Resolution No.

STOCKTON CITY COUNCIL
RESOLUTION AWARDING A PROGRESSIVE DESIGN-BUILD CONTRACT IN THE AMOUNT OF $485,591 WITH PCL CONSTRUCTION, INC. FOR THE DESIGN AND DEVELOPMENT OF A LUMP SUM PRICE PROPOSAL FOR THE REHABILITATION OF SOUTH STOCKTON SYSTEM GROUNDWATER WELL SSS8 (PROJECT NO. UH22008); AND AUTHORIZING A REAPPROPRIATION OF $5,650,000 FROM EXISTING CAPITAL PROJECTS UH21002 ($2,400,000), UH17002 ($1,750,000), UH21005 ($750,000), AND UH14014 ($750,000) TO THE SOUTH STOCKTON SYSTEM GROUNDWATER WELL SSS8 (PROJECT NO. UH22008) The Rehabilitation of South Stockton System Groundwater Well SSS8 Project will provide a design and lump sum price proposal to implement wellhead treatment and facility improvements as an economic, cost-effective approach to reactivate inactive wells in lieu of constructing new wells. Groundwater well rehabilitation in the South Stockton System will ensure continued water supply, quality, reliability, and drought resiliency for the community; and Once the Phase 1 engineering design is advanced and construction lump sum price is determined, staff will return to Council to award the Phase 2 construction contract; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:

The Progressive Design-Build Contract for the Project, in the amount of $485,591, between the City of Stockton and PCL Construction, Inc., of Tempe AZ is hereby awarded, a copy of which is attached hereto as Exhibit 1 and incorporated by reference.

The City Manager is hereby authorized and directed to execute the Progressive Design-Build Contract for the Project with PCL Construction, Inc.

The City Manager is hereby authorized to take the appropriate actions to carry out the purpose and intent of the resolution.

The City Manager is hereby authorized to reappropriate funds in the amount of $5,650,000 from existing capital projects UH21002 ($2,400,000), UH17002 ($1,750,000), UH21005 ($750,000), and UH14014 ($750,000) to the South Stockton System Groundwater Well SSS8 (Project No. UH22008).

This Resolution shall take effect upon its adoption.

The City Manager is authorized to take all necessary and appropriate steps to carry out the purpose and intent of this Resolution.

PASSED, APPROVED, and ADOPTED: March 22, 2022 .

KEVIN J. LINCOLN II
Mayor of the City of Stockton
ATTEST:

ELIZA R. GARZA, CMC
City Clerk of the City of Stockton