EXHIBIT 2
1 (Rev. 10.30.18)
EXHIBIT A
STATEMENT OF WORK
1. Project Objectives
The purpose of this project is to perform a geotechnical investigation, evaluate the feasibility, provide planning, and to develop a feasibility study and report for the Delta Water Treatment Plant (DWTP) Groundwater Recharge Basin Improvements Project. The geotechnical investigations will establish the subsurface soil characteristics and evaluate if they have the likelihood of supporting a successful groundwater recharge project.
2. Proj ect Scope
Pr
ovide professional services to conduct a geotechnical investigation and hydrogeologic characterization of a portion of the DWTP site for direct groundwater recharge and recovery potential. The intent of this effort is to conduct a subsurface investigation at the DWTP site to:
• Determine soil profile characteristics for suitability of infiltrating surface- applied water for direct recharge
• Subsurface lithology
• Groundwater levels
• Potential storage volume (volume of water that can be recharged and recovered while avoiding local impacts)
• Specific yield
• Hydraulic conductivity
• Water quality
D
ata acquired and conclusions from this work effort will be used to confirm the feasibility of a direct DWTP site recharge project. Engineering design, environmental review, water rights and project funding will be the focus of a future project phase.
3. Specifications
T
he City uses ArcGIS. The data natively is in California State Plane grid 3 EPSG 2227 – units are in feet. The GIS system does not adhere to a vertical system.
The horizontal and vertical coordinate system and datums will be based on the North American Datum of 1983 (NAD83) converted to the California Grid EXHIBIT 2
2 (Rev. 10.30.18)
Coordinate System of 1983, Zone 3 (CA83111-F) as referenced by the City of Stockton Horizontal Control System.
The vertical datum will be based on the National Vertical Datum of 1929 (NGVD29) as referenced by available City of Stockton 1996 Local Adjustment (COS96) benchmarks.
4. Major
Deliverables
• T
echnical Memorandum Summarizing results of Literature Search • Meetings to discuss project and results
• Topographic Survey in feature class format within a file geodatabase using NAD83 State Plane, California Zone 3 (feet)
• Summarizing results of utility locations and historical land use • Geophysical survey analysis report, including lithologic and stratigraphic data interpretations
• Final Work Plan
• Drilling permits
• Model Documentation Report
• Feasibility Report
5. Tasks That Support the Deliverables
T
ask 1: Project Management
T
he Consultant shall provide comprehensive project management services to include budget and schedule maintenance, resource allocation, communication management and quality assurance and quality control of project deliverables.
C
onsultant shall establish a regional geotechnical setting for the DWTP groundwater recharge and recovery site by reviewing and referencing publicly sourced geotechnical information including existing well and groundwater monitoring locations, groundwater elevations, groundwater flow direction and groundwater quality data to be used to plan the geotechnical and hydrogeologic approach and site groundwater recharge and recovery evaluation.
T
ask 2: GIS-based Survey, Utilities Evaluation and Site Assessments P
rovide all field survey work necessary to support the subsurface investigation effort. Survey and base mapping of the project site shall be prepared in US Customary English units by a California licensed Land Surveyor in EXHIBIT 2
3 (Rev. 10.30.18)
accordance with the City guidelines in Geographical Information System (GIS) format.
• Utilities Research
• Coordinate the proposed geotechnical work with existing field conditions and utilities.
• Site Assessments
Research property history for any prior site assessments to determine any prior site uses that may impact the geotechnical work or site suitability.
Task 3: Surface Geophysical Survey
Consultant shall conduct a surface geophysical survey of the DWTP recharge pond sites utilizing an Electrical Resistivity Profiling (ERP) method.
The d ata shall provide a Geo physical survey analysis report, including lithologic and stratigraphic data interpretation.
Task 4: Preliminary Geotechnical Investigation Approach and Planning Activities
Consultant shall provide a draft work plan and schedule demonstrating the approach to the geotechnical investigation that will document subsurface soil conditions over the site.
The preliminary geotechnical investigation approach and planning activities must provide adequate detail regarding the suitability of the soil matrix to support the hydrogeologic characterization effort and ultimately inform the potential of the DWTP site to support a groundwater recharge and recovery operation.
Task 5: Final Geotechnical Plan
Upon review and approval of City staff, Consultant shall finalize the geotechnical investigation plan and schedule to project completion.
Task 6: Permits
EXHIBIT 2
4 (Rev. 10.30.18)
Consultant is responsible for acquiring the necessary regulatory approvals and required permits. Submit applications and pay associated fees in advance of the geotechnical investigation.
Task 7: Geotechnical Investigation
• Conduct exploratory test borings in accordance with the Final Geotechnical Plan.
• Maintain a boring log of the soils encountered for visual examination, classification, and laboratory testing.
• Conduct field penetration tests to evaluate relative density, strength, compression, and percolation characteristics of the native soils. • Submit soil and groundwater samples to a certified laboratory for testing to confirm the following characteristics:
o Density
o Gradation
o Strength
o Compression
o Corrosion Characteristics
o TDS
o Nitrates
o TOC (THM potential)
o Other recommended analyses not listed here
Task 8: Hydrogeologic Characterization
The purpose of the hydrogeologic characterization is to assess the ability of the site to accept, store and recover stored surface water. This characterization shall include the following:
• Expected percolation rate
• Specific yield estimate
• Hydraulic conductivity
• Available storage estimate
• Recovery well production rates (location and number of recovery wells) • Existing groundwater quality
• Groundwater flow direction
EXHIBIT 2
5 (Rev. 10.30.18)
Task 9: Feasibility Report
This task will compile results of the geotechnical and hydrogeologic characterization into a Groundwater Recharge and Recovery Project Feasibility Report. This report shall confirm the following:
• Suitability to recharge surface-applied water in terms of feet/day over the site and an estimate of the annual quantity of water capable of being recharged to the underlying groundwater basin
• Potential for groundwater recovery in terms of million gallons per day or acre-feet per year
• Recommendation for monitoring groundwater movement to determine the volume of water recharged and available for recovery without negatively impacting the groundwater basin and/or nearby private (or public) wells • Preliminary basin layout that considers the existing surface water delivery locations and how water is best distributed and managed across the site • Environmental clearance requirements
• Permitting requirements
• Operation and maintenance recommendations
• Estimate of probable design and construction cost
6. N
otices
Pursuant to Exhibit C – General Terms and Conditions, Paragraph 15 – Notices, the mailing address for all required notices is as follows:
Contractor: Geosyntec Consultants, Inc City: City of Stockton 3043 Gold Canal DR, Suite 100 Attn: City Manager
Rancho Cordova, CA 95670 425 N. El Dorado Street
Stockton, CA 95202
7. K ey Personnel
Danny Trejo
Program Manager III, Water Division
11373 N Lower Sacramento Rd
Lodi, CA 95242
8. O ption to Renew.
There is no option to renew.
EXHIBIT 2
NOTE: The City of Stockton is now using the online insurance program PINS Advantage. Once you have been awarded a contract you will receive an email from the City’s online insurance program requesting you to forward the email to your insurance provider(s).
Exhibit B:
I
nsurance Requirements for Professional Services
C
ontractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Contractor, its agents, representatives, or employees.
MINIMUM SCOPE AND LIMIT OF INSURANCE
Coverage shall be at least as broad as:
1. Com
mercial General Liability (CGL): Insurance Services Office Form CG 00 01 covering CGL on an “occurrence” basis, including products and completed operations, property damage, bodily injury and personal & advertising injury with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location (ISO CG 25 03 or 25 04) or the general aggregate limit shall be twice the required occurrence limit.
2. Aut
omobile Liability: Insurance Services Office Form Number CA 0001 covering, Code 1 (any auto), or if Contractor has no owned autos, Code 8 (hired) and 9 (non- owned), with limit no less than $1,000,000 per accident for bodily injury and property damage.
3. Work
ers’ Compensation insurance as required by the State of California, with Statutory Limits, and Employer’s Liability Insurance with limit of no less than $1,000,000 per accident for bodily injury or disease.
(Not required if Contractor provides written verification it has no employees)
4. Pro
fessional Liability (Errors and Omissions) Insurance appropriate to the Contractor’s profession, with limit no less than $2,000,000 per occurrence or claim, $2,000,000 aggregate. (If Claims-made, see below.)
It
shall be a requirement under this agreement that any available insurance proceeds broader than or in excess of the specified minimum insurance coverage requirements and/or limits shall be available to the Additional Insured. Furthermore, the requirements for coverage and limits shall be (1) the minimum coverage and limits specified in this Agreement; or (2) the broader coverage and maximum limits of coverage of any Insurance policy or proceeds available to the named insured; whichever is greater. No EXHIBIT 2
representation is made that the minimum insurance requirements of this agreement are sufficient to cover the obligations of the Contractor under this agreement.
Limits of Insurance
The limits of insurance required in this agreement may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non-contributory basis before the City’s own insurance or self-insurance shall be called upon to protect it as a named insured.
Other Insurance Provisions
The insurance policies are to contain, or be endorsed to contain, the following provisions:
Additional Insured Status
The City of Stockton, its officers, officials, employees, and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts, or equipment furnished in connection with such work or operations. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance (at least as broad as ISO Form CG 20 10 11 85 or if not available, through the addition of both CG 20 10, CG 20 26, CG 20 33, or CG 20 38; and CG 20 37 if a later edition is used). Additional insured Name of Organization shall read “City of Stockton, its officers, officials, employees, and volunteers.” Policy shall cover City of Stockton, its officers, officials, employees, and volunteers for all locations work is done under this contract.
Primary Coverage
The Additional Insured coverage under the Contractor’s policy shall be “primary and non-contributory” and will not seek contribution from the City’s insurance or self- insurance and shall be at least as broad as CG 20 01 04 13. The City of Stockton does not accept endorsements limiting the Contractor’s insurance coverage to the sole negligence of the Named Insured.
Notice of Cancellation
Each insurance policy required above shall state that coverage shall not be canceled, except with notice to the City of Stockton.
EXHIBIT 2
Waiver of Subrogation
Contractor hereby grants to City of Stockton a waiver of any right to subrogation which any insurer of said Contractor may acquire against the City of Stockton by virtue of the payment of any loss under such insurance. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation, but this provision applies regardless of whether or not the City of Stockton has received a waiver of subrogation endorsement from the insurer. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of the City of Stockton for all work performed by the Contractor, its employees, agents and subcontractors.
Self -Insured Retentions
All Self-insured retentions must be disclosed to Risk Management for approval and shall not reduce the limits of liability. The City of Stockton may require the Contractor to purchase coverage with a lower retention or provide proof of ability to pay losses and related investigations, claim administration, and defense expenses within the retention.
The policy language shall provide, or be endorsed to provide, that the self-insured retention may be satisfied by either the named insured or City of Stockton.
Acceptability of Insurers
Insurance is to be placed with insurers with a current A.M. Best’s rating of no less than A:VII, unless otherwise acceptable to the City of Stockton.
Claims Made Policies (note – applicable only to professional liability)
If any of the required policies provide coverage on a claims-made basis:
1. The Retroactive Date must be shown and must be before the date of the contract or the beginning of contract work.
2. Insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of the contract of work .
3. If coverage is canceled or non-renewed, and not replaced with another claims - made policy form with a Retroactive Date prior to the contract effective date, the Contractor must purchase “extended reporting” coverage for a minimum of five (5) years after completion of contract work.
EXHIBIT 2
Verification of Coverage
Contractor shall furnish the City of Stockton with original certificates and amendatory endorsements or copies of the applicable policy language effecting coverage required by this clause. All certificates and endorsements are to be received and approved by the City of Stockton Risk Services before work commences. However, failure to obtain the required documents prior to the work beginning shall not waive the Contractor’s obligation to provide them. The City of Stockton reserves the right to require complete, certified copies of all required insurance policies, including endorsements required by these specifications, at any time.
Contractor shall, prior to the commencement of work under this Agreement, provide the City of Stockton with a copy of its declarations page(s) and endorsement page(s) for each of the required policies.
Subcontractors
Contractors shall require and verify that all subcontractors, or other parties hired for this work, purchase and maintain coverage for indemnity and insurance requirements as least as broad as specified in this agreement to the extent they apply to the scope of the subcontractor’s work with the same certificate of insurance requirements and naming as additional insureds all parties to this contract. Contractor shall include the following language in their agreement with Subcontractors: “S ubcontractors hired by
Contractor agree to be bound to Contractor and City in the same manner and to the same extent as Contractor is bound to City under the contract documents and provide a valid certificate of insurance and the required endorsements included in the agreement as proof of compliance prior to commencement of any work and to include this same requirement for any subcontractors they hire for this work. A copy of the owner contract document indemnity and insurance provisions will be furnished to the subcontractor upon request.” Contractor shall provide proof of such compliance and verification to the City upon request.
Special Risks or Circumstances
City of Stockton reserves the right to modify these requirements, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other special circumstances.
Certificate Holder Address
Proper address for mailing certificates, endorsements and notices shall be:
City of Stockton Attn: City Risk Services
400 E Main Street, 3
rd Floor – HR
Stockton, CA 95202
EXHIBIT 2
1 (Rev. 10.30.18; Mod 10.28.20 SG)
EXHIBIT C
GENERAL TERMS AND CONDITIONS
1. Goods, Equipment and Services. Subject to the terms and conditions set forth in this Agreement, Contractor shall provide to City the services described in Exhibit A of the Agreement . Contractor shall provide said services at the time, place and in the manner specified in Exhibit A of the Agreement.
2. City Assistance, Facilities, Equipment and Clerical Support. Except as set forth in Exhibit A, Contractor shall, at its sole cost and expense, furnish and maintain all facilities and equipment that may be required for furnishing services pursuant to this Agreement. If applicable, City shall furnish to Contractor only the facilities and equipment listed in Exhibit A to the Agreement.
3. Compensation. City shall pay Contractor for services rendered pursuant to this Agreement as described more particularly in Exhibit A and Exhibit E to the Agreement.
3.1 Invoices submitted by Contractor to City must contain a brief description of work performed, time spent and City reference number . Within thirty (30) days of receipt of Contractor’s invoice, City will review invoice, and if acceptable make payment on approved invoice.
3.2 Upon completion of work and acceptance by City, Contractor shall have sixty (60) days in which to submit final invoicing for payment. An extension may be granted by City upon receiving a written request thirty (30) days in advance of said time limitation. The City shall have no obligation or liability to pay any invoice for work performed which the Contractor fails or neglects to submit within sixty (60) days, or any extension thereof granted by the City, after the work is accepted by the City.
4. Sufficiency of Contractor ’s Work. All Contractor services, work , and deliverables shall be performed in a good and workmanlike manner with due diligence in accordance with the degree of skill normally exercised by similar contractors supplying services and work of a similar nature, and in conformance with applicable laws, codes and professional standards . Contractor’s work shall be adequate and sufficient to meet the purposes of this Agreement.
5. Ow nership of Work. All reports, work product, all other docu ments completed or partially completed by Contractor or its approved subcontractors , in performance of this Agreement, and if applicable, drawings, designs, and plan review comments shall become the property of the City. Any and all copyrightable subject matter in all materials is hereby assigned to the City and the Contractor and its approved subcontractors agree EXHIBIT 2
2 (Rev. 10.30.18; Mod 10.28.20 SG)
to execute any additional documents that m ay be necessary to evi dence such assignment. All materials shall be delivered to the City upon completion or termination of the work under this Agreement. If any materials are lost, damaged or destroyed before final delivery to the City, the Contractor sh all replace them at its own expense.
Contractor and its approved subcontractors shall keep materials confidential. Mate rials shall not be used for purposes other than performance of services under this Agreement and shall not be disclosed to anyone not connected with these services, unless the City provides prior written consent.
6. Timeliness. Time is of the essence in this Agreement. Further, Contractor acknowledges that the failure of Contractor to comply with the time limits described in Exhibit A and Exhibit F may result in economic or other losses to the City.
7. Changes. Both parties to this Agreement understand that it may become desirable or necessary during the term of this Agreement for City to modify the scope of services provided for under this Agreement. Any material extension or change in the scope of work shall be discussed with City and the change and cost shall be memorialized in a written amendment to the original contract prior to the performance of the additional work. Until the amendment is so executed, City will not be responsible to pay any charges Contractor may incur in performing such additional services, and Contractor shall not be required to perform any such additional services.
8. Amendment. No variation of the terms of this Agreement shall be valid unless an amendment is made in writing and signed by both parties.
9. Contractor’s Status.
9.1 In performing the obligations set forth in this Agreement, Contractor shall have the status of an independent contractor and Contractor shall not be considered to be an em ployee of the City for any purpose. All persons working for or under the direction of Contractor are its agents and employees and are not agents or employees of City. Contractor by virtue of this Agreement, has no authority to bind or incur any obligation on behalf of City. Except as expressly provided in Exhibit A, Contractor has no authority or responsibility to exercise any rights or power vested in the City. No agent, officer or employee of the City is to be considered an employee of the Contractor.
It is understood by both Contractor and City that this Agreement shall not be construed or considered under any circumstances to create an employer -employee relationship or a joint venture.
9.2 Contractor shall determine the method, details and means of performing the work and services to be provided by Contractor under this Agreement. Contractor shall be responsible to City only for the requirements and results specified in this Agreement and, except as expressly provided in this Agreement, shall not be subjected to City's EXHIBIT 2
3 (Rev. 10.30.18; Mod 10.28.20 SG)
control with respect to the physical action or activities of Contractor in fulfillment of this Agreement. Contractor has control over the manner and means of performing the services under this Agreement. If necessary, Contractor has the responsibility for employing other persons or firms to assist Contractor in fulfilling the terms and obligations under this Agreement.
9.3 If in the performance of this Agreement any third persons are employed by Contractor, such persons shall be entirely and exclusively under the direction, supervision and control of Contractor. All terms of employment including hours, wages, working conditions, discipline, hiring and discharging or any other term of employment or requirements of law shall be determined by the Contractor.
9.4 It is further understood and agreed that Contractor must issue W-2 forms or other forms as required by law for income and employment tax purposes for all of Contractor's assigned personnel under the terms and conditions of this Agreement.
10. Subcontractor.
10.1 Subcontractors shall not be recognized as having any direct or contr actual relationship with City. Contractor shall be responsible for the work of subcontractor s, which shall be subject to the provisions of this Agreement. Subcontractors will be provided with a copy of the Agreement and be bound by its terms. Contractor is responsible to City for the acts and omissions of its sub contractors and persons directly or indirectly employed by them.
10.2 If in the performance of this Agreement any third persons are employed by Contractor, such persons shall be entirely and exclusively under the direction, supervision and control of Contractor. All terms of employment including hours, wages working conditions, discipline, hiring, and discharging or any other term of employment or requirement of law shall be determined by Contractor.
10.3 It is further understood and agreed that Contractor must issue W-2 forms or other forms as required by law for income and employment tax purposes for all of Contractor’s personnel.
11. Termination.
11.1 Termination for C onvenience of City . The City m ay terminate this Agreement at any time by mailing a notice in writing to Contractor. The Agreement shall then be deemed terminated, and no further work shall be performed by Contractor. If the Agreement is so terminated, the Contractor shall be paid for the work actually completed at the time the notice of termination is received.
EXHIBIT 2
4 (Rev. 10.30.18; Mod 10.28.20 SG)
11.2 Should either party default in the performance of this Agreement or materially breach any of its provisions, the other party, at that party’s option, may terminate this Agreement by giving written notification to the other party.
11.3 Funding- Non-Appropriation. It is mutually understood between the Parties that payment to the Contractor for performance shall be dependent upon the availability of appropriations by the City Council for the purposes of this Agreement. No legal liability on the part of the City for any payment may arise under this Agreement until funds are made available and until the Contractor has received funding availability, which will be confirmed in writing. If funding for any fiscal year is reduced or deleted, or if the City loses funding for any reason, the City, in its sole discretion, shall have the option to either (a) cause this Agreement to be canceled or terminated pursuant to applicable provisions of the Agreement; or (b) offer to amend the Agreement to reflect the reduced funding for this Agreement.
12. Non-Assignability. The Contractor shall not assign, sublet, or transfer this Agreement or any interest or obligation in the Agreem ent without the prior written consent of the City, and then only upon such terms and conditions as City m ay set forth in writing. Contractor shall be solely responsible for reimbursing subcontractors.
13. Indemnity and Hold Harmless. To the fullest extent permitted by law, Contractor shall hold harmless, defend at its own expense, and indemnify the City of Stockton, its officers, employees, agents, and volunteers, against any and all liability, claims, losses, damages, or expenses, including reasonable attorney’s fees, arising from all acts or omissions of contractor or its officers, agents, or employees in rendering services under this contract; excluding, however, such liability, claims, losses, damages, or expenses arising from the City of Stockton’s sole negligence or willful acts.
The duty to defend and the duty to indemnify are separate and distinct obligations. The indemnification obligations of this section shall survive the termination of this agreement.
14. Insurance. During the term of this Agreement, Contractor shall maintain in full force and effect at its own cost and expense the insurance coverage as set forth in the attached Exhibit B to this Agreement and shall otherwise comply with the other provisions of Exhibit B to this Agreement.
15. Notices. All notices herein required shall be in writing and shall be sent by certified or registered mail, postage prepaid, addressed in Exhibit A to this Agreement.
16. Conformance to A pplicable Laws. Contractor shall com ply with all applicable Federal, S tate, and Municipal laws, rules, and ordinances. Contractor shall not discri minate in the em ployment of persons or in the provision of services under this Agreem ent on the basis of any legally protected classification, including race, color, national origin, ancestry, sex or religion of such person.
EXHIBIT 2
5 (Rev. 10.30.18; Mod 10.28.20 SG)
17. Licenses, Certifications and Permits. Prior to the City’s execution of this Agreement and prior to the Contractor’s engaging in any operation or activity set forth in this Agreement, Contractor shall obtain a City of Stockton business license, which must be kept in effect during the term of this Agreement. Contractor covenants that it has obtained all certificates, licenses, permits and the like required to perform the services under this Agreement. Such licenses, certificates and permits shall be maintained in full force and effect during the term of this Agreement.
18. Records and Audits . Contractor shall maintain all re cords reg arding this Agreement and the services performed for a period of three (3) years from the date that final payment is made. At any time during normal business hours, the records shall be made available to the City to inspect and audit. To the extent Contractor renders services on a time and materials basis, Contractor shall maintain complete and accurate accounting records, in a form prescribed by City or, if not prescribed by City, in accordance with generally accepted accounting principles, such records to include, but not be limited to, payroll records, attendance cards, time sheets, and job summaries.
19. Confidentiality. Contractor shall exercise reasonable precautions to prevent the unauthorized disclosure and use of City reports, information or conclusions.
20. Conflicts of Interest . Contractor covenants that o ther th an this Agreement, Contractor has no financial interest with any official, employee or other representative of the City. Contractor and its principals do not have any financial interest in real property, sources of income or investment that would be affected in any manner of degree by the performance of Contractor’s services under this Agreement. If such an interest arises, Contractor shall immediately notify the City.
21. Waiver. In the event either City or Contractor at any time waive any breach of this Agreement by the other, such waiver shall not constitute a waiver of any other or succeeding breach of this Agreement, whether of the same or of any other covenant, condition or obligation. No payment, partial payment, acceptance, or partial acceptance by City shall operate as a waiver on the part of City of any of its rights under this Agreement.
22. Governing Law. California law shall govern any legal action pursuant to this Agreement with venue for all claims in the Superior Court of the County of San Joaquin, Stockton Branch or, where applicable, in the Federal District Court of California, Eastern District, Sacramento Division.
23. No Personal Liability. No official or employee of City shall be personally liable to Contractor in the event of any default or breach by the City or for any amount due Contractor.
EXHIBIT 2
6 (Rev. 10.30.18; Mod 10.28.20 SG)
24. Severability. If any portion of this Agreement or application thereof to any person or circumstance shall be declared invalid by a court of competent jurisdiction or if it is found in contravention of any federal, state or city statue, ordinance or regulation the rema ining provisions of this Agreement or the application thereof shall not be invalidated thereby and shall remain in full force and effect to the extent that the provisions of this Agreement are severable.
25. Non-Discrimination. During the performance of this Agreement, Contractor and its officers, employees, agents, representatives or subcontractors shall not unlawfully discriminate in violation of any federal, state, or local law, rule or regulation against any employee, applicant for employment or person receiving services under this Agreement because of race, religion, color, national origin, ancestry, physical or mental disability, medical condition (including genetic characteristics), marital status, age, political affiliation, gender identity, gender expression, sex or sexual orientation, family and medical care leave, pregnancy leave, or disability leave. Contractor and its officers, employees, agents, representative or subcontractors shall comply with all applicable Federal, State and local laws and regulations related to non- discrimination and equal opportunity, including without limitation the City’s nondiscrimination policy; the Fair Employment and Housing Act (Government Code sections 1299 0 (et seq.); California Labor Code sections 1101, 1102 and 1102.1; the Federal Civil Rights Act of 1964 (P.L. 88-352), as amended; and all applicable regulations promulgated in the California Code of Regulation or Code of Federal Regulations. Title VI of the Civil Rights Act of 1964 requires that “no person in the United States shall, on the grounds of race, color, or national origin be excluded from participation in, be denied the benefits of, or be subjected to discrimination under any program or activity receiving federal financial assistance.” (42 USC Section 2000d).
http://www.dol.gov/oasam/regs/statutes/titlevi.htm. The City requires compliance with the requirements of Title VI in all of its programs and activities regardless of funding source.
26. Force Majeure. Neith er party shall be responsible for delays or failures in performance resulting from acts of God, acts of civil or military authority, terrorism, fire, flood, strikes, war, epidemics, pandemics, shortage of power or other acts or causes reasonably beyond the control of that party. The party experiencing the force majeure event agrees to give the other party notice promptly following the occurrence of a force majeure event, and to use diligent efforts to re- commence performance as promptly as commercially practicable.
27. Taxes and Charges. Contractor shall be responsible for payment of all taxes, fees, contributions or charges applicable to the conduct of the Contractor’s business.
28. Cumulative Rights. Any specific right or remedy provided in this Agreement will not be exclusive but will be cumulative of all other rights and remedies to which may be legally entitled.
EXHIBIT 2
7 (Rev. 10.30.18; Mod 10.28.20 SG)
29. Advice of Attorney. Each party warrants and represents that in executing this Agreement, it has received independent legal advice from its attorneys or the opportunity to seek such advice.
30. Heading Not Controlling. Headings used in this Agreement are for reference purposes only and shall not be considered in construing this Agreement.
31. Entire Agreement, Integration, and Modification.
31.1 This Agreement represents the entir e integrated agreement between Contractor and the City; supersedes all prior negotiations, representations, or agreements, either written or oral between the parties and may be amended only by a written Amendment signed by the Contractor and City Manager.
31.2 All Exhibits to this Agreement and this Agreement are intended to be construed as a single document.
32. Counterparts. This Agreement may be executed in one or more counterparts, each of which shall be deemed an original. All counterparts shall be construed together and shall constitute one agreement.
33. Authority. The individual(s) executing this Agreement represent and warrant that they have the legal capacity and authority to do so on behalf of their respective legal entities.
EXHIBIT 2
1 (Rev. 10.30.18)
EXHIBIT D
PROFESSIONAL SERVICES SPECIAL TERMS AND CONDITIONS
1. D efinitions . The following words and phrases have the following meanings for purposes of this Agreement:
1 .1 "Services" means, collectively, the services, duties and responsibilities described in Exhibit A of this Agreement and any and all work necessary to complete them or carry them out fully and to the standard of performance required in this Agreement.
1.2 “Deliverable” means quantifiable goods or services that will be provided upon completion of a project. A deliverable is any tangible material, work or thing delivered by one party to the other, including associated technical documentation. A deliverable can be tangible or intangible parts of the development process, and often are specified functions or characteristics of the project.
2. G
eneral . The following terms and conditions are applicable for the Professional Services only. The special conditions shall be read in conjunction with the Standard Agreement, General Terms and Conditions (“GTC”) Exhibit C, and all other Exhibits identified in the Standard Agreement.
2 .1 Where any portion of the GTC is in conflict to or at variance with any provisions of the Special Conditions of the Agreement, then unless a different intention stated, the provision(s) of the Special Conditions of the Agreement shall be deemed to override the provision(s) of GTC only to the extent that such conflict or variations in the Special Conditions of the Agreement are not possible of being reconciled with the provisions of the GTC.
2.2 In the case of modification of a part or provision of the GTC , the unaltered part or provision, or both shall remain in effect. The Special Conditions shall relate to a particular project and be peculiar to that project but shall not weaken the character or intent of the GTC.
3. T
ime for Performance .
3.1 Contractor shall perform the services according to the schedule contained in Exhibit F.
3.2 Timeliness of Performance i) Contractor shall provide the S ervices, and Deliverables within the term and within the time limits required under this Agreement, pursuant to the provisions of Exhibit A and Exhibit F. ii) Neither Contractor nor Contractor’s agents, employees nor subcontractors are entitled to any damages from the City, nor is any party entitled to be reimbursed by the City, for damages, charges or other EXHIBIT 2
2 (Rev. 10.30.18)
losses or expenses incurred by Contractor by reason of delays or hindrances in the performance of the Services, whether or not caused by the City.
4. S tandard of Performance
In addition to Exhibit C, Section 4 and 17, Contractor agrees as follows:
4.1 Contractor’s S ervices shall be performed in accordance with generally accepted professional practices and principles and in a manner consistent with the level of care and skill ordinarily exercised by member s of Contractor’s profession currently practicing under similar conditions. Contractor shall comply with the profession’s standard of performance, applicable laws, regulations, and industry standards . By delivery of completed work, Contractor certifies that the work conforms to the requirements of this Agreement and all applicable federal, state and local laws. If Contractor is retained to perform services requiring a license, certification, registration or other similar requirement under California law, Contractor shall maintain that license, certification, registration or other similar requirement throughout the term of this Agreement.
4.2 Contractor acknowledges that it is entrusted with or has access to valuable and confidential information and records of the City and with respect to that information, Contractor agrees to be held to the standard of care of a fiduciary. Contractor shall assure that all services that require the exercise of professional skills or judgment are accomplished by professionals qualified and competent in the applicable discipline and appropriately licensed, if required by law. Contractor must provide copi es of any such licenses. Contractor remains responsible for the professional and technical accuracy of all Services or Deliverables furnished, whether by Contractor or its s ubcontractors or others on its behalf. All Deliverables must be prepared in a form and content satisfactory to the Using Agency and delivered in a timely manner consistent with the requirements of this Agreement.
4.3 If Contractor fails to comply with the foregoing standards, Contractor must perform again, at its own expense, all Services required to be re-performed as a direct or indirect result of that failure. Any review, approval, acceptance or payment for any of the Services by the City does not relieve Contractor of its responsibility for the professional skill and care and technical accuracy of its Services and Deliverables. This provision in no way limits the City’s rights against Contractor either under this Agreement, at law or in equity.
5. C
ompensation
5.1 In addition to Section 3 Compensation in Exhibit C – G TC, the Contractor shall be compensated for the services provided under this Agreement as follows:
5.1.1 Contractor shall be compensated for services rendered and accepted under this Agreement and shall be paid monthly, in arrears on a not to exceed EXHIBIT 2
3 (Rev. 10.30.18)
basis, based upon the rates set forth in Exhibit E attached hereto and made a part of this Agreement. Contractor may vary the compensation for each task in Exhibit E provided that the total project compensation listed in Exhibit E and the Standard Agreement is not exceeded.
6. P ersonnel
6.1 None of the work or services covered by this Agreement shall be subcontracted without the prior written approval of the City . Any work or services subcontracted hereunder shall be specified by written agreement and shall be subject to each provision of this Agreement. Contractor shall provide subcontractor a copy of this fully executed Agreement.
6.2 Contractor agrees to assign only competent personnel according to the reasonable and customary standards of training and experience in the relevant field to perform services under this Agreement. Failure to assign such competent personnel shall constitute grounds for termination of this Agreement. The payment made to Contractor pursuant to this Agreement shall be the full and complete compensation to which Contractor and Contractor’s officers, employees, agents, and subcontractors are entitled for performance of any work under this Agreement. Neither Contractor nor Contractor’s officers or employees are entitled to any salary or wages, or retirement, health, leave or other fringe benefits applicable to employees of the City. The C ity will not make any federal or state tax withholdings on behalf of Contractor. The City shall not be required to pay any workers' compensation insurance on behalf of Contractor . Contractor shall pay, when and as due, any and all taxes incurred as a resul t of Contractor’s compensation hereunder, including estimated taxes, and shall provide City with proof of such payments upon request.
6.3 K
ey Personnel : Because of the special skills required to satisfy the requirements of this Agreement, Contractor shall not reassign or replace key personnel without the written consent of the City, which consent the City will not unreasonably withhold. "key p ersonnel" means those job titles and the persons assigned to those positions in accordance with the provisions of t his Agreement. The City may at any time in writing notify Contractor that the City will no longer accept performance of Services under this Agreement by one or more Key Personnel listed. Upon that notice Contractor shall immediately suspend the services of the key person or persons and must replace him or them in accordance with the terms of this Agreement. A list of k ey personnel is found in Exhibit A, Scope of Services.
7. R
eports and Information
Contractor shall at such times and in such forms as the City may require furnish the City such periodic reports as it may request pertaining to the work or services undertaken pursuant to this Agreement , the costs and obligations incurred or to be incurred in connection therewith, and any other matters are covered by this Agreement as specified in Exhibit A and Exhibit E.
EXHIBIT 2
4 (Rev. 10.30.18)
8. Findings Confidential
All of the reports, information, data, et cetera, prepared or assembled by the Contractor under this Agreement are confidential and the Contractor agrees that they shall not be made available to any individual or organization without the prior written approval of the City . Contractor shall not be required under the provisions of this paragraph to keep confidential any data or information which is or becomes publicly available, is required by applicable law or by proper legal or governmental authority, is already rightfully in the Contractor’s possession without obligation of confidentiality, is independently developed by Contractor outside the scope of this Agreement or is rightfully obtained from third parties. Contractor shall give City prompt notice of any such legal or governmental demand and reasonably cooperate with City in any effort to seek a protective order or otherwise to contest such required disclosure.
9. C
opyright
No materials, including but not limited to reports, maps, or documents produced as a result of this Agreement , in whole or in part, shall be available to Contractor for copyright purposes. Any such materials produced as a result of this Agreement that might be subject to copyright shall be the property of the City and all such rights shall belong to the City, and the City shall be sole and exclusive entity who may exercise such rights.
10. D eliv erables
Contractor shall prepare or provide to the City various Deliverables. "Deliverables" include work product, such as written reviews, recommendations, reports and analyses, produced by Contractor for the City. The City may reject Deliverables that do not include relevant information or data, or do not include all documents or other materials specified in this Agreement or reasonably necessary for the purpose for which the City made this Agreement or for which the City intends to use the Deliverables. If the City determines that Contractor has failed to comply with the foregoing standards, it has 30 days from the discovery to notify Contractor of its failure. If Contractor does not correct the failure, or if it is possible to do so, within 30 days after receipt of notice from the City specifying the failure, then the City, by written notice, may treat the failure as a default of this Agreement.
Partial or incomplete Deliverables may be accepted for review only when requi red for a specific and well-defined purpose and when consented to in advance by the City . Such Deliverables will not be considered as satisfying the requirements of this Agreement and partial or incomplete Deliverables in no way relieve Contractor of its commitments under this Agreement.
