1SJAFCA MISSION STATEMENT ‐ Reduce and Manage the Region’s Flood Risk

LOWER SAN JOAQUIN RIVER PROJECT

TEN MILE SLOUGH LEVEE IMPROVEMENTS
Brookside Neighborhood Segment Briefing

STOCKTON CITY COUNCIL
AGENDA ITEM 15.1
March 1, 2022
Briefing
Agenda
SJAFCA Mission & Organization
On-going Flood Protection Projects
 Lower San Joaquin River
Today’s Focus
 Lower San Joaquin River Project (LSJR)
 Phase I
 First Increment
 Brookside Neighborhood Along Ten Mile
Slough
2  Joint Powers Authority formed in May 1995
City of Stockton, San Joaquin County and the San Joaquin County Flood Control & Water Conservation District
Address flood protection for the City of Stockton & surrounding County area
 Expanded to include Cities of Lathrop & Manteca in 2018 Board includes Directors (9) from member agencies and the public 3 Who We Are

Mission
Reduce and Manage the Region’s Flood Risk
(Cities of Stockton, Lathrop and Manteca and
some adjacent unincorporated County areas)
4 SJAFCA
Boundary
5 6
 Yes, it does flood here!
 Lower San Joaquin Project
 Taking steps now to save lives,
livelihood and the environment
Stockton Diverting Canal, 1958

7Reduce and Manage the Region’s Flood Risk

LSJR Project Partners
SJAFCA & Dept. of Water Resources & Central Valley Flood Protection Board Roles:
 Cost Share Project Costs
 Real Estate Property Acquisitions
 Utilities Relocations
 Environmental compliance (CEQA)
 Public Outreach
8Reduce and Manage the Region’s Flood Risk
LSJR Project Partners
United States Army Corps of Engineers Federal Partner Federal California Department of Water Resources
State Partner Non ‐ Federal
Sponsors
(NFS)
Central Valley Flood Protection Board
San Joaquin Area Flood Control Agency Local Partner
 Purpose: flood risk reduction; estimated 122k
people and $28B damages
 Over 23 miles of levee cutoff walls + levee raises,
new setback, geometry improvements, erosion
protection, new levees, and 2 closure structures
(incl. Smith Canal Gate)
 San Joaquin River Basin, LSJR Feasibility Report,
EIS/EIR completed in 2018
 $17 M dollar contract awarded to Kleinfelder
Inc. for the entire LSJR Geotech Explorations
 Construction contract award of Phase 1 is in year
2023 with estimated cost over $20M
 Estimated construction completion of phase 1 of
the LSJR project is end of October 2023
 Est. completion of all phases of LSJR project is
2030
9Reduce and Manage the Region’s Flood Risk

Lower San Joaquin River Project –P h a s e I
Ten Mile Slough Segment: Status Update
100% Design
March 2022
Environmental Phase
A. NEPA April 2022
B. Draft CEQA SEIR
(March 2022)
Transplant Elderberry
Shrubs & Remove
Trees
Nov. 2022
Start & Complete
Construction 2023
Lower San Joaquin River Project –P h a s e I
Ten Mile Slough
Estimated Project Costs
Design Cost: $6,346,000
 Design Cost Share: USACE-Federal ($4,125,000)
Non-Federal Sponsor –
State & Local ($2,221,000)
Construction Cost: $20M
Construction Cost Share Agreement:
Federal (65%)
State (24.5%)
Local (10.5%)
11Reduce and Manage the Region’s Flood Risk

Lower San Joaquin River Project – Phase I
Ten Mile Slough Segment: Status Update
12 Ten Mile Slough (TS_30_L)
Currently Under Design March 2022
Design Completion
July 2022
Construction
Contract Ready to
Advertise
Sept 2022
Construction
Contract Awarded
Oct 2023
Construction End
 Features found in the Feasibility Study
 Cutoff wall
 Erosion protection
Reduce and Manage the Region’s Flood Risk

Project & Community Impacts
 Traffic impacts on March Lane west of I‐5
 Estimated 120 trucks trips (approximately 25 to 30 trucks) per day between borrow and project sites
 Noise impacts due to construction equipment (Backhoe, Concrete pump, Trucks, Dozer)
 Dust impacts due to excavations and construction traffic  Construction Work hours are (7 a.m.‐7 p.m.). This was coordinated with City departments
 Truck Haul Hours (8 a.m.‐4 p.m.)
 Construction window –2  years (2022 & 2023)
13Reduce and Manage the Region’s Flood Risk

RD 2119/2115/1608 Fourteen Mile Slough
14 June 2022 ‐ Geotech &
Pre‐Design Complete
June 2023 ‐ Design
Complete
Oct 2024 ‐
Construction Contract
Ready to Advertise
Mar 2025 ‐
Construction Contract
Issued
Nov 2025 ‐
Construction End
Shima Tract
Brookside
Reduce and Manage the Region’s Flood Risk

Conclusion
 Insight into role of your SJAFCA in protecting lives, livelihoods, and environment
 Mindful of the impacts of flood protection improvements – a necessary public safety infrastructure
 Working with your staff to address those impacts
 Hold public meetings to meet and address concerns by our neighbors 15Reduce and Manage the Region’s Flood Risk

16 QUESTIONS?
SJAFCA MISSION STATEMENT ‐ Reduce and Manage the Region’s Flood Risk