Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

Resolution No.

STOCKTON CITY COUNCIL
RESOLUTION APPROVING THE NOTICE OF EXEMPTION NO. NOE32-21, APPROVING THE PLANS AND SPECIFICATIONS, AND AWARDING A CONSTRUCTION CONTRACT FOR THE ALEXANDRIA AND FIVE MILE SLOUGH CULVERT REPLACEMENT, PROJECT NO. WT19018 On January 20, 2022, the City Clerk of the City of Stockton opened, examined, and publicly declared the sealed proposals or bids offered for the Alexandria and Five Mile Slough Culvert Replacement, Project No. WT19018 (formerly PW1918); and The project will replace the existing corrugated metal pipe culvert beneath Alexandria Place and Five Mile Slough. The project will also install erosion mitigation elements near the Alexandria Place and Five Mile Slough storm pump station; and Sinclair General Engineering Construction, Inc. is the apparent low bidder in the amount of $708,215; and The project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA) as specified under Section 15301(d) of the CEQA Guidelines, because this is a discretionary project under the City’s jurisdiction and qualifies as a project which has been determined to not have a significant effect on the environment; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:

The City Council approves the filing of Notice of Exemption No. NOE32-21 under the CEQA for the Alexandria and Five Mile Slough Culvert Replacement, Project No. WT19018 (formerly PW1918), a copy of which is attached as Exhibit 1 and incorporated by this reference.

The City Council approves the plans and specifications for the Alexandria and Five Mile Slough Culvert Replacement, Project No. WT19018 (formerly PW1918).

The City Council awards a Construction Contract between the City of Stockton and Sinclair General Engineering Construction, Inc., in the amount of $708,215, and the City Manager is authorized and directed to execute same, a copy of which is attached as Exhibit 2 and incorporated by this reference. //
//
The City Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.

PASSED, APPROVED, and ADOPTED April 5, 2022 .

KEVIN J. LINCOLN II
Mayor of the City of Stockton
ATTEST:

ELIZA R. GARZA, CMC
City Clerk of the City of Stockton