EXHIBIT 2
1 (Rev. 10.30.18)
EXHIBIT E
COMPENSATION SCHEDULE
The Contractor shall be compensated for the services identified in Exhibit A, Exhibit C, and Exhibit D to this Agreement as follows:
1. Project Price
1.1 The maximum the Contractor shall be paid on this Agreement is $__538,303________ (hereafter the “not to exceed” amount). The “not to exceed” amount includes all payments to be made pursuant to this Agreement, including City approved reimbursable expenses, if any. Nothing in this Agreement requires the City to pay for work that does not meet the Standard of Performance identified in Exhibit D section 4 or other requirements of this Agreement.
1.2 Standard Reimbursable Items : Only the reimbursable items identified in Exhibit A , C, and D ( Compensation), shall be compensated to the Contractor.
Reimbursable expenses will be reimbursed without markup. Fees plus reimbursable expenses shall not exceed the amount set forth in section 1.1 of this Exhibit and a copy of the original invoice for the items listed in i, ii or iii below shall be attached to the invoice submitted to the City for reimbursement. Payments shall be based upon work documents submitted by the Contractor to the City and accepted by the City as being satisfactory to City’s needs. The City shall not pay a markup on any of the items listed in i, ii or iii.
Additionally, items such a telephone, fax, postage or freight are already included in the billable hourly rate. Contractor shall be reimbursed the direct expenses, which are the actual cost of the following items that are reasonable, necessary and actually incurred, by the Contractor in connection with the services:
i. Expenses, fees or charges for printing, reproduction or binding of documents at actual costs with no markup added to the actual cost.
ii. Any filing fees, permit fees, or other fees paid or advanced by the Contractor at actual costs with no markup added to the actual cost.
iii. Travel expenses shall be reimbursed in accordance with the City’s travel policy, which is incorporated herein by reference.
Reimbursement shall be made at actual costs with no markup added to the actual cost.
1.3 The Contractor shall be entitled to receive payments for its work performed pursuant to the Agreement. The City will pay Contractor based on invoices for acceptable work performed and approved until the “not to exceed” amount is reached.
Thereafter, Contractor must complete services based on the Agreement without additional compensation unless there is a material change to the Statement of Work and Scope by a written Amendment.
EXHIBIT 2
2 (Rev. 10.30.18)
1.4 If work is completed before the “not to exceed” amount is reached, the Contractor’s compensation will be based on the Contractor ’s invoices previously submitted for acceptable work performed and approved.
1.5 Subcontractor Costs: Compensation for sub contractors shall be limited to the same restrictions imposed on the Contractor . Maximum markup Contractor may apply to subcontractor fees, minus reimbursable expenses, shall not exceed __0___%.
2. Task Price . Below is the price for the services and reimbursable expenses as described in Exhibit A of this Agreement.
Not Applicable
3. Additional Fees. Should an amendment to the Agreement be issued for additional services that require the following items, the unit prices are as follows:
Not Applicable
5. Invoice to Address. Each invoice submitted shall identify the specific task(s) listed in Exhibit A , the contract number (purchase order number), and the completed work product/deliverable.
Invoices are to be submitted electronically to the City’s Vendor Self Service portal at http://ww1.stocktonca.gov/ or emailed directly to [email protected].
Invoices may also be mailed to:
Delta Water Treatment Plant (MUD)
Attn: MUD Finance
2500 Navy Drive
Stockton, CA 95206
EXHIBIT 2
1 (Rev, 10.30.18)
EXHIBIT F
TIMELINE
1. Consultant shall complete the requested services identified in Exhibit A as follows:
1.1 TIMELINE FOR COMPLETION OF WORK
1.1.1 Task 1 August 2022
1.1.2 Task 2 August 2022
1.1.3 Task 3 August 2022
1.1.4 Task 4 September 2022
1.1.5 Task 5 September 2022
1.1.6 Task 6 November 2022
1.1.7 Task 7 February 2023
1.1.8 Task 8 February 2023
1.1.9 Task 9 February 2023
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report Proposal Fee
We pr
opose to complete the scope of work on a Time and Materials basis, Not to Exceed without prior authorization.
Att
ached is:
1) Pri
cing Summary
2) Breakdown by Task and Other Direct Costs
3) Geosyntec Standard Rate Schedule
Assumptions
Task 1
• Project Administration will include 6-hours per month each for PM and Administrative Staff. • Quarterly progress reports will not be revised
• The TM will be revised based on one set of comments provided by the City. • The TM will be provided in electronic (pdf) format
• Two meeting will be attended by Geosyntec Project Manager and 2 Professional Staff. • Meetings will be by teleconference and will be 2-hours in duration • 3 hours of preparation time will be required by Project Manager and one Professional Staff for each meeting
Task 2
• Reports reviewed for Site Assessment will be provided by the City. • The TM
will be revised based on one set of comments provided by the City. • The TM
will be provided in electronic (pdf) format.
o A verti
cal benchmark and horizontal control with data exist and are provided within one- half
mile of site (or can be approximated)
o Dimensions are approximated based on a 80-acre square o The
survey does not include property boundary, easements or other legal property information
o The survey
does not include new aerial mapping
o There are no unique surveying or GIS guidelines required by the City o Three trips will be made to site
o No design or drafting for basin, borings or other efforts are included o Access is provided when needed for performing work
Task 3
• The City will provide access to the Site.
• The survey will be completed within seven (7) 8-hour days. • Geophysical report will be revised based on one set of comments provided by the City • The geophysical
report will be provided in electronic (pdf) format.
• A har
d copy report will not be provided.
Task 4
• The Draft Work Plan will be revised based on one set of comments provided by the City. • The Draft Work Plan will be provided in electronic (pdf) format. • Two meetings will be attended by Geosyntec Project Manager and 2 Professional Staff. • Meeting will be by teleconference and will be 2-hours in duration.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report • 3 hours of preparation time will be required by Project Manager and one Professional Staff for each meeting
Task 5
• Two hard copies of the Final Work Plan will be provided to the City. The Final Work Plan will also be provided in electronic (pdf) format.
Task 6
• Drilling permits will be obtained for 5 CPT points, 4 soil borings, 1 nested monitoring well, and 1 pumping well
Task 7
Field Setup Coordination
• The drilling contractor will prepare their own site-specific healthy plan. • No revisions to the field safety plan will be required. • The Site visit will be completed within one (1) 8-hour day.
CPT Survey
• Total depth of CPT points will be 90 feet bgs.
• The City will provide access to the Site.
• The CPT survey will be completed within four (3) 10-hour days. • Up to 6
pore pressure tests will be conducted at each CPT location Soil Borings
• Four (4) soil borings will be drilled to 90 feet bgs. • Two downhole permeability t
ests each will be conducted in the soil borings.
• Drilling a
nd testing will be completed within four (4) 10-hour workdays. • Costs do not include delays encountered due to weather conditions. • Water needed
for drilling activities will be provided by the City and located within 0.5 miles of t
he Site.
• Drill cuttings will be spread at the Site.
• No hazardous wastes will be generated
Well Installation
• One (1) Nested monitoring well will be completed in one soil boring consisting of screen intervals
at three separate depths to a depth of 90 feet bgs.
• The well completed for pumping tests will consist of 6-inch PVC casing and will be completed at a depth of 90-feet bgs.
• Drilling and development
of the nested monitoring well and pumping well will be
completed within 5 10-hour workdays.
• All work will be conducted during normal business hours. • Costs do not include delays encountered due to weather conditions. • Water
needed for drilling activities will be provided by the City and located within 0.5 miles of
the Site.
• Four vented pressure transducers with cables will be purchased for the step-test and pumping test described below.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report • Drill cuttings will be spread at the Site and purge water from development and step test will be discharged at the Site.
• No hazardous wastes will be generated
Aquifer Test
• Transducers will be placed in observation wells (3) and pumping well at least one week before c
onstant rate test to assess regional water level changes. • The aquifer
test will be 8-hours i n duration.
• Water will be discharged directly to the ground surface. • The constant rate test including recovery will be completed in 1 10-hour day.
Groundwater, Soil, and Source Water Sampling
• Including quality control samples, a total of 15 soil samples will be submitted for laboratory testing.
• Including quality
control samples, a total of 20 water samples will be submitted for laboratory
testing.
Task 8
• The Model Documentation Report will be revised based on one set of comments.
Task 9
• The Feasibility Report will be revised once based on one set of comments from the City. • A meeting will be conducted to present the results of the Report • The meeting will be attended by the PM and 2 professional staff. • The meeting will be 3-hour in duration and conducted at the City offices • A total of 4-hours each for preparation of meeting material will be required by the PM and one professional staff.
EXHIBIT 2
Labor Hours Labor
Direct
Expenses Cost
Task 1.1 Project Management 75 $13,830 $0 $13,830
Task 1.2 Data Review and Compilation 29 $5,176 $117 $5,293 Task 1.3 TM 49 $7,789 $0 $7,789
Task 1.4 Meetings 29 $5,670 $117 $5,787
Total Task Budget Authorization Request 153 $32,465 $234 $32,699 Labor Hours Labor
Direct
Expenses Cost
Task 2.1 GIS-Based Topo Survey 13 $2,419 $36,689 $39,108 Task 2.2 Utility Survey 20 $3,388 $59 $3,447
Task 2.3 Site Assessments 34 $6,472 $30 $6,502
Task 2.4 TM 35 $5,878 $0 $5,878
Total Task Budget Authorization Request 102 $18,157 $36,778 $54,935 Labor Hours Labor
Direct
Expenses Cost
Task 3.1 Geophysical Survey 18 $2,952 $48,341 $51,293
Task 3.2 Report 19 $3,286 $0 $3,286
Total Task Budget Authorization Request 37 $6,238 $48,341 $54,579 Labor Hours Labor
Direct
Expenses Cost
Task 4.1 Draft Work Plan 82 $15,203 $0 $15,203
Task 4.2 Meetings 24 $5,086 $0 $5,086
Total Task Budget Authorization Request 106 $20,289 $0 $20,289 Labor Hours Labor
Direct
Expenses Cost
Task 5.1 Final Work Plan 35 $5,545 $0 $5,545
Total Task Budget Authorization Request 35 $5,545 $0 $5,545 Labor Hours Labor
Direct
Expenses Cost
Task 6.1 Final Work Plan 8 $1,226 $4,400 $5,626
Total Task Budget Authorization Request 8 $1,226 $4,400 $5,626 Labor Hours Labor
Direct
Expenses Cost
Task 7.1 Field Setup 30 $5,572 $88 $5,660
Task 7.2 CPT 44 $7,096 $26,159 $33,255
Task 7.3 Soil Borings 62 $11,638 $61,636 $73,274
Task 7.4 Well Installation 72 $12,128 $90,496 $102,624
Task 7.5 Aquifer Test 53 $8,964 $21,160 $30,124
Task 7.6 Lab 11 $1,924 $41,107 $43,031
Total Task Budget Authorization Request 272 $47,322 $240,646 $287,968 Labor Hours Labor
Direct
Expenses Cost
Task 8.1 Compile and Review Data 25 $5,172 $0 $5,172
Task 8.2 Model 96 $18,144 $0 $18,144
Task 8.3 TM 63 $11,327 $0 $11,327
Total Task Budget Authorization Request 184 $34,643 $0 $34,643 Labor Hours Labor
Direct
Expenses Cost
Task 9.1 Report 200 $36,810 $0 $36,810
Task 9.2 Meeting 27 $5,138 $71 $5,209
Total Task Budget Authorization Request 227 $41,948 $71 $42,019 Project Total Budget Authorization 1124 $207,833 $330,470 $538,303 Proposal Fee Summary
TASK 9 - Feasibility Report
TASK 7 - Investigation
TASK 8 - Hydrogeologic Characterization
TASK 1 - PM and Review
TASK 2 - GIS, Utilities, and Site Assessment
TASK 4 - Draft Work Plan
TASK 5 - Final Work Plan
TASK 6 - Permits
TASK 3 - ERP Survey
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Staff Professional $132 $0 $0 $0 $0 0 $0
Senior Staff Professional $154 $0 20 $3,080 $0 $0 20 $3,080 Professional $175 $0 $0 15 $2,625 4 $700 19 $3,325
Project Professional $198 $0 $0 $0 $0 0 $0
Senior Professional $224 $0 5 $1,120 10 $2,240 10 $2,240 25 $5,600 Principal $244 $0 $0 $0 $0 0 $0
Senior Consultant/Project Manager $244 50 $12,200 4 $976 5 $1,220 10 $2,440 69 $16,836 Senior Principal $262 $0 $0 2 $524 $0 2 $524
$0 $0 $0 $0 0 $0
Technician I $70 $0 $0 $0 $0 0 $0
Technician II $74 $0 $0 $0 $0 0 $0
Senior Technician I $83 $0 $0 $0 $0 0 $0
Senior Technician II $89 $0 $0 $0 $0 0 $0
Site Manager I $98 $0 $0 $0 $0 0 $0
Site Manager II $108 $0 $0 $0 $0 0 $0
Construction Manager I $120 $0 $0 $0 $0 0 $0
Construction Manager II $130 $0 $0 $0 $0 0 $0
$0 $0 $0 $0 0 $0
Senior Designer $170 $0 $0 $0 $0 0 $0
Designer $140 $0 $0 $0 $0 0 $0
Senior Drafter/Senior CADD Operator $125 $0 $0 2 $250 $0 2 $250 Drafter/CADD Operator/Artist $110 $0 $0 $0 $0 0 $0
Project Administrator $70 15 $1,050 $0 5 $350 $0 20 $1,400 Clerical $58 10 $580 $0 10 $580 5 $290 25 $1,450
$0 $0 $0 $0 0 $0
Total Direct Labor 75 $13,830 29 $5,176 49 $7,789 29 $5,670 182 $32,465 Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 $0 $0 $0 0 $0.00 Mileage (Federal rate) $0.585 $0 200 $117 $0 200 $117 400 $234.00 Rental Car Expense (daily, all-inclusive) $87.87 $0 $0 $0 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 $0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
TOTAL ODCs $0 $117 $0 $117 $234
Task Grand Total $13,830 $5,293 $7,789 $5,787 $32,699
TM Meetings
Task Name Total
Task 1.1
Project Management
Task 1.2 Task 1.3 Task 1.4
Task Name Task Name Task Name
Data Review and
Compilation
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Staff Professional $132 $0 $0 $0 $0 0 $0
Senior Staff Professional $154 8 $1,232 8 $1,232 8 $1,232 $0 24 $3,696 Professional $175 1 $175 8 $1,400 16 $2,800 20 $3,500 45 $7,875 Project Professional $198 $0 $0 $0 $0 0 $0
Senior Professional $224 $0 $0 $0 $0 0 $0
Principal $244 $0 $0 8 $1,952 2 $488 10 $2,440
Senior Consultant/Project Manager $244 2 $488 1 $244 2 $488 2 $488 7 $1,708 Senior Principal $262 2 $524 1 $262 $0 1 $262 4 $1,048
$0 $0 $0 $0 0 $0
Technician I $70 $0 $0 $0 $0 0 $0
Technician II $74 $0 $0 $0 $0 0 $0
Senior Technician I $83 $0 $0 $0 $0 0 $0
Senior Technician II $89 $0 $0 $0 $0 0 $0
Site Manager I $98 $0 $0 $0 $0 0 $0
Site Manager II $108 $0 $0 $0 $0 0 $0
Construction Manager I $120 $0 $0 $0 $0 0 $0
Construction Manager II $130 $0 $0 $0 $0 0 $0
$0 $0 $0 $0 0 $0
Senior Designer $170 $0 $0 $0 5 $850 5 $850
Designer $140 $0 $0 $0 $0 0 $0
Senior Drafter/Senior CADD Operator $125 $0 2 $250 $0 $0 2 $250 Drafter/CADD Operator/Artist $110 $0 $0 $0 $0 0 $0
Project Administrator $70 $0 $0 $0 $0 0 $0
Clerical $58 $0 $0 $0 5 $290 5 $290
$0 $0 $0 $0 0 $0
Total Direct Labor 13 $2,419 20 $3,388 34 $6,472 35 $5,878 102 $18,157 Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 $0 $0 $0 0 $0.00 Mileage (Federal rate) $0.585 100 $59 100 $59 50 $30 $0 250 $148.00 Rental Car Expense (daily, all-inclusive) $87.87 $0 $0 $0 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 AAX $33,300.00 1 $36,630 $0 $0 $0 1 $36,630.00
$0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
