NEW CITY HALL
RENOVATIONS AND  RELOCATION PROJECT
Public Works Department
City Council Meeting
May 3, 2022
Agenda Item 9.2
PROJECT LOCATION
New City Hall Renovations and Relocation Project
PROJECT INFORMATION
New City Hall Renovations and Relocation Project
 Existing Site:  4.83‐acres with two buildings
 501 W. Weber –5 ‐Story building (58,929 sf)
 509 W. Weber –5 ‐Story building over basement (70,690 sf)  Improvements:   Tenant, onsite & parking lot across street  2018‐2021 – Space planning, design, construction plans  Indigo Hammond + Playle Architects
 November 2021 – Approve Construction Management Contract  Griffin Structures
 March 2022 – Open construction bids –N e w City Hall
 Consolidation of City Departments & Services
 Mayor & Council
 City Manager
 City Attorney
 City Clerk
 Administrative Services
 Community Development
 Economic Development
 Human Resources
 Information Technology
 Fire Administration
 Public Works
PROJECT GOAL
New City Hall Renovations and Relocation Project
 May 2022 – Award New City Hall Construction Contract
 Roebbelen Contracting, Inc.
 Construction starts Summer 2022
 May 2022 –A p p r o v ed e s i g n amendment #5
 Indigo Hammond + Playle Architects
 Spring 2023 – Award Parking Lot Construction Contract  Spring 2024 –E s t i m a t e d construction completion for both projects  Spring‐Summer 2024 –P h a s e d department relocations PROJECT NEXT STEPS
New City Hall Renovations and Relocation Project
DESIGN ELEMENTS
New City Hall Renovations and Relocation Project
DESIGN ELEMENTS
New City Hall Renovations and Relocation Project
DESIGN ELEMENTS
New City Hall Renovations and Relocation Project
DESIGN ELEMENTS
New City Hall Renovations and Relocation Project

DESIGN ELEMENTS
New City Hall Renovations and Relocation Project

It is recommended that the City Council adopt a resolution authorizing the City Manager to:
 Approve the plans and specifications
 Transfer $12,600,000 from the General Fund Contingency Reserves to the project E016015
 Award a $42,348,123 Construction Contract to Roebbelen Contracting, Inc. of El Dorado Hills, CA
 Execute Amendment No. 5 to the Standard Agreement with Indigo, Hammond + Playle Architects, LLP in the amount of $600,000 for design construction support services

RECOMMENDATION
New City Hall Renovations and Relocation Project
Questions?