STOCKTON CITY COUNCIL
RESOLUTION APPROVING THE NOTICE OF EXEMPTION NO. NOE59-21, APPROVING THE PLANS AND SPECIFICATIONS, AND AWARDING A CONSTRUCTION CONTRACT FOR THE MCNAIR SOCCER COMPLEX PHASE 2, PROJECT NO. CR16024 On December 16, 2021, the City Clerk of the City of Stockton opened, examined, and publicly declared the sealed proposals or bids offered for the McNair Soccer Complex Phase 2, Project No. CR16024; and The Phase 2 improvements include installation of four electronic scoreboards for the baseball fields, installation of a fenced storage area, and upgrading the security entrance gate to the west side of the facility; and TBS Contractors is the lowest responsible bidder in the amount of $325,924.84; and The project conforms with the City’s General Plan, pursuant to California Government Code, section 65402, and is categorically exempt from the requirements of the California Environmental Quality Act (CEQA) as specified under sections 15301(e), 15301(h), and 15303(e) of the CEQA Guidelines, because this is a discretionary project under the City’s jurisdiction and qualifies as a project which has been determined to not have a significant effect on the environment; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:

The City Council approves the filing of Notice of Exemption No. NOE59-21 under the CEQA for the McNair Soccer Complex Phase 2, Project No. CR16024, a copy of which is attached as Exhibit 1 and incorporated by this reference.

The City Council approves the plans and specifications for the McNair Soccer Complex Phase 2, Project No. CR16024.

The City Council awards a Construction Contract between the City of Stockton and TBS Contractors, in the amount of $325,924.84, and the City Manager is authorized and directed to execute same, a copy of which is attached as Exhibit 2 and incorporated by this reference. //
//
The City Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.

PASSED, APPROVED, and ADOPTED April 5, 2022 .