$0 $0 $0 $0 0 $0.00
TOTAL ODCs $36,689 $59 $30 $0 $36,778
Task Grand Total $39,108 $3,447 $6,502 $5,878 $54,935
Task 2.3 Task 2.4
GIS-Based Topo Survey Utility Survey Site Assessments TM TotalTask Name Task Name Task Name Task Name
Task 2.1 Task 2.2
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost
Staff Professional $132 $0 $0 0 $0
Senior Staff Professional $154 16 $2,464 15 $2,310 31 $4,774 Professional $175 $0 $0 0 $0
Project Professional $198 $0 $0 0 $0
Senior Professional $224 $0 $0 0 $0
Principal $244 $0 $0 0 $0
Senior Consultant/Project Manager $244 2 $488 4 $976 6 $1,464 Senior Principal $262 $0 $0 0 $0
$0 $0 0 $0
Technician I $70 $0 $0 0 $0
Technician II $74 $0 $0 0 $0
Senior Technician I $83 $0 $0 0 $0
Senior Technician II $89 $0 $0 0 $0
Site Manager I $98 $0 $0 0 $0
Site Manager II $108 $0 $0 0 $0
Construction Manager I $120 $0 $0 0 $0
Construction Manager II $130 $0 $0 0 $0
$0 $0 0 $0
Senior Designer $170 $0 $0 0 $0
Designer $140 $0 $0 0 $0
Senior Drafter/Senior CADD Operator $125 $0 $0 0 $0
Drafter/CADD Operator/Artist $110 $0 $0 0 $0
Project Administrator $70 $0 $0 0 $0
Clerical $58 $0 $0 0 $0
$0 $0 0 $0
Total Direct Labor 18 $2,952 19 $3,286 37 $6,238
Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 2 $324 $0 2 $324.00 Mileage (Federal rate) $0.585 $0 $0 0 $0.00
Rental Car Expense (daily, all-inclusive) $87.87 $0 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 2 $249 $0 2 $249.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 Norcal $43,425.00 1 $47,768 $0 1 $47,768.00
$0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
TOTAL ODCs $48,341 $0 $48,341
Task Grand Total $51,293 $3,286 $54,579
Geophysical Survey TM
TotalTask Name Task Name
Task 3.1 Task 3.2
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost
Staff Professional $132 $0 $0 0 $0
Senior Staff Professional $154 $0 $0 0 $0
Professional $175 35 $6,125 10 $1,750 45 $7,875
Project Professional $198 $0 $0 0 $0
Senior Professional $224 8 $1,792 4 $896 12 $2,688
Principal $244 8 $1,952 $0 8 $1,952
Senior Consultant/Project Manager $244 10 $2,440 10 $2,440 20 $4,880 Senior Principal $262 5 $1,310 $0 5 $1,310
$0 $0 0 $0
Technician I $70 $0 $0 0 $0
Technician II $74 $0 $0 0 $0
Senior Technician I $83 $0 $0 0 $0
Senior Technician II $89 $0 $0 0 $0
Site Manager I $98 $0 $0 0 $0
Site Manager II $108 $0 $0 0 $0
Construction Manager I $120 $0 $0 0 $0
Construction Manager II $130 $0 $0 0 $0
$0 $0 0 $0
Senior Designer $170 $0 $0 0 $0
Designer $140 8 $1,120 $0 8 $1,120
Senior Drafter/Senior CADD Operator $125 $0 $0 0 $0
Drafter/CADD Operator/Artist $110 $0 $0 0 $0
Project Administrator $70 $0 $0 0 $0
Clerical $58 8 $464 $0 8 $464
$0 $0 0 $0
Total Direct Labor 82 $15,203 24 $5,086 106 $20,289
Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 $0 0 $0.00 Mileage (Federal rate) $0.585 $0 $0 0 $0.00
Rental Car Expense (daily, all-inclusive) $87.87 $0 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 Land Surveyor $0 $0 0 $0.00
Utility Locator $0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
TOTAL ODCs $0 $0 $0
Task Grand Total $15,203 $5,086 $20,289
Draft Work Plan Meetings
TotalTask Name Task Name
Task 4.1 Task 4.2
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost
Staff Professional $132 $0 0 $0
Senior Staff Professional $154 $0 0 $0
Professional $175 15 $2,625 15 $2,625
Project Professional $198 $0 0 $0
Senior Professional $224 5 $1,120 5 $1,120
Principal $244 $0 0 $0
Senior Consultant/Project Manager $244 5 $1,220 5 $1,220 Senior Principal $262 $0 0 $0
$0 0 $0
Technician I $70 $0 0 $0
Technician II $74 $0 0 $0
Senior Technician I $83 $0 0 $0
Senior Technician II $89 $0 0 $0
Site Manager I $98 $0 0 $0
Site Manager II $108 $0 0 $0
Construction Manager I $120 $0 0 $0
Construction Manager II $130 $0 0 $0
$0 0 $0
Senior Designer $170 $0 0 $0
Designer $140 $0 0 $0
Senior Drafter/Senior CADD Operator $125 $0 0 $0
Drafter/CADD Operator/Artist $110 $0 0 $0
Project Administrator $70 $0 0 $0
Clerical $58 10 $580 10 $580
$0 0 $0
Total Direct Labor 35 $5,545 35 $5,545
Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 0 $0.00 Mileage (Federal rate) $0.585 $0 0 $0.00
Rental Car Expense (daily, all-inclusive) $87.87 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 $0 0 $0.00
$0 0 $0.00
$0 0 $0.00
$0 0 $0.00
$0 0 $0.00
TOTAL ODCs $0 $0
Task Grand Total $5,545 $5,545
Task 5.1
Final Work Plan
TotalTask Name
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost
Staff Professional $132 $0 0 $0
Senior Staff Professional $154 6 $924 6 $924
Professional $175 $0 0 $0
Project Professional $198 $0 0 $0
Senior Professional $224 $0 0 $0
Principal $244 $0 0 $0
Senior Consultant/Project Manager $244 1 $244 1 $244
Senior Principal $262 $0 0 $0
$0 0 $0
Technician I $70 $0 0 $0
Technician II $74 $0 0 $0
Senior Technician I $83 $0 0 $0
Senior Technician II $89 $0 0 $0
Site Manager I $98 $0 0 $0
Site Manager II $108 $0 0 $0
Construction Manager I $120 $0 0 $0
Construction Manager II $130 $0 0 $0
$0 0 $0
Senior Designer $170 $0 0 $0
Designer $140 $0 0 $0
Senior Drafter/Senior CADD Operator $125 $0 0 $0
Drafter/CADD Operator/Artist $110 $0 0 $0
Project Administrator $70 $0 0 $0
Clerical $58 1 $58 1 $58
$0 0 $0
Total Direct Labor 8 $1,226 8 $1,226
Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 0 $0.00 Mileage (Federal rate) $0.585 $0 0 $0.00
Rental Car Expense (daily, all-inclusive) $87.87 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 Permits $4,000.00 1 $4,400 1 $4,400.00
$0 0 $0.00
$0 0 $0.00
$0 0 $0.00
$0 0 $0.00
TOTAL ODCs $4,400 $4,400
Task Grand Total $5,626 $5,626
Task 6.1
Permits
TotalTask Name
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater
Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Staff Professional $132 $0 $0 $0 $0 16 $2,112 $0 0 $2,112 Senior Staff Professional $154 $0 40 $6,160 $0 60 $9,240 16 $2,464 $0 100 $17,864 Professional $175 24 $4,200 $0 50 $8,750 $0 $0 8 $1,400 82 $14,350 Project Professional $198 2 $396 $0 $0 $0 16 $3,168 $0 2 $3,564 Senior Professional $224 $0 2 $448 2 $448 2 $448 $0 $0 6 $1,344 Principal $244 $0 $0 $0 $0 $0 $0 0 $0
Senior Consultant/Project Manager $244 4 $976 2 $488 10 $2,440 10 $2,440 5 $1,220 1 $244 27 $7,808 Senior Principal $262 $0 $0 $0 $0 $0 $0 0 $0
$0 $0 $0 $0 $0 $0 0 $0
Technician I $70 $0 $0 $0 $0 $0 $0 0 $0
Technician II $74 $0 $0 $0 $0 $0 $0 0 $0
Senior Technician I $83 $0 $0 $0 $0 $0 $0 0 $0
Senior Technician II $89 $0 $0 $0 $0 $0 $0 0 $0
Site Manager I $98 $0 $0 $0 $0 $0 $0 0 $0
Site Manager II $108 $0 $0 $0 $0 $0 $0 0 $0
Construction Manager I $120 $0 $0 $0 $0 $0 $0 0 $0
Construction Manager II $130 $0 $0 $0 $0 $0 $0 0 $0
$0 $0 $0 $0 $0 $0 0 $0
Senior Designer $170 $0 $0 $0 $0 $0 $0 0 $0
Designer $140 $0 $0 $0 $0 $0 2 $280 2 $280
Senior Drafter/Senior CADD Operator $125 $0 $0 $0 $0 $0 $0 0 $0 Drafter/CADD Operator/Artist $110 $0 $0 $0 $0 $0 $0 0 $0 Project Administrator $70 $0 $0 $0 $0 $0 $0 0 $0
Clerical $58 $0 $0 $0 $0 $0 $0 0 $0
$0 $0 $0 $0 $0 $0 0 $0
Total Direct Labor 30 $5,572 44 $7,096 62 $11,638 72 $12,128 53 $8,964 11 $1,924 219 $47,322 Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 3 $486 4 $648 5 $810 4 $648 $0 16 $2,592.00 Mileage (Federal rate) $0.585 150 $88 $0 180 $106 120 $71 150 $88 $0 600 $353.00 Field Equipment and Supplys $150.00 $0 $0 4 $600 5 $750 4 $600 $0 13 $1,950.00 Transducers $2,800.00 $0 $0 $0 4 $11,200 $0 $0 4 $11,200.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 3 $373 4 $497 5 $621 2 $249 $0 14 $1,740.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 $0 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 $0 $0 $0 $0 $0 $0 0 $0.00
CPT $23,000.00 $0 1 $25,300 $0 $0 $0 $0 1 $25,300.00
Sonic $54,350.00 $0 $0 1 $59,785 $0 $0 $0 1 $59,785.00
Well Installation $51,040.00 $0 $0 $0 1 $56,144 $0 $0 1 $56,144.00 Well Development $19,000.00 $0 $0 1 $20,900 $0 $0 1 $20,900.00 Pump and Rig Aquifer Test $17,795.00 $0 $0 1 $19,575 $0 1 $19,575.00 Lab $31,370.00 $0 $0 $0 $0 $0 1 $34,507 1 $34,507.00
Geotech Lab $6,000.00 $0 $0 $0 $0 $0 1 $6,600 1 $6,600.00 TOTAL ODCs $88 $26,159 $61,636 $90,496 $21,160 $41,107 $240,646 Task Grand Total $5,660 $33,255 $73,274 $102,624 $30,124 $43,031 $287,968 Task 7.2 Task 7.3 Task 7.4 Task 7.5
Task Name Task Name Task Name Task Name Total
Task 7.5
Task Name
Aquifer Test
Task Name
Field Setup CPT Survey Soil Borings Well Installation Lab Task 7.1
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost Hours Cost
Staff Professional $132 $0 $0 $0 0 $0
Senior Staff Professional $154 5 $770 40 $6,160 25 $3,850 70 $10,780 Professional $175 2 $350 10 $1,750 5 $875 17 $2,975
Project Professional $198 6 $1,188 15 $2,970 5 $990 26 $5,148 Senior Professional $224 5 $1,120 15 $3,360 10 $2,240 30 $6,720 Principal $244 $0 $0 $0 0 $0
Senior Consultant/Project Manager $244 5 $1,220 16 $3,904 8 $1,952 29 $7,076 Senior Principal $262 2 $524 $0 4 $1,048 6 $1,572
$0 $0 $0 0 $0
Technician I $70 $0 $0 $0 0 $0
Technician II $74 $0 $0 $0 0 $0
Senior Technician I $83 $0 $0 $0 0 $0
Senior Technician II $89 $0 $0 $0 0 $0
Site Manager I $98 $0 $0 $0 0 $0
Site Manager II $108 $0 $0 $0 0 $0
Construction Manager I $120 $0 $0 $0 0 $0
Construction Manager II $130 $0 $0 $0 0 $0
$0 $0 $0 0 $0
Senior Designer $170 $0 $0 $0 0 $0
Designer $140 $0 $0 $0 0 $0
Senior Drafter/Senior CADD Operator $125 $0 $0 $0 0 $0
Drafter/CADD Operator/Artist $110 $0 $0 $0 0 $0
Project Administrator $70 $0 $0 2 $140 2 $140
Clerical $58 $0 $0 4 $232 4 $232
$0 $0 $0 0 $0
Total Direct Labor 25 $5,172 96 $18,144 63 $11,327 184 $34,643 Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 $0 $0 0 $0.00 Mileage (Federal rate) $0.585 $0 $0 $0 0 $0.00
Field Equipment and Supplys $150.000 $0 $0 $0 0 $0.00
Rental Car Expense (daily, all-inclusive) $87.87 $0 $0 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 $0 $0 $0 0 $0.00
$0 $0 $0 0 $0.00
$0 $0 $0 0 $0.00
$0 $0 $0 0 $0.00
$0 $0 $0 0 $0.00
TOTAL ODCs $0 $0 $0 $0
Task Grand Total $5,172 $18,144 $11,327 $34,643
TotalTask Name Task Name Task Name
Compile and Review
Data Model TM
Task 8.1 Task 8.2 Task 8.3
EXHIBIT 2
Fee Estimator/Project Manager Joe Turner
Date:
Project Name: DWTP Groundwater Recharge
Job Classifications and function performed (prime) 2021 Rate Table C Labor Rate Hours Cost Hours Cost Hours Cost
Staff Professional $132 $0 $0 0 $0
Senior Staff Professional $154 40 $6,160 $0 40 $6,160
Professional $175 20 $3,500 $0 20 $3,500
Project Professional $198 20 $3,960 $0 20 $3,960
Senior Professional $224 20 $4,480 $0 20 $4,480
Principal $244 5 $1,220 10 $2,440 15 $3,660
Senior Consultant/Project Manager $244 35 $8,540 7 $1,708 42 $10,248 Senior Principal $262 15 $3,930 $0 15 $3,930
$0 $0 0 $0
Technician I $70 $0 $0 0 $0
Technician II $74 $0 $0 0 $0
Senior Technician I $83 $0 $0 0 $0
Senior Technician II $89 $0 $0 0 $0
Site Manager I $98 $0 $0 0 $0
Site Manager II $108 $0 $0 0 $0
Construction Manager I $120 $0 $0 0 $0
Construction Manager II $130 $0 $0 0 $0
$0 $0 0 $0
Senior Designer $170 10 $1,700 $0 10 $1,700
Designer $140 15 $2,100 5 $700 20 $2,800
Senior Drafter/Senior CADD Operator $125 $0 $0 0 $0
Drafter/CADD Operator/Artist $110 $0 $0 0 $0
Project Administrator $70 5 $350 $0 5 $350
Clerical $58 15 $870 5 $290 20 $1,160
$0 $0 0 $0
Total Direct Labor 200 $36,810 27 $5,138 227 $41,948
Sub and ODC Markup value 10%
Subcontractors and Other Direct Costs (ODCs) Rate Units Cost
(includes
Markup)
Units
Cost
(includes
Markup)
Units Cost
Per Diem (only applicable involving overnight stay) $162.00 $0 $0 0 $0.00 Mileage (Federal rate) $0.585 $0 120 $71 120 $71.00
Field Equipment and Supplys $150.000 $0 $0 0 $0.00
Rental Car Expense (daily, all-inclusive) $87.87 $0 $0 0 $0.00 Rental 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 0 $0.00 Company 4-Wheel Drive or Truck Expense (daily, all-inclusive) $124.05 $0 $0 0 $0.00 SUBS and VENDORS ( recurring or lump-sum cost) 0 $0.00 $0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
$0 $0 0 $0.00
TOTAL ODCs $0 $71 $71
Task Grand Total $36,810 $5,209 $42,019
TotalTask Name Task Name
Feasibillity Report Meetings
Task 9.1 Task 9.2
EXHIBIT 2
RATEC2021
GEOSYNTEC CONSULTANTS
2021 RATE SCHEDULE
Rate/Hour
$127
$147
$168
$192
$215
$235
$254
$ 66
$ 70
$ 75
$ 83
$ 92
$100
$115
$124
$164
$134
$120
$105
Staff Professional
Senior Staff Professional
Professional
Project Professional
Senior Pr
ofessional
P
rincipal
Senior Principal
T
echnician I
Technician II
Senior Technician I
S
enior Technician II
Site Manager I
Site Manager II
Construction Manager I
Construction Manager II
Senior De signer
Designer
Senior Drafter/Senior CADD Operator
Drafter/CADD Operator/Artist
Project Administrator
Clerical
Direct Expenses
Subcontract Services
Specialized Computer Applications (per
hour) Personal Automobile (per mile)
Photocopies
(per page)
$ 68
$ 54
C
ost plus 10%
Cost plus 12%
$ 12
Current
Gov’t Rate
$ .08
Rates
are provided on a confidential basis and are client and project specific.
Unless otherwise agreed, rates will be adjusted annually based on a minimum of the Producer Price Index for Engineering Services (PPI).
Rates for field equipment, health and safety equipment, and graphical supplies presented upon request .
Construction management fee presented upon request.
EXHIBIT 2
8-1
8.0 PROPOSAL DOCUMENTS
DWTP GROUNDWATER RECHARGE IMPROVEMENT PROJECT
GEOTECHNICAL INVESTIGATION AND HYDROGEOLOGIC CHARACTERIZATION REPORT
PUR 21-034
SUBMITTAL DUE: THURSDAY, MARCH 10, 2022, AT 2:00 PM
RFP Submittal
Mailing, Delivery Address
and Electronic Mail
Office of the City Clerk
425 North El Dorado Street, First Floor
Stockton, CA, 95202-1997
[email protected] (if applicable)
Proponent Business Name
Proponent Contact Name
Proponent Address
Proponent Phone Number
Proponent Email Address
Department of Industrial
Relations ID Number (if
applicable)
Geosyntec Consultants Inc.
Joseph "Joe" Turner
3043 Gold Canal Drive, Suite 100,
Rancho Cordova, CA 95670
(916) 637-8351
[email protected]
1000016329
EXHIBIT 2
DWTP GROUNDWATER RECHARGE
IMPROVEMENTS PROJECT GEOTECHNICAL
INVESTIGATION AND HYDROGEOLOGIC
CHARACTERIZATION REPORT
RFP PUR 21-034
Prepared By: Prepared For:
EXHIBIT 2
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 2 | Page
a. Executive Summary
Established in 1983 as an employee-owned corporation, Geosyntec has grown to comprise a staff of more than 1,600 engineers, geologists, scientists, other technical professionals, and project support staff located in more than 80 offices throughout the United States (U.S.).
Geosyntec has strong water resource capabilities in the w estern U.S., with over 130 water resource professionals working across varied specialties in recharge assessments, groundwater, surface water, stormwater, and water treatment. We have an internal working group that focuses on how these core components of water resources can combine and interact to help public and private sector clients sustainably manage water over the long-term.
Our project team is composed of experts in sustainable groundwater management from hydrogeology, engineering, and policy perspectives. We are well versed with the various methods to assess groundwater recharge projects for providing cost -effective feasibility, planning, and preliminary design services on individual projects and offer the following advantages:
A responsive team : Joe Turner, PG, CHG, will serve as
the project manager and act as the single point of contact for the project. He is a California Professional Geologist and Certified Hydrogeologist with over 35 years of
experience managing and directing similar projects. Joe will be supported by Amer Hussain, PE, Principal -in-
Charge. Mr. Hussain will ensure that the project has the resources to successfully execute the scope of work.
Periodically, he will check in with the City to ensure that we are meeting your expectations.
Mr. Turner, as project manager, will be responsible for the overall project technical elements, schedule, and budget.
He is supported by qualified leads for each task. Mr. Turner will manage the subcontractors to support services
required to execute this project.
This project will be primarily served out of our Sacramento office to enable frequent face -to-face interaction and the ability to act swiftly to accommodate evolving project
needs.
Expertise: Our proposed team has successfully worked
together on similar projects in Northern California and greater Central Valley area and is committed for the
performance of this project. Our proposed Project
Manager, Joe Turner , PG, CHG , has overseen similar
projects including the assessment, design, pilot testing, permitting, and operation of groundwater infiltration basin at Sacramento County’s Kiefer Landfill, the $1,600,000 Lower Tuscan Aquifer Monitoring, Recharge, and Data
Management Project and the proof -of-concept feasibility assessment for a flood- managed aquifer recharge (Flood - MAR) project for the Sacramento Area Flood Control
Agency.
Our proposed Project Director and Civil Engineer, Amer
Hussain, PE and Technical Advisor Bob Anderson, LHG,
Infiltration basin located at Sacramento County’s
Kiefer Landfill. Geosyntec team members, Joe
Turner, Mike van den Enden, and Craig Riddle
were responsible for the design, pilot testing,
and assistance with permitting with the Water
Board for full -scale operation. Thes e small 2 -
acre basi ns were documented to be able to
handle more than 4 acre -feet per day of
continuous discharge. Site was awarded the
Outstanding Waste Mana gement Award from
the American Society of Civil Engineers
Sacramento Section.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 3 | Page
CWRE, completed a pilot test and feasibility analysis for an aquifer storage and recovery well that has many of the same issues that will be encountered for this project including demonstrating that infiltrated water will not impact nearby supply wells. Amer Hussain, PE supported by Joe Turner, PG, CHG have also recently completed a feasibility assessment of a sixty acre property proposed for use as an infiltration basin in Tulare County. This work included a literature search to assess water quality , potential regional effects from recharge, and completion of soil borings and infiltration testing to assess the suitability of the on-site soils for recharge.
Team members Brandon Steets , PE and Scott Struck , PhD are assisting the California State Water Resources Control Board in the development of statewide standards for dry wells and their use in infiltration projects. These structures may become an important component of the overall design of the recharge basin to allow water to bypass low permeability sediments that are known to occur within the shallow surface.
Partnered with the Department of Energy’s Lawrence Berkley National Laboratory and the United States Bureau of Reclamation and Geological Survey, Brandon and Scott have also developed the use of electrical resistivity tomograph (ERT) sensors for assessing the pathways of recharge through the vadose zone.
Site Knowledge: Arthur Forma, PG, CEG, CHG, EIT and his team have been working for over 10 years on groundwater issues at the nearby Lincoln Center site (more information about this project may be found on page 4). The project has included development of a detailed hydrogeologic conceptual model used to assess aquifer properties, soil permeabilities, fluid migration pathways from the surface to the vadose zone , groundwater quality, and potential effects on nearby supply wells from groundwater extraction wells. They have also designed and installed groundwater extraction wells that provided additional information on the aquifer properties in the area. Joe Turner assis ted with the development and design of future groundwater monitoring networks that were included in the Eastern San Joaquin Groundwater Basin G roundwater Sustainability Plan (GSP) and has also published papers describing the makeup of the geologic formations that exist beneath the DWTP and how to recognize these formations during the drilling of soil borings.
Long-Range Planning : Geosyntec has been assisting clients with a broad range of issues related to groundwater resources and mechanisms for recharge including initial assessments, pilot testing, water market development, funding, permitting, and satisfying requirements of California’s Sustainable Groundwater Management Act (SGMA). From this experience, we are well aware that successful planning during feasibility assessments requires foresight for future portions of the project so that appropriate data and conceptual designs take into account future considerations and portions for the project. For example, our proposed approach for data collection considers the full cycle of the project, including long-term and full- scale operation and maintenance, and analysis for future proposal solicitation packages to obtain grant funds for project construction.
High-Quality Deliverables: Geosyntec is known for providing our clients with the highest quality of service from draft preparation and filing to public meeting support. We understand the need to work closely with the City and stakeholders when finalizing a deliverable and will maintain direct contact with your team to provide accurate, high-quality project deliverables.
Geosyntec is confident that the experience of the team outlined above and in the following pages will provide the City of Stockton with a unique group of individuals that can perform the requested scope of services for a successful assessment of the DWTP proposed recharge basin.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 4 | Page
b. References
Firm Performance References
The Firm Performance References are the same as the Team Performance References provided below.
Team Performance References
South Fork Kings GSA Aquifer Storage and Recovery Pilot Test South Forks Kings Groundwater Sustainability Agency
Kings County, CA
Project Budget: $311,496
Completion Date: March 2022
Name: Charlotte Gallock
Title: Manager of Water Resources,
Kings River Conservation District
Email: [email protected]
Phone: (530) 307-7934
Services Provided:
• Preparation of Work Plan
• Permitting
• Aquifer Testing and Analysis
• Groundwater Recharge and Recovery
• Assessment on effects on Nearby Groundwater Wells
• Modeling
• Water Quality Assessment
Project Description
As part of the Tulare Lake Subbasin’s GSP implementation, Geosyntec conducted an Aquifer Storage and Recovery (ASR) pilot test in an existing active irrigation supply well within the South Fork Kings GSA (SFKGSA). This GSA has poor soils that are not amenable to surface infiltration, and the objective of the test was to evaluate the potential for direct injection as a method for developing groundwater storage using excess surface water when it is available. The test involved comprehensive monitoring of water levels and water quality and was designed to be compatible with typical irrigation operations in the area. Twenty-six million gallons of water was injected into the aquifer, stored for 45 days, and then recovered for irrigation.
Geosyntec’s Scope of Services
Geosyntec was retained by the South Forks Kings GSA to design and complete a pilot test for ASR using an existing active irrigation supply well. The goal of the pilot test was to demonstrate that active irrigation wells could be used for ASR so that SFKGSA could develop an expanded ASR program for the basin.
Geosyntec prepared a work plan for submittal and approval of the pilot test to the Central Valley Regional Water Quality Control Board (CVRWQCB) and Division of Drinking Water and obtained an U nderground Injection Control permit from the United States Environmental Protection Agency. Pre- pilot test work
included identifying nearby supply/domestic wells, water sampling and analysis of groundwater and source water to be used for recharge, performance of aquifer tests to collect aquifer parameters a nd assess interactions within aquifer zones where nearby wells are located, and groundwater modeling analysis to evaluate the influence of injecting, storing, and extracting groundwater. Injection began on June 21, 2021, using water obtained from a nearby canal and continued until August 1, 2021. The injected water was stored for 45 days then recovered for irrigation. An approximate total of 26 million gallons of water was injected into the aquifer at an average injection rate of 800 gallons per minute. Dur ing the pilot test, Geosyntec maintained the system and collected water levels and water quality data from the injection well and nearby observation wells.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 5 | Page
Notable Accomplishments
Geosyntec has provided valuable insight and advocacy for the SFKGSA towards achieving an overall program for ASR within the basin. Geosyntec was able to help the agency identify realistic goals for operation of wells and identified a key maintenance issue to be considered. The system design was critical for the startup of the test to not drag air down the well as it limits the amount of water that can be injected.
Geosyntec is currently assessing changes to the well efficiency of the irrigation well to allow adjustments in the ASR program and design appropriate operation and maint enance procedures for future ASR
operations.
Engineering Evaluation – Proposed Recharge Facility
Crescent Management, LLC
Tulare County, CA
Project Budget: $60,000
Completion Date: March 2022
Name: Allen Nazarian
Title: Realtor and Associate Broker
Email: [email protected]
Phone: (310) 266-9761
Services Provided:
• Preparation of Work Plan
• Literature Search
• Infiltration Testing
• Feasibility Study
• Development of Hydrogeologic Conceptual Model
• Assessment on Regional Effects from Recharge
• Assessment of Site Recharge Potential
• Identification of Data Gaps
Project Objective
In the preliminary assessment, Geosyntec conducted
an engineering evaluation for a potential infiltration
basin of a 60-acre parcel located near the City of Terra Bella in Tulare County. The goal of the project was to
provide Crescent Management a preliminary
assessment of the site as a groundwater recharge
facility prior to purchase of the property. Specific
objectives for the project included estimating the rate of recharge that could occur on the site and the
expected fate of the recharge water and Identifying
data gaps needed to fully assess the recharge
potential of the Site and provide recommendations for
collecting these data.
Geosyntec’s Scope of Services
Geosyntec’s scope for this project included: an initial review of available information including well logs, water level data, water quality data, and groundwater flow directions; drilling of soil borings to assess lithology and allow collec tion of soil samples for physical testing; and completion of downhole infiltration tests (within borehole) at depths anticipated for recharge basin. Physical soil testing included grain size analysis, moisture content, and permeability testing. The downhole infiltration tests were conducted by drilling to desired depth, installing well casing and placing bentonite pellets within the annular space so that water used for test cannot come back up the borehole. The test is conducted by adding water to the well casing and measuring water levels with a pressure transducer. After completion of the field program, Plot showing results of downhole infiltration test used for estimating infiltration rates of proposed basin.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 6 | Page
Geosyntec prepared report discussing the suitability of the property as a recharge basin and provided recommendations for future activities if the property is purchased.
Notable Accomplishments
Geosyntec has provided valuable insight into the potential use of property as a recharged facility. Based on the results of infiltration testing and assessment on the ability of infiltrated water to reach groundwater, it was estimated that a 10-acre basin constructed on property could infiltrate between 30 acre-feet per day to 280 acre-feet per day. Geosyntec also provided insights into future needs for a recharge facility including additional testing needed, permitti ng, and fate of the infiltrated water that the Client is currently using to assess if they will purchase the property.
Lincoln Center Remediation Project
Lincoln Center Remediation Trust
Stockton, CA
Project Budget: $7,738,067
Completion Date: In process
Name: Phil Johnson
Title: President
Email: [email protected]
Phone: (209) 478-9200
Services Provided:
• Groundwater Extraction
• Development of hydrogeologic conceptual model
• Assessment of infiltration through vadose zone
• Regional water quality issues
Project Description
Lincoln Center is a commercial property located in Stockton, California where past operation by three dry cleaners impacted soil and groundwater with PCE on- and off-site and is located about 4 -miles south of the DTWP facility. Joe Niland (Geosyntec Senior Principal) is the Trustee named by the Federal court to oversee the assessment and remediation of the project. Through his oversight, a long-term strategy for the final remedy was develo
ped to bring the site to closure quickly and within the financial limits of the insurance policy. As part of this plan, Geosyntec evaluated existing site data and developed a hydrogeologic conceptual model that assessed : fluid migration pathw ays from the vadose zone to groundwater (infiltration); aquifer properties; groundwater flow paths and directions; groundwater quality ; and data gaps. From this assessment, Geosyntec developed an investigation plan to close the identifie d data gaps, complete the conceptual site model, and support development of the final feasibility study for remediation of the groundwater plume. The investigation included design and installation oversight of the more than a dozen groundwater monitoring, injection, and extraction wells. Following the investigation, Geosyntec tested and designed the final in-situ remediation approach in groundwater, which included pilot testing, Waste Discharge Requirement permitting, injection well system design (similar to ASR wells), and construction oversight. From this project, Geosyntec has gained valuable insights into the characteristics of the vadose zone soils and groundwater system that will be transferable to an assessment of a recharge basin at DTWP site.
Notable Accomplishments
Geosyntec also successfully negotiated permanent shutdown of the soil vapor extraction SVE system and case closure for soil source areas with the CVRWQCB using our detailed knowledge of fluid migration pathways through the vadose zone. Geosyntec currently oversees the op erations and maintenance activities of the groundwater extraction and injection system and has implemented several system optimization cost savings measures. We have implemented a cost effective and expeditious remedy that will meet budget and schedule req uirements of the stakeholders and meet the requirements of the CVRWQCB and the Federal court.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 7 | Page
Argo Infiltration Recharge Basin
City of Los Angeles, Bureau of Engineering and Bureau of Sanitation
Los Angeles, CA
Project Budget: $610,000
Completion Date: June 2021
Name: Bryan Powell
Title: Civil Engineer for Los Angeles
Bureau of Engineering (LABOE)
Email: [email protected]
Phone: (213) 485-5908
Services Provided:
• Performed multi-phase geotechnical investigations
• Conducted hydrological and geotechnical analyses
• Lead Pre-Design Report preparation
• Produced preliminary design civil drawings
Project Objective
The Argo Drain Stormwater Best Management Practice (BMP) project is a regional stormwater BMP that is designed to comply with Santa Monica Bay Beaches Bacteria Total Maximum Daily Load (SMBBB TMDL), the 2012 Los Angeles Municipal Separate Storm Sewer System Permit, and the 2015 Industrial General Permit. The Project is located at the northwest edge of Los Angeles International Airport near the intersections of Westchester Parkway and Falmouth Avenue and will treat runoff from a 2,320 acre drainage area, consisting of commercial, residential, and industrial areas. The project is designed to demonstrate compliance specified for the applicable drainage area. The recommended Project design diverts and conveys stormwater runoff from three existing major storm drain lines to an underground infiltration facility where runoff is infiltrated into the groundwater basin underneath.
The proposed facility includes diversion structures, a pumping station, an 8.9 million gallon underground infiltration gallery, and a network of infiltration dry wells.
G
eosyntec’s Scope of Services
Geosyntec previously completed the draft 100% design in 2008. The project was put on hold following the design completion and was re-initiated in 2015. Design modifications are necessary to meet new regulatory criteria associated with the 2012 MS4 Permit and the 2015 IGP, and to account for an updated methodology for estimating compliance with the SMBB TMDL as outlined in the Santa Monica Bay Watershed J2/3 Enhanced Watershed Management Program ( EWMP). Geosyntec was contracted to acquire necessary subsurface geotechnical information; develop new design criteria based on updated regulatory and geotechnical information; perform hydrologic modeling (using EPA SWMM) and geotechnical analyses to address changes from the previous design; produce preliminary design layouts; and assist project cost estimation and project schedule development.
Notable Accomplishments
Geosyntec worked closely with the City of Los Angeles, Los Angeles World Airports, and other consulting teams to come up with a feasible, cost-effective solution to meet all design criteria within project site constraints, including minimizing interference with airfield operation during construction and operation phases, and integrating with the existing storm drain network. Modeling results indicate that the proposed facility can achieve the required capture efficiency.
c. Financial Statement
Geosyntec Consultants, Inc. has sufficient financial resources to ensure that we can satisfactorily provide the services required. We have provided a balance sheet and income statement in Attachment D which is CONFIDENTIAL.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 8 | Page
d. Project Understanding
The purpose of the project is to evaluate the feasibility, provide planning, and preliminary design services related to developing a feasibility study and preliminary design report for the DWTP Groundwater Recharge Basin Improvements Project. The DWTP is located along Lower Sacramento Road north of 8 -Mile Road between the City of Stockton and the City of Lodi. The geotechnical investigations will establish the subsurface soil characteristics and evaluate if they have the likelihood of supporting a successful groundwater recharge project. The specific area that will be assessed for the project is open land to the east as depicted in the adjacent photo.
During the design phase of the DWTP, the City of S tockton Municipal Utility District (MUD) commissioned the Design-Build team to conduct a preliminary groundwater recharge feasibility study of the approximately 70-acre site adjacent to the DWTP. This draft study, completed in 2009, concluded that with available water from the Woodbridge Irrigation District (WID) and possibly City of Lodi stormwater flows, a direct groundwater recharge and recovery project was feasible and recommended additional engineering feasibility and desi gn
s
tudies to confirm water availability, recharge infiltration rates, and storage capabilities.
Proposed Approach
This section presents Geosyntec’s proposed approach for performing the Geotechnical Investigation and Hydrogeologic Characterization for the DWTP groundwater recharge improvement project. The tasks developed for this approach follow those presented in the RFP and subsequent addendums. The specific scope and approach presented within each task is based on Geosyntec’s experience both in the immediate area and performance of infiltration/recharge investigations throughout California. In addition, our proposed approach for data collection considers the full cycle of the project, including long-term and full-scale operation and maintenance, and future proposal solicitation packages to obtain grant funds for project construction.
We have also designed our proposed scope of work to follow a phased approach whereby the results of each task are assessed to determine if subsequent tasks should be revised or if enough information has been collected that indicates that the basin will not be an effective location for recharge. For example, if the results of the geophysical survey indicate that soils beneath the site are all low permeability, the subsequent drilling program may be reduced to confirm this finding, or the project can be discontinued at this stage. This approach will make sure the City does not spend unnecessary funds to complete the overall goal of the project to assess if the DWTP site is suitable for recharge.
Review of existing data for the vicinity of the DWTP Facility is key to developing an initial conceptual site model for the site and guiding the initial phases of the field programs. Geosyntec will develop a GIS geodatabase, conduct a geophysical survey and CPT program with infiltration data , complete soil borings with continuous cores for detailed lithologic analysis, and collect soil, groundwater, and source water samples to assess water quality and potential changes to groundwater quality from potential recharge operations, and conduct an aquifer test to assess aquifer properties . The collection of high- quality data is essential for the success of subsequent modeling to assess groundwater mounding from recharge, groundwater recovery, residence time of water between the recharge basin, dry wells, or injection wells and production wells, potential influence on the local and regional groundwater systems. These data will also provide the information needed for preliminary design layouts, operation and maintenance considerations, and estimate of probable design and construction costs. All the data collected will be uploaded to a common geodatabase to facilitate efficient incorporation into models and future design phases of the project.
