $3,040,265.45Sposeto Engineering Inc
5 $3,187,678.70JJR Construction, Inc
6 $3,225,241.80FBD Vanguard Construction, Inc.
7 $3,240,647.00Zara Construction, Inc.
8 $3,296,037.43Kerex Engineering
9 $3,339,405.80Redgwick Construction Co.
$3,487,740.00Engineers Estimate
Construction Budget
9 Construction Contract $2,837,985.75
Construction Contingency (20%) $567,597.15
Total Construction Contract Authority Budget $3,405,582.90 Schedule
10 Stage 1
Pre-Construction
•June 2026 – August 2026
Stage 2
CONSTRUCTION
•August 2026 – August 2027
Safe Routes to School 2026
City of South San Francisco