Resolution No.
STOCKTON CITY COUNCIL
RESOLUTION APPROVING THE NOTICE OF EXEMPTION NO. NOE58-21, APPROVING THE PLANS AND SPECIFICATIONS, AND AWARDING A CONSTRUCTION CONTRACT FOR THE NEIGHBORHOOD TRAFFIC MANAGEMENT PROGRAM, PROJECT NO. WT16008 On December 16, 2021, the City Clerk of the City of Stockton opened, examined, and publicly declared the sealed proposals or bids offered for the Neighborhood Traffic Management Program, Project No. WT16008; and The project will install approximately 15 traffic calming measures in each of the four neighborhoods consisting of speed humps/cushions/tables, striping, warning signs, and pavement markings; and Robert Burns Construction, Inc. is the lowest responsive and responsible bidder in the amount of $138,630, and its bid is regular in all respects; and The project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA) as specified under section 15301(c) of the CEQA Guidelines, because this is a discretionary project under the City’s jurisdiction and qualifies as a project which has been determined to not have a significant effect on the environment; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:
The City Council approves the filing of Notice of Exemption No. NOE58-21 under CEQA for the Neighborhood Traffic Management Program, Project No. WT16008, a copy of which is attached as Exhibit 1 and incorporated by this reference.
The City Council approves the plans and specifications for the Neighborhood Traffic Management Program, Project No. WT16008.
3. The City Council awards a Construction Contract between the City of Stockton and Robert Burns Construction, Inc., in the amount of $138,630, and the City Manager is authorized and directed to execute same, a copy of which is attached as Exhibit 2 and incorporated by this reference.
4. The City Council authorizes the City Manager to execute two optional one-year extensions to the Construction Contract upon completion of the original term, at an annual cost of $138,630, for a total contract amount of $415,890.
5. The City Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.
PASSED, APPROVED, and ADOPTED March 22, 2022 .
KEVIN J. LINCOLN II
Mayor of the City of Stockton
ATTEST:
ELIZA R. GARZA, CMC
City Clerk of the City of Stockton