Several physical parameters determine the suitability of a potential site for providing groundwater recharge benefits. Some parameters may require significant research to determine suitability or suitable methods. Not all physical parameters are important for every recharge mechanism (e.g. , the requirements for recharge Recharge Basin
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 9 | Page
basins are different than those for in -lieu recharge or dry wells). Important physical parameters include the following:
• Hydraulic conductivity (vertical and horizontal) of the vadose-zone and aquifer • Depth to groundwater and fluctuation of depth to groundwater • Groundwater storage capacity
• Chemical properties of the soil, vadose-zone, and aquifer materials • Chemical properties of the water available for recharge and receiving groundwater.
Each of these parameters with respect to the Site will be assessed for this project as discussed for the tasks presented below. In addition to the above parameters, existing and historical land use, and production wells in the vicinity are important for consideration in the evaluation of feasibility and design of recharge.
As discussed in the RFP, the City of Stockton is requesting analysis for a recharge basin using Delta Water as the source water for infiltration. In addition, our investigation will include assessment of other recharge mechanisms such as dry wells, aquifer storage and recovery wells, and combinations of technologies. Our anticipated scope of work for the overall project is based on our initial review of readily available information as discussed in the following sections.
Preliminary Hydrogeologic Conceptual Model
The project site is within the Bear Creek interfan area between the Mokelumne and Calaveras River alluvial fans. The Eastern San Joaquin Groundwater Sustainability Plan ( GSP) reports that the interfan soils generally have well-developed profiles, medium-to-heavy textures, fairly well-compacted subsoils, and local hardpan that overlies silty to silty clay loams. Consequently, the interfan soils generally have low infiltration rates (less than 0.6 inches per hour).
Figure 3-14 from the GSP shows the modified Soil Agricultural Groundwater Banking Index (SAGBI). This index provides a composite evaluation of soil suitability to accommodate groundwater recharge while maintaining healthy soils, crops, and a clean groundwater supply. The SAGBI is based on five major factors that are critical to successful agricultural groundwater banking: deep percolation, root zone residence time, topography, chemical limitations, and soil surface condition. However, a limitation of this index is that it only assesses soils within the top 5 to 10 feet. To account for this limitation, the modified SAGBI map (shown below) includes an assumption that all soils with restrictive layers in the upper couple feet are modified by deep tillage. Even with the assumption of deep tillage, the map suggests that soils in the vicinity of the DWTP Figure 3 -14 from GSP showing
SGAGBI mod ified map for Site
area.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 10 | Page
are poor for accommodating groundwater recharge.
Note, however, that the regional map shows soils with
excellent groundwater banking potential not far to the
north of the DWTP location.
As stated in the RFP, infiltration testing conducted at the Site in 2009 concluded that a direct groundwater
recharge and recovery project was feasible with a
preliminary infiltration rate of 0.8 acre -feet per day.
However, the speci fic area and depth of the infiltration tests were not provided in the report describing this
information. Geosyntec has reviewed several boring
logs in the vicinity of the Site. Based on these boring logs a cross-section (adjacent) shows intervals of san d and gravel that are likely present beneath the Site that are conducive for recharge. However, these permeable
zones may be at depths that will require more than deep tillage to access. Accordingly, based on the results of the characterization, Geosyntec will consider engineered
alternatives to a recharge basin such as shallow wells
(“dry wells”) or trenches.
The cross -section also suggests that there may be a
good pathway for recharge water to reach the underlying water table. Based on a hydrograph (below) for a nearby well in the DWR’s Water Data Library, the depth of the
water table beneath the DWTP facility is approximately
60 feet. Based on data presented in the Eastern San
Joaquin GSP and other documents in the area, transmissivity (T) of the underlying aquifer is 4,100 to 5.000 feet
2/day. In wells with T values greater than 1,300 ft 2/day, the production yields are typically sufficient for industrial, municipal, or irrigation use indicating that the underlying aquifer has the capacity to allow storage of recharged water.
Vertical hydraulic conductivity of the soil beneath the recharge basin and of the alluvial sediments in the upper 50 feet are a key constraint on the percolation rates that are feasible for the basin. Consequently, Geosyntec’s proposed scope of work includes a feasibility evaluation of a network of shallow percolation wells (sometimes called “dry wells”) or system of trenches to enhance the recharge rate at the DWTP facility.
Geosyntec staff are experts in the design of dry wells and are w orking with the California State Water Resources Control Board to develop the permit requirements for these types of recharge facilities.
Stratigraphic cross section constructed using well logs near Site.
Hydrograph for well complete d near
Site as shown on DWR’s Water Data
Library.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 11 | Page
Although additional assessments are required, a cursory review of California’s GeoTracker database suggests the g roundwater beneath the Site has not been impacted with volatile organic compounds or pesticides, but there might be some elevated nitrate concentrations in the area. Water quality data obtained from DWR’s Water Data Library for wells near the Site with reported depths less than 200 feet BGS indicate that water quality beneath the Site is of good quality with the average total dissolved solids (TDS) values below 500 milligrams per liter. These data also indicate a calcium-bicarbonate to sodium-bicarbonate water type for the upper aquifer . Calcium-bicarbonate is typical of shallow fresh groundwaters, and sodium- bicarbonate is typical of groundwater influenced by ion exchange processes. This type of data assessment will be critical for assessing how recharge water may interact with the underlying groundwater.
Task 1 – Project Management and Review of Groundwater Subbasin Data Project Management
Geosyntec’s project manager, Joe Turner , PG, CHG, will develop an internal project management plan (PMP) as a guide t o monitor project performance. The plan will document critical success factors, a work breakdown structure (WBS), milestones, key deliverable dates, task budgets, and a project schedule. Joe has managed several recharge assessments including the assessment and construction of recharge basin at the Kiefer Landfill in Sacramento and the $1.6M Lower Tuscan Aquifer Monitoring, Recharge, and Data Management Project. He was also the Senior Principal Hydrogeologist for the ASR project conducted for the South Fork Ki ngs Groundwater Sustainability Agency. The approach described below is based on the successful administration of these projects.
Cost Management
Budget procedures, reports , and the baseline budget will be included in the project budget management section of the PMP. Geosyntec’s Project Manager Dashboard provides a detailed view of project financials and helps monitor and control the project by providing near real-time project data. The system will also help Joe confirm invoice accuracy. Each invoice will sh ow how the budget is managed month- to-month and will be structured to match the tasks presented in the approved agreement.
Managing Risks
Geosyntec will coordinate with the City project team to identify risks and develop mitigation measures to better control the outcome of the project. This assessment will be a guide to help the project team to detect and mitigate risks.
Quality Assurance/Quality Control (QA/QC)
Geosyntec has established QA/QC procedures that require review of calculations and deliverables by senior professionals. The PMP will include a Quality Management Plan (QMP) which will provide a road map for meeting your quality expectations. By integrating planning and tracking tools with major project requirements, ongoing interaction and guidance by company experts will facilitate program delivery that is on time, within budget, and at a level of quality that meets the City’s expectations.
Joe Turner will work closely with the City for the duration of the project and resolve potential changes in scope. Any suggested or requested changes to the scope of work derived through meetings or other communications with our team will be communicated promptly to the City. Joe will also work with the team and expeditiously discuss and propose potential additional tasks that would add value to the project.
Status Reports
Geosyntec will provide the City with written progress reports as part of the monthly invoicing to communicate progress, issues, changes, and deliverable status. In addition, Geosyntec will a lso maintain open and frequent communication with the City. This approach will provide an efficient use of resources for successful project execution and will help the City to inform other stakeholders on the progress of the project.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 12 | Page
Data Review and Compilation
Geosyntec will conduct a literature search and file
review to compile information on hydrogeology in the
vicinity of the DWTP including aquifer characteristics, existing production well and groundwater monitoring
locations, groundwater elevations , g roundwater flow
directions, and groundwater quality. Geosyntec will use this information to plan the geotechnical and
hydrogeologic approach and site groundwater
recharge and rec overy evaluation. As discussed on
page 6 of this proposal, Geosyntec team member s
have worked extensively at the nearby Lincoln Center
facility (4-miles south of DWTP) and have developed
detailed conceptual and geologic site models that will
be instrumental in developing the initial conceptual site model for the study area. Other information that will be assessed includes, the following:
• Eastern San Joaquin County Groundwater
Authority GSP (2019)
• Department of Water Resources California Statewide Groundwater Elevation Monitoring (CASGEM) Program
• SGMA Data Viewer
• DWR’s Water Data Library
• California State Water Resources Control Board GeoTracker database • California Department of Toxic Substances Envirostor database • USGS Groundwater Ambient and Monitoring and Assessment (GAMA) Program • Eastern San Joaquin Data Management System
• SAGBI Data for the Site Vicinity
• California Natural Resource Agency (CNRA) Well Completion Report Map Application In addition to the Lincoln Center Facility, known facilities that have public records on Geotracker and Envirostor within the study area include the ass ociated facilities with the Lodi Plume and several leaking underground fuel sites. Many of the publically available files for these sites could have information regarding soil and aquifer properties that can be used for the assessment of the hydrogeologic properties of the general vicinity of the DWTP Facility.
Geosyntec will document the results of the literature search and review in a Technical Memorandum (TM) that will include the initial conceptual site model and focus on assessing how a groundwater rec harge and recovery operation may affect local groundwater conditions and production wells in the vicinity of the DWTP facility. The TM will also identify data gaps needed for assessment of the recharge potential of the Site.
These identified data gaps will form the basis of the Work Plan for Tasks 4 and 5.
Deliverables
1. TM summarizing results of Literature Search
2. Two meetings to discuss project and results
Cross Section from Lincoln Center showing fluid migration to groundwater surface.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 13 | Page
Task 2 - GIS-based Survey, Utilities Evaluation and Site Assessments GIS-Based Survey
This task will include development of a Geographic
Information Systems (GIS) formatted topographic
survey over the recharge basin area as outlined
below. As specified in the RFP, a topographic survey
will be conducted by a California licensed Land
Surveyor. This survey will be conducted by AAX
Engineering, LLP (AAX) to support the recharge
basin design and subsurface investigation discussed
for Tasks 3 through 7.
Utilities
AAX will conduct a utility survey of the proposed
recharge basin area using geophysical methods on
the surface. USA and geophysical markings w ill be
collected by field survey, and sewer and drainage
manhole depths measured within the proposed
recharge basin area. Identified utilities from the as - built drawings and utility survey will be included in the geodatabase. Conclusions of likely utility loc ations
and project impacts will be identified and coordinated with the City and applicable utility owners. If warranted, pothole locations and relocation efforts will be proposed. No subsurface investigations or utility relocation efforts are currently anticipated but can be provided if deemed necessary.
Survey
AAX will conduct the survey which includes:
• Survey points around the perimeter of the recharge basin at a spacing of approximately 25 -feet including the edge of road improvements,
• Survey points internal to the recharge basin on a grid spaced at approximately 200-feet, • V isible permanent structures, utility appurtenances and markings placed by USA and Utility locator within the recharge basin area,
• Identify gravity sewer and drainage manholes with pipe lines crossing the work area wil l b e s
urveyed and dipped,
• S urvey points will be imported into Autodesk Civil3D and illustrated with applicable linework, • City GIS data, as-builts and other utility records collected by Geosyntec will be added to drawing, • Exi sting surface will be modeled, and contours generated in Autodesk Civil3D, • Aerial imagery included with Autodesk Civil3D will be overlaid, • All drawing and model data will be output to a shape file or other city approved GIS format for further use by others.
Site Assessments
Geosyntec will research history for any prior site assessments to evaluate any prior site uses including agrichemical use that may impact the geotechnical work or Site suitability for use for a recharge facility.
Potential reports would include geotechnical and soils reports completed for construction of the DWTP and environmental assessments completed for purchase of the property.
The results of Task 2 will be summarized in a TM that will include a copy of the topographic map, utilit y locations, and other geographic information. Relevant data from Task 1 will also be added to and georeferenced (where applicable) in the file geodatabase. This TM will also update data gaps discussed in Figure showing approximate locations of water lines near proposed recharge basin area (Source: RFP).
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 14 | Page
the TM for Task 1 for an assessment of the recharge
potential of the Site. As indicated for Task 1, these
identified data gaps will form the basis of the Work
Plan described for Tasks 4 and 5.
Deliverables
1. Topographic Survey in feature class format
within a file geodatabase using NAD83 State
P
lane, California Zone 3 (feet)
2. Project specific geodatabase
3. TM summarizing results of utility locations
and historical land use
Task 3: Surface Geophysical Survey
Electrical resistivity profiling (ERP) measures subsurface electrical properties related to lithologic and chemical variations of the pore water. For example, fine grained silts and clays typically have lower electrical resistivities than coarser grained sands and gravel. The apparent resistivity of subsurface material is determined by transmitting electrical current into the ground through electrodes placed along a traverse and measuring the resulting voltage. The adjacent figure shows a typical profile from Turner et al (2014) for the Kiefer landfill located in Sacramento showing differences between low permeability silts and clays (blue) and coarse-grained sands and gravel (red). As seen on these figures sands and gravels form channel -like features (red) that control the migration of fluids. This information was critical in designing the infiltration basins for discharge of treated water completed by Geosyntec team members Joe Turner, Mike van den Enden, and Craig Riddle. Joe Turner, PG, CHG has completed several similar studies in northern California including assisting in the interpretation of air borne electromatic method (AEM) surveys in Butte County to assess recharge pathways and has been a speaker at two symposiums discussing the interpretation of geophysical surveys for development of hydrogeologic conceptual models for use in assessing groundwater migration pathways.
For this task, the City has requested an ERP survey using an Advanced Geosciences Inc. (AGI) SuperSting RB Resistivity/IP Earth Resistivity meter. NORCAL Geophysical Consultant s, Inc. ( NORCAL) of Cotati , California will conduct the ERP survey. NORCAL conducted the ERP survey discussed above for the Kiefer landfill and has worked with Joe Turner on several other similar projects. As specified in the RFP , data for the survey will be acquired along each transect using the dipole- dipole and s trong gradient array configuration with up to 56- electrodes. Measurements will be made at transmitter -receiver separations (n- spacings) of at least 1 through 8 using an electrode
separation (a-spacing) of 30 feet. This spacing results in a depth of detecti on of approximately 400- to 450-
feet and a length of about 1,540 feet that extends
across the entire length in the north to south direction of the proposed basin. After the initial acquisition
along the 56 -electrode array is completed, data are
acquired by rolling along each line in 14 - to 28 -
electrode increments until the total distance of each
line is reached. Data post -processing and numerical
modeling are accomplished using Earthlmager 2D to
generate 2 -dimensional (x -z) gee -electric cross-
sections of electrical resistivity along each survey line.
The survey conducted will consist of 4 transects
across the proposed recharge basin as shown in
above figure.
Example of geophysi cal survey from Turner et al (2 014) for Site located in Sacramento, California
Red lines show anticipated locations of ERP lines.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 15 | Page
Prior to issuance of Addendum 3, we had included this task as part of Task 6 (now Task 7), Geotechnical Investigation, but recommended an electrode separation (a-spacing) of 15 feet as opposed to 30 feet. This spacing provides a depth of detection of approximately 200 feet as opposed to 400 feet b ut with better resolution on the shallower material. As dis cussed in the preliminary hydrogeologic model above, groundwater at the DWTP facility is approximately 60 feet below ground surface (bgs) and the upper aquifer is within the first 150 feet bgs. Based on these depths, we recommend changing the spacing to 15 feet. This change will provide better information of the shallower material and insights into infiltration pathways for recharge pathways. In addition, this higher resolution for the shallower material will allow better recommendations for locations and depths for subsequent tasks conducted in Task 7.
Deliverable:
1. Geophysical survey analysis report, including lithologic and stratigraphic data interpretation Task 4: Preliminary Geotechnical Investigation Approach and Planning Activities After City approval of the TMs prepared for Tasks 1 and 2 and geophysical report for Task 3, Geosyntec will prepare a Draft Work Plan and schedule for the approach to the geotechnical investigation that will characterize subsurface soil conditions beneath the vicinity of t he DWTP facility. The preliminary geotechnical investigation approach and planning activities will be designed to evaluate the suitability of the soil matrix and hydrogeologic properties of the subsurface. As discussed above, the specific scope of work presented in the Draft Work Plan will be based on the information and data gaps identified in the Tasks 1 and 2 TMs and the information from the ERP survey conducted for Task 3. The Draft Work Plan will be based on the Geosyntec team’s experience preparing work plans for similar types of projects.
Based on a preliminary assessment of data presented in the preliminary hydrogeologic model discussed above, Geosyntec anticipates that the Draft Work Plan will include methods and procedures for the following:
CPT borings to provide continuous profiles of
geotechnical properties including Soil Behavior Type
(SBT) indices. In addition, pore-dissipation testing
(PPDT) will be conducted at selected depths to provide
calculations of hydraulic conductivity (K) . The pore-
dissipation test should provide more accurate local
measurements of K that will be used to calibrate the
profile of K values calculated from the SBT data. The
adjacent figure is an example of a profile at a CPT
boring calculated from normalized SBT indices that also includes several K values based on the PPDTs.
Installation of soil borings and monitoring wells.
The Work Plan will include sampling, and logging
procedures, estimated depths, anticipated screen
intervals, and development procedures, for borings
and monitoring wells. The drilling of soil borings will be conducted in two phases. The first phase will be with
sonic drilling method to allow collection of continuous cores for preparation of detailed lithologic logs to
assess fluid migration pathways. The locations of
these soil borings will be based on the results of the
geophysical and CPT surveys discussed above.
Downhole permeability tests will be conducted within
major lithologic units identified during the CPT survey.
This method will confirm hydraulic conductivity
Estimate of hydraulic conductivities by depth from CPT data constructed by Geosyntec for facilit y operate d by the West Basin Municipal Water District in El Segundo, California.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 16 | Page
calculations conducted during the CPT survey and will provide valuable input parameters for hydraulic calculations and groundwater modeling.
U
sing this information in conjunction with the detailed
lithologic logs developed from the s onic core s, the
second phase will include drilling of soil borings for
installation of monitoring wells and a pumping well that will be used for aquifer testing. Alt hough currently not recommended, based on initial results of Tasks 1
through 3, it may be r ecommended to install ERT
sensors. The ERT sensors, placed at various depths,
can be used to observe the progression of the wetting
front as moisture from rain events or pilot tests of
infiltration basins passes through the subsurface and
provide similar i nformation downhole to the ERP
survey discussed in Task 3 . Scott Struck , PhD
successfully used this method to assess infiltration of water through dry wells for the Los Angeles County
Public Works. For this project, Geosyntec was teamed
with the Department of Energy’s Lawrence Berkley
National Laboratory and partnered with the United
States Bureau of Reclamation and Geological Survey.
The project was conducted to better quantify the
benefits of infiltrating stormwater.
Geosyntec anticipates installing multiple screened intervals at monitoring well locations for use as observation wells during subsequent pump tests as discussed below to assess vertical hydraulic conductivities. These wells can also be used for monitoring of mounding of groundwater and groundwater chemistry changes during infiltration pilot tests. At least one soil boring will be converted to a well that can be used as a pumping well for aquifer testing (see discussion of anticipated field program for Task 7).
Sampling of soil, groundwater, and source water. The Work Plan will include procedures and locations for samples of soil, groundwater, and the source water anticipated to be used for recharge. The Work Plan will include sampling frequency, analyte list, and QA/QC procedures. The primary objective of this testing will be to assess interactions between soils, recharge source water, and groundwater. The anticipated analytical program is discussed for Task 7 and includes soil physical properties and, chemical parameters.
After completion of the Draft Work Plan, Geosyntec will schedule a meeting with the City and other stakeholders to present the overall recommended approach. This meeting will provide the City with opportunities to ask questions prior to their review and approval of the recommended approach.
Deliverables
1. Draft Work Plan
Task 5: Final Geotechnical Plan
After review and approval of the Draft Work Plan by the City, Geosyntec will finalize the plan with an updated schedule for conducting the field program discussed for Task 7 and submitt al of hydrogeologic characterization discussed for Task 8.
Deliverables
1. Final Work Plan
Still shot from animation created from ERT data used to assess dry well. Light blue features show water migrating down through the soil column.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 17 | Page
Task 6: Permits
Geosyntec will obtain all necessary permits and regulatory approval for the project. At this time, it is only anticipated that permits from the Coun ty E nvironmental Management Department to drill wells and soil borings will be required for this project.
Deliverables
1. Drilling Permits
Task 7: Geotechnical Investigation
Geosyntec will conduct the geotechnical investigation in accordance with the approved Final Work Plan. Our anticipated scope of work for this task is based on our initial review of readily available information as discussed in the preliminary hydrogeologic conceptual model provided above. As discussed in our project approach, we have designed our field program to follow a phased approach whereby the results of each task are assessed to determine if subsequent tasks should be revised or if enough information has been collected that indicates that the basin will not be an effective location for recharge. For example, for the field program, if the results of the CPT survey and soil boring program indicate that soils beneath the site are not conducive to a recharge pr ogram, it may be recommended that the subsequent program for installation of wells and performance of aquifer test not be conducted, and the project could be discontinued at this stage Proposed Scope of Work
Based on our compilation and review of existing data as discussed above, our anticipated scope of work includes performance of a C PT program, drilling and sampling of t wo soil borings, drilling sampling and installation of one nested (multiple well screens in one soil boring) monitoring well and one well used for aquifer test, performance of aquifer test, and physical and chemical testing of soil, groundwater, and source water samples. Each item is discussed below. The actual scope of work will be as approved by the City in the Final Work Plan. Fieldwork will be under the supervision of a California Professional Geologist and Certified Hydrogeologist.
Field Setup Coordination
This task includes coordinating with subcontractors, obtaining necessary field supplies and preparation of site-specific field safety plan for use by the Geosyntec team, and marking Site for clearance of utilitie s by USA. The task also includes a site visit to discuss the overall project with City personnel and mark locations for the USA utility clearance.
CPT Survey
The CPT borings will provide data on the geotechnical
properties of the subsurface including continuous profiles of SBT indices, and pore-pressure dissipation testing. The anticipated locations are shown on the adjacent figure that includes four CPT points. The actual locations may be
modified based on the results of the geophy sical survey.
This figure also shows the locations of anticipated soil borings at the Site.
For each CPT boring, pore- pressure dissipation tests will be conducted at approximately 6 depths. To assess the
infiltration rates at various depths, v alues of hydraulic conductivity K w ill be calculated from the SBT data to provide detailed trends of stratigraphic variation of K.
However, the pore-dissipation test should provide more accurate local measurements of K that will be used to calibrate the profile of K values calculated from t he SBT data. An example of a profile at a CPT boring Anticipated Locations of CPT and soil borings
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 18 | Page
calculated from normalized SBT indices that also includes several K values based on Pore -Pressure Dissipation Test (PPDT) values was illustrated in discussion for Task 4.
Soil Borings
As shown on the p revious page, two soil borings
are proposed. The actual location of these soil
borings may be modified based on the results of the
geophysical and CPT surveys. The soil borings will
be drilled using the sonic boring method that allows
collection of a continuous core sample. These
cores will be logged by the on- site geologist
proficient in the methods described by ASTM
D2488-84 and reviewed by a California
Professional Geologist and Certified
Hydrogeologist. The boring logs will provid e
detailed lithologic profiles that will be used to
prepare stratigraphic cross -sections. At selected
depths, during the drilling of these soil borings,
down-hole permeability tests will be conducted.
These tests will allow assessment of infiltration rates within the major material types encountered at the Site and will also allow verification of the results provided by the CPT survey. Tests will be conducted by advancing the outer casing of sonic drill stem to the desired depth. A pressure transducer will then be lowered down the drill stem and programmed to record water levels at 10 to 15 second intervals. The drill stem will then be filled with water then allowed to infiltrate into the desired materials. Infiltration rates are then calculated by the slope of the line developed during this process as shown on the adjacent figure produced for a down-hole permeability test conducted at the Terra Bella, California Site.
Well Installation
Geosyntec anticipates that one soil boring will be drilled for installation of a monitoring well cluster (multi-completion) at a location determined based on the results of the above investigations. The well would consist of three 2-inch-diameter casings with 5-foot screened intervals (e.g., 60 to 70 feet BGS, 75 to 85 feet BGS, and 95 to 100 feet BGS).
Based on cost, logistics, and access issues, the monitoring cluster may be constructed in a single boring or in separate borings. Actual screened intervals will be based on results of the geophysical and CPT surveys and soil boring programs discussed above and observations during drilling of these soil borings. The monitoring well will facilitate collection of groundwater samples for water quality testing and will also be used as an observation well for the aquifer test described below. This well can also be used for assessment of mounding during any subsequent pilot tests of infiltration and potential long-term recharge operations.
An additional well will be installed that will be used to conduct the aquifer pumping test. This test well will be located and designed based on the results of the field testing discussed above. The test well will also allow collection of groundwater samples for comparison with samples collected from the individual depth intervals screened by the nested monitoring wells. Fol lowing development of this well , a step-drawdown test will be conducted that will provide preliminary values of T and K and determi nation of pumping rate used for the Nested monitoring well designed and
installed by proposed Project Manager Joe
Turner for the Lower Tu scan Aquifer
Recharge and Monitoring project. Wells
completed to depths of 1,000 feet BGS.
Plot of data for downhole infiltration test used to calculate infiltration rates at Crescent Management proposed infiltration basin near Terra Bells, California
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 19 | Page
constant rate pumping test described below. This
well wi ll be scr eened over the entire i nterval
monitored by the observation well (e.g., 60 to 100)
and is anticipated to be 6-inches in diameter.
Aquifer Test
After completion of development of the observation
wells and pumping well, a constant rate pumping
test will be c onducted. The pumping r ate will be
based on the results of the step test discussed
above. It is anticipated that the constant rate test
will be 8-hours in duration, but a longer test may be
recommended based on results of the step test. To
monitor the test, vented pressure transducers will
be placed in each well within the nested monitored
well (3 total) and the pumping well. Use of vented
pressure transducers eliminates the need for
barometric corrections of the data. The transducers
will be placed in the wells during the step t est
discussed above and allowed to record water levels
at 1-hour intervals to assess regional changes to groundwater levels prior to the constant rate test.
Groundwater, Source Water, and Soil Sampling
Geosyntec anticipates that approximately 6 soil samples will be collected from each of the cored soil borings:
3 samples from the vadose zone and 3 samples from the saturated zone.
The actual sample depths will be based on specific conditions observed while drilling each boring with the objective of obtaining samples of both coarse- and fine-grained horizons.
Each soil sample will be analyzed for:
• Grain-size distribution (sieve analysis)
• Atterberg limits
• Moisture content
• Electrical conductivity
• Metals
• Cations and anions
• Total organic carbon (TOC)
If the resul ts of the literature search discussed for Tasks 1 and 2 indicates potential for environmental impacts, other constituents such as pesticides and volatile organic compounds may be added to the list.
Geosyntec anticipates collection of grab groundwater samples near the total depth of each of the t wo soil borings, two additional grab water samples each will also be collected from relatively permeable depths in three of the CPT points based on observations in the field, and one sample from each screen interval of the nested monitoring well and from the pumping test well collected after development. In addition, we propose to collect and analyze two samples of the potential source water for recharge: one at the beginning of the field investigation program and one at the end.
Conceptual model and schematic of pumping well and observation wells used for aquifer testing during the Lower Tuscan Aquifer project. From Turner et al, 2013.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 20 | Page
Each groundwater and source water sample will be analyzed for the following:
Analysis Specific Compounds
Cations Cations Calcium, iron, magnesium, manganese, sodium, potassium Anions Chloride, alkalinity, nitrate/nitrite, phosphate, sulfate/sulfide General Parameters THM Potential, TOC, Total dissolved solids, total suspended solids, hardness, pH, electrical conductivity, oxidation/reduction potential, dissolved oxygen Metals Title 22 Metals
E
lectrical conductivity, oxidation/reduction potential, dissolved oxygen, and pH will be collected as field parameters during collection of grab groundwater samples. Additional analytes may be added based on results of Tasks 1 and 2.
Task 8: Hydrogeologic Characterization
The Geosyntec team will characterize the hydrogeology of the vicinity of the DWTP. This assessment will include documentation of our calculations and estimation of:
• Percolation rate and migration pathways
• Specific yield
• Hydraulic conductivity
• Available storage
• Recovery well production rates, and recommended location and number of recovery wells • Groundwater flow directions
• Existing groundwater quality
• Potential chemical interactions between source water, soils, and groundwater.
Geosyntec will develop a thre e-dimensional groundwater flow model as a tool to evaluate the recharge capacity and engineering alternatives to optimize recharge and recovery. The model properties will be based on information from the ESJ Water Resources Model (ESJWRM, Woodard & Curran, 2018, Appendix 2-A, ESJ Groundwater Authority, 2019) with refinements based on site -specific data including lithologic logs of boring, aquifer testing data, and well information in the vicinity. The model grid will be designed with sufficient resolution of hydraulic gradients and groundwater mounding associated with simulated recharge from the basin engineered recharge alternatives such as shallow wells and trenches.
Geosyntec will use the model to evaluate and compare engineering alternatives including:
• a recharge basin,
• a network of percolation wells,
• a network of trenches,
• injection wells, and
• r
ecovery wells.
The model simulations will provide calculations of:
• groundwater mounding,
• flow directions,
• percolation rates from a recharge basin, percolation wells, or trenches, • i
njection rates,
• recovery well production rates,
• travel time of groundwater between the recharge facility and production wells, and • percentage of recycled water pumped by production wells.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 21 | Page
We will also conduct sensitivity analys es of the model results with simulations using a range of assigned hydraulic properties. Geosyntec will document the model design and simulations that will be included as an appendix to the Feasibility Report for Task 9.
Deliverable
1. Model Documentation Report
Task 9 Feasibility Report
After completion of Task 8, Geosyntec will prepare a Groundwater Recharge and Recovery Project Feasibility Report that will include the compiled results of the geotechnical investigation (Task 7) and hydrogeologic characterization (Task 8). This report will provide the following information:
• Suitability to recharge surface-applied water in terms of feet per day over the site and an estimate of the annual quantity of water capable of being recharged to the underlying groundwater basin. • Potential for groundwater recovery in terms of millions of gallons per day or acre-feet per year • Recommendation for monitoring groundwater movement to determine the volume of water recharged and av
ailable for recovery without negatively impacting the groundwater basin and/or nearby private (
or public) wells
• Potential Impacts to groundwater quality related to recharge operations • Preliminary basin layout that considers the existing surface water delivery locations and how water is best distributed and managed across the site
• Environmental clearance requirements
• Permitting requirements
• Operation and maintenance recommendations
• Estimate of probable design and construction cost
The report will also provide recommendations for performance of pilot tests for the preliminary basin outlet, and, if applicable, engineered alternatives including dry wells and trenches that could enhance the performance of recharge. The information provided in the report will be formatted so that it can be used as part of package for obtaining grant funding such as grants for SGMA implementation.
Deliverable
1. Feasibility Report
e. Corporate Structure, Organization
Geosyntec is a consulting and engineering firm that works with private and public sector clients to address new ventures and complex problems involving our environment, natural resources, and civil infrastructure.
Geosyntec serves our clients with 1,700 engineers, scientists, and support personnel in the United States and worldwide. We offer more than 20 in- house technical disciplines and a breadth of resources to apply appropriate expertise and experience to address project needs. This project would be primarily served by staff in our Sacramento office.
History of Geosyntec
Geosyntec was founded in 1983 and since then we have grown based on the application of sustainability principles to projects involving engineering and design for environmental, water resources, civil infrastructure, environmental contamination studies and remediation; natural resources assessment and restoration; and compliance management for air emissions, wastewater discharges, and waste disposal . We are known for our technology leadership, broad experience, and exceptional client service.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 22 | Page
Our public sector clients include departments and agencies of municipal, state/provinc ial, regional, and national governments. Our private sector clients come from a variety of industries including oil and gas, chemical, aerospace, pharmaceutical, diversified manufacturing, advanced technology, power and utility and environmental management. Our private sector clients also include regional and national developers, large commercial property owners, and law firms.
Our Businesses
We deliver solutions through Geosyntec and our seamlessly integrated divisions, SiREM, Savron, and Applied Technology & Management.
Key Personnel
Presented below are the biographies of the key personnel. These staff represent the management and technical leadership that will guide the project from Task 1 through Task 9. The team was assembled so the staff involved in the data review in Task 1, will be involved in the draft work plan in Task 4 , and then carry that knowledge to the final work plan in Task 5 . This will provide the City with a cohesive team that is knowledgeable in all aspects of the project.
All key personnel are experienced project managers capable of implementing a scope of work under a budget and schedule. Following the biographies is a table highlighting the technical resource that will support the key personnel. Full resumes for key staff are provided as Attachment 5.
Joseph “Joe” Turner, PG, CHG
Role: Project Manager ; Task 1 Lead – Project Management and Review of Groundwater Subbasin Data; Task 3 Lead – Surface Geophysical Survey; Task 8 Lead – Hydrogeologic Characterization
Education: MS, Geological Sciences; BS, Marine Geology
Professional Registration: Professional Geologist, CA No. 5125; Certified Hydrologist, CA No. 454
Summary: Joe has more than 33 years of experience providing hydrogeologic services from California. His experience includes design and installation of pilot and full-scale infiltration basins, feasibility assessment of flood-managed aquifer recharge (Flood-MAR) using infiltration basins and/or dry wells, and assessment of aquifer storage and recovery wells. Joe has also designed and performed large-scale investigations to assess recharge mechanisms using infiltration testing, geophysical methods, aquifer testing, isotopic analysis, and surface water/groundwater interaction assessments using stream gauging and temperature profiling. He is also the geologist of record for preparation of Groundwater Sust ainability Plans (GSPs) in compliance with Sustainable Groundwater Management Act for the Sutter, Vina, and Wyandotte Creek Subbasins located in Northern California that require assessment of recharge mechanisms for the basins.
Joe has published papers describing methods to assess aquifer characteristics, aquifer interactions, recharge mechanisms, and development of criteria to recognize geologic formation boundaries during drilling including the primary geologic formations that occur at the DWTP site.
Role: Task 2 Lead – GIS-Based Survey, Utilities Evaluation and Site Assessment Education: BS, Geosciences in Geology
Professional Registration:
Engineer-in-Training, CA No. 119478; Registered Professional Geologist, CA No. 8133; Certified Engineering Geologist, CA No. 2443; Certified Hydrogeologist, CA No. 896 Arthur Forma, PG, CEG, CHG, EIT
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 23 | Page
Summary: Arthur Forma has over 23 years of consulting experience including project management, soil and groundwater investigation, implementation of remedial action programs, and assuring compliance with regulatory requirements. He is adept at the development and refinement of hydrogeologic conceptual site models for complex projects. Arthur is experienced in the development and management of monitoring programs for projects in complex hydrostratigraphic terrains. He currently manages Geosyntec’s Aerojet database management contract that includes more than 3,000 monitoring wells separated into 17 programs across an approximate 60 square mile site. Reporting tasks include performance evaluation reports for the multiple groundwater extraction and treatment systems, compliance monitoring reports, and routine monitoring reports. He also oversees management of the project’s database which includes daily incoming field and analytical data, data validation, and advanced project chemistry support.
Role: Task 4 Lead – Preliminary Geotechnical Investigation Approach Planning Activities; Task 5 Lead – Final Geotechnical Plan; Task 6 Lead – Permits; Task 7 Lead – Geotechnical Investigation
Education: BA, Geology
Professional Registration: Professional Geologist, CA No. 9369 Summary: Craig Riddle is a professional hydrogeologist and projec t manager with a specialized focus in hydrogeologic and environmental work throughout California. He provides expertise in hydrogeologic evaluations, water supply planning and assessments, pre-constru ction permitting (local and State), and conducts well pumping tests, well rehabilitation, aquifer analysis, surface water and groundwater sampling, and water quality investigations. Typical responsible geologic work includes evaluation and interpretation of geologic, hydrogeologic and geophysical data for technical reports, interpretation of subsurface lithology and groundwater parameters, evaluation of groundwater flow and chemistry trends, aquifer analysis and construction groundwater extraction/dewatering analysis. Mr. Riddle is an experienced project and tas k manager including project planning and scheduling, procurement/ delivery management, engineering and subcontractor schedule management, construction coordination, cost control, quality control, change order review and negotiation/administration, and safety management.
Role: Principal-in-Charge; Task 9 Lead – Feasibility Report Education: MS, Civil Engineering; BS, Civil Engineering Professional Registration: Professional Engineer, CA No. 57343 Summary: Amer Hussain, PE has more than 25 years of experience, primarily in the southern Central Valley. He has led a variety of projects focused on water resources development, water quality, groundwater assessment and remediation, regulatory compliance and permitting. As a practicing civil engineer in the Central Valley, he has knowledge of farm activities and irrigation practices. In addition, he has close working relationship with the local water supply providers and regulatory agencies.
Craig Riddle, PG
Amer Hussain, PE
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 24 | Page
Organizational Structure
Geosyntec proposes the organizational structure below.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 25 | Page
Non-Key Personnel
The table below represents the staff that will support the key personnel. Resumes for these staff are provided in Attachment 5.
Name Role
Years
of Exp. Education Brief Biography
David Finney
Task 1 Data Review
Task 3 Geophysical
Task 4 Draft Work
P
lan
Task 5 Geotechnical
Plan
Task 6 Permits
Task 7 Investigation
Task 8 Hydrogeologic
Characterization
5 MS, Geology
BS, Geology
Focus is on sustainable groundwater management
projects and subsurface investigations. Experience
includes Superfund site investigation/remediation,
aquifer storage and recovery, and water quality
investigations. Technical skills include performing
geologic analysis and interpretations, groundwater
plan development, and design and construction of
wells.
Naomi Dailey Task 2 GIS-Based
Survey
4 MA, Geography
BS, Anthropology
GIS specialist with experience in structured query
language (SQL) and database management,
geographic information systems (GIS) analysis, and
implementing automated solutions for data
visualization and processing. Develops tools with
Python and visual basic applications (VBA) for data
quality assurance, designs and manages multiple
databases, and utilizes GIS for spatial data analysis.
Chris Conkle,
PE, GE
Task 4: Draft Wor
k
P lan
Task 9 Feasibility
Rep
ort
18 MS,
G eoengineering
BS, Civil
Engineering
Geotechnical engineer with experience in
geotechnical engineering including management
and execution of design, analysis, quality assurance
monitoring, and geotechnical investigations for a
variety of water resources projects.
Wendy Key,
PG
Task 2 Site
Investigation
15 MS, Geology
BS, Geology
Experience in the management, planning,
implementation, data analysis, and reporting phases
of environmental assessments including ASTM-
compliant Phase I Environmental Site Assessments
(ESAs), subsurface soil, and groundwater
investigations.
Jill Ghelerter,
PhD, PG,
CHMM, PMP
Task 2 Agricultural
Assessment
18 PhD, Chemistry
(Concentration in
Geology)
MS, Geology
BS, Geology
Technical experience in agricultural chemicals and
their impact to soil and groundwater on irrigated
farmland, oil fields, and processing facilities.
Todd Olsen Task 7 Geotechnical
Investigation
10 MS,
Environmental
Engineering
BS, Chemistry
BA, Mathematics
Experience conducting data verification and Stage
2A data validation. This experience includes the
evaluation of organic and inorganic analytical
methods for soil, water, and air sample matrices.
Julie
Chambon,
PhD
Task 8 Hydrogeologic
Characterization
9 PhD,
Environmental
Engineering
MS,
E
nvironmental
Engineering
MS, Engineering
Responsible for managing and supporting multiple
projects that include groundwater flow and transport
modeling, hydrogeological evaluations, well field
design, groundwater monitoring and remediation
performance evaluation.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 26 | Page
Name Role
Years
of Exp. Education Brief Biography
Claire
Wildman, PE
Task 8 Hydrogeologic
Characterization
15 PhD,
Environmental
Science and
Engineering
MS,
Environmental
Science and
Engineering
BS, Civil
Engineering
Applies her background in environmental
engineering, water chemistry, and geochemistry to
remediation and litigation technical support.
Keaton Belli,
PhD
Task 8 Hydrogeologic
Cha
racterization
3 PhD,
B iogeochemistry
BS, Earth and
Atmospheri
c
S
ciences
Specializes in biogeochemistry and
biogeochemistry. Applies his experience in
biogeochemistry, soil and groundwater sampling,
and geochemical modeling to projects involving
organic and inorganic contaminants in diverse
geochemical and geological environments.
Michael van
den Enden,
PG
Task 8 Hydrogeologic
Characterization
16 BS, Geology
Provides site investigation and remediation
services; hazardous materials and hazardous waste
management; asbestos, lead-based paint; PCB
management; and regulatory compliance on
contaminated sites across central and Northern
California.
Brandon
Steets, PE
Task 8 Hydrogeologic
Cha
racterization
22 MS,
E
nvironmental
Engineering
BS,
E
nvironmental
Engineering
Specializes in NPDES and TMDL regulations,
pollutant source investigation, watershed water
quality modelling, and Green Infrastructure design.
He often serves as technical expert on Clean Water
Act litigation. He helped develop new guidance for
state regulators nationwide, for ITRC’s Stormwater
BMP Performance and Harmful Cyanobacteria
Bloom teams.
Scott Struck,
PhD
Task 8 Hydrogeologic
Characterization
19 PhD, Water
Resources
Management
MS, Water
Resources
Engineering and
Management
MPA, Env. Policy
and Natural
Resource Mgmt.
BS, Zoology
BA, Psychology
Water resources experience with a focus on
planning and implementation of stormwater
management practices including green stormwater
infrastructure to meet drainage and NPDES permit
requirements. He is experienced in infrastructure
prioritization, modeling, design, optimization, real-
time controls, monitoring, performance assessment,
economic and triple bottom line cost analyses, and
integrated watershed planning. Dr. Struck serves as
an associate journal editor for the Journal of
Sustainable Water in the Built Environment and is
currently the President of the Environmental and
Water Resources Institute of the American Society
of Civil Engineers.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report 27 | Page
Vendors
Vendor Task Involvement and Service
Gregg Drilling CPT, sonic drilling, well installation, pumping services in Task 7 AAX Engineering LLP Utility Search and Surveying in Task 2 Fruit Growers Laboratory, Inc. Laboratory services in Task 7 NORCAL Geophysical Geophysical survey in Task 3
G
eosyntec has worked with these firms on dozens of projects.
Gregg Drilling
Gregg Drilling, in business since 1985, offers a wide range of drilling and cone penetration testing (CPT) services for environmental and geotechnical site investigation and remediation. Gregg is widely recognized as a leader and innovator in drilling, sampling, and subsurface investigation for industry and government clients.
AAX Engineering LLP (AXXAE)
AAX specializes in supporting public improvement projects through land surveying, civil engineering, and geology. They have a capable team with strong backgrounds in surveying, utility improvements, site development, design, site remediation, geology, flood control, and roadways. This knowledge is coupled with a strong technical pr oficiency in related land surveying, GIS, AutoCAD, Civ il 3D, and SSWMM/XPSWMM modeling software and the other crucial tools of the trade. AAX has a strong professional team including Professional Land Surveyors (PLS with FAA License), Professional Engineers (PE), and Professional Geologists (PG & CEG).
Fruit Growers Lab
Fruit Grow ers Lab is a local laboratory, familiar with Geosyntec’s expectations for data quality and the Requirements for minimum practical quantitation limits to meet RECAP requirements.
NORCAL
NORCAL is a team of Professional Geologists and Geophysicists dedicated to providing a comprehensive range of proven geophysical technologies in support of geologic, groundwater, environmental and engineering investigations. NORCAL provides non-invasive geophysical surveys from the ground surface as well as geophysical logging in boreholes to provide images or models of subsurface conditions. Our geophysical services include carefully defining specific survey objectives, designing a cost -effective approach to meet those objectives, acquiring high quality geophysical data using state -of-the-art instrumentation, analyzing the resulting geophysical data using leading edge computer processing and inversion techniques and providing our interpretation of the results. f. Similar Processes
Geosyntec has experience with similar proces ses as highlighted in the Executive Summary, References, Team References, Resumes and demonstrated in our Project Understanding and Project Approach. g. Additional Data
No additional information is provided.
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report Attachments
Attachment 1-Acknowledgement of Addendum(s)
The A
cknowledgement of the four addenda is provided on the following pages.
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report Attachment 2- Proponent’s Covenant
The executed Proponent’s Covenant is provided on the following page.
EXHIBIT 2
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report Attachment 3 - Non-Collusion Affidavit
The ex
ecuted Non-Collusion Affidavit is provided on the following pages.
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
EXHIBIT 2
Proposal to Provide DWTP Groundwater Recharge Improvements Project Geotechnical Investigation and Hydrogeologic Characterization Report Attachment 5-Resumes
K
ey staff resumes are provided on the following pages.
EXHIBIT 2
Career Summary
Joe has more than 33 years of experience providing hydrogeologic services from the southern end of California in El Centro and San Diego to the northern end in Crescent City and Tulelake. His experience includes design and installation of pilot and full-scale infiltration basins, feasibility assessment of flood-managed aquifer recharge (Flood-MAR) using infiltration basins and/or dry wells, and assessment of aquifer storage and recovery wells. Joe has also designed and performed large- scale investigations to assess recharge mechanisms using infiltration testing, geophysical methods, aquifer testing, isotopic analysis, and surface water/groundwater interaction assessments using stream gauging and temperature profiling. He is also the geologist of record for preparation of Groundwater Sustainability Plans (GSPs) in compliance with Sustainable Groundwater Management Act for the Sutter, Vina, and Wyandotte Creek Subbasins located in Northern California that require assessment of recharge mechanisms for the basins. Joe has published papers describing methods to assess aquifer characteristics, aquifer interactions, recharge mechanisms, and development of criteria to recognize geologic formation boundaries during drilling including the primary geologic formations that occur at the DWTP site.
Relevant Project Experience
On-Call Groundwater Consultation and Infiltration Basin Pilot Test, Sacramento County Waste Management Department
As program manager and principal hydrogeologist, Joe provided consultation to the county on groundwater issues associated with active and inactive landfills. At the active Kiefer Landfill, Joe led the design and implementation for pilot test of an infiltration basin for use in infiltrating treated groundwater back into the groundwater system. The assessment included detailed monitoring of aquifer effects from the infiltrated groundwater using detailed analysis of hydrographs, water quality data, and knowledge of the overall regional hydrogeologic conditions.
The pilot test was successful, and Joe assisted the County in obtaining a permit from the Regional Water Quality Control Board for full-scale operation.
Aq
uifer Storage and Recovery (ASR) Pilot Test, South Fork Kings Groundwater Sustainability Agency
Joe is the senior principal hydrogeologist for this ASR Pilot Test being completed by the recently completed GSP for the Tulare Lake Subbasin. The pilot test consists of injecting surface waters from a nearby canal system into existing supply well then extracting the water for use in irrigation practices as a test for ASR within the region. Project included response to comments to project Work Plan from the Regional Water Quality Control Board that included performance of aquifer test to assess potential hydraulic and water quality effects on nearby domestic wells. The Work Plan was approved based on data from the aquifer test and begin in the Summer of 2021 and is currently ongoing. Injection rates for the test range between 600 to 800 gallons per minute. Joe assisted with initial startup of the system to improve efficiencies with the injection that included developing injecting process that did not allow air to enter the well screen.
P
roof of Concept Analysis, Flood-Managed Aquifer Recharge, American River Groundwater Basin, Sacramento Area Flood Control Agency
Joe acted as project manager and senior principal hydrogeologist for this feasibility study to assess if sediments within the Study Area are conducive to Flood-MAR using dry wells and water from adjacent canal system. The primary objective of this analysis was to identify if there are any “fatal flaws” that would result in a Flood- Mar project not working at the anticipated location within the Study Area. Specific objectives of this analysis included: 1) demonstrate that subsurface materials within the Study Area have the potential to allow adequate infiltration in this Flood- MAR project, 2,000 acre-feet of water for a pilot test and 14,000 acre-feet of water for full-scale implementation, to the regional groundwater aquifer systems; 2) demonstrate that dry well technology can successfully infiltrate the anticipated volume of water during this Joseph “Joe” Turner,
PG, CHG
Senior Consultant
34 Years of Experience
2 Years with Geosyntec
P
roject Roles
Project Manager
Task 1 Lead
Task 3 Lead
Task 8 Lead
Specialties
Landfill Title 27 Compliance
G
roundwater Remediation
Well Design and Installation
Environmental Site
Assessment and Closure
Education
MS, Geologic Sciences,
San Diego State University,
San Diego, California, 1986
BS, Marine Geology, San
Diego State University, San
Diego, California, 1983
Registration & Certifications
California Professional
Geologist No. 5125
California Certified
H
ydrogeologist No. 454
EXHIBIT 2
J
oe Turner, PG, CHG
Flood-MAR project; and, 3)demonstrate that a Flood-MAR project within the Study Area consisting of both infiltration and later extraction will not adversely affect known contaminant plumes in the area. The results of these analyses were also used to identify data needs for a Flood-MAR project so that a work plan for the pilot study can be developed.
L
ower Tuscan Aquifer (LTA) Investigation and Stable Isotope Recharge Study, Butte County Department of Water and Resource Conservation (BCDWRC), CA
Joe acted as a project manager and chief hydrogeologist for this 3-year project funded by a DWR-awarded Proposition 50 Grant. Butte County oversaw the project in cooperation with a four-county group comprised of Butte, Tehama, Colusa, and Glenn counties. The project objective was to further the scientific understanding of the LTA system by assessing the recharge areas that included the collection, analysis, and interpretation of the stable isotopes deuterium and oxygen- 18.
Other activities included design and installation of nested monitoring wells and design, performance, and interpretation of aquifer tests conducted using pumping of agricultural wells during normal irrigation practices. Other activities included conducting infiltration testing, assessing groundwater interaction through the installation of monitoring wells, performance of aquifer pumping tests, water quality interactions between surface water and groundwater, and stream aquifer interaction. Joe was the author for development of field sampling plans that included identifying geologic formation boundaries from lithologic samples collected during drilling. Joe helped BCDWRC with coordination and facilitating public outreach programs and meetings with a Technical Steering Committee. The data collected from this projec t were critical in framing the basis for future studies of the aquifer system including the need for additional isotopic studies.
P
reparation of Groundwater Sustainability Plan, Sutter Subbasin, Sutter County, CA As the senior principal hydrogeologist for preparation of the Sutter Subbasin GSP funded by a DWR -awarded Proposition 1 Grant, Joe was responsible for development of the hydrogeologic conceptual model (HCM) and assessment of aquifer interactions and source of salts identified within specific zones of the basin. The assessment included development of detailed hydrographs from numerous nested wells within the basin used to assess aquifer interactions and stresses on the overall basin and water quality data used to assess zones where impacts from natural conditions such as arsenic, iron, and manganese occurred.
C
ompletion of Groundwater Sustainability Plans (GSPs) for the Vina and Wyandotte Creek Subbasins, Butte County Department of Water and Resource Conservation (BCDWRC), CA Joe is the project manager and senior principal hydrogeologist for completion of these GSPs funded by a DWR -awarded Proposition 1 Grant. As part of this project, Joe provided review and comments to development of hydrogeologic conceptual models based on previous work done in the basins, assessment of groundwater monitoring networks, and development of sustainable management criteria, estimates of the sustainable yield, and project management actions and projects in accordance with California’s Sustainable Groundwater Management Act. Joe also assisted in the interpretation of the AEM survey with regards to geologic formations presented as a cross- section for the Vina Subbasin GSP.
As-N
eeded Groundwater Consulting, Sustainable Groundwater Management Act (SGMA), City of San Diego Public Utilities Department, San Diego, CA
Joe was the Program Manager and Senior Principal Hydrogeologist providing groundwater supply evaluations. This was one of the first comprehensive contracts for the statewide SGMA, recently enacted by the state to monitor and manage California’s groundwater resources. Individual projects for this contract are listed below:
• Development of HCM and Assessment of Groundwater Levels, San Pasqual Valley Groundwater Basin Joe was the Project Manager and Senior Principal Geologist for development of hydrogeologic conceptual model (HCM and assessment of groundwater level trends with the groundwater basin. The review was conducted to identify data gaps in the HCM, assess seasonal variations in groundwater trends, assess interactions with surface water a nd
gr
oundwater and effects from agricultural pumping, interactions between basin aquifers and underlying bedrock fractured system, provided recommendations for development of data management system consistent w ith SGMA, and review relevance of existing groundwater model of basin for use as part of the SGMA process. • Groundwater Quality Resource Stewardship Assessments, San Pasqual Valley Groundwater Basin Joe was the Project Manager and Senior Principal Hydrogeologist for project designed to develop a tool that can be us
ed to assess existing and future operations within the groundwater basin and provide a roadmap for acceptabl e oper
ations that will improve groundwater quality within the basin. Project Included initial assessment of potential sources identified agricultural water impacts both within and outside the groundwater basin, literature search and pr
eliminary GIS assessment and mapping, development of a site prioritization and ratings table, and development of custom Excel spreadsheet tool for use as management tool to assess future operations within the basin.
EXHIBIT 2
J
oe Turner, PG, CHG
• Installation of Nested Monitoring Wells, Aquifer Testing, Aquifer Recharge Assessment, and Preparation o f M
onitoring Plan, San Pasqual Valley Groundwater Basin
Joe was the Project Manager and Senior Principal Hydrogeologist for project designed to provide data for use in development of Groundwater Sustainability Plan. The project included: design, installation, and development of nested monitoring wells with screens within basin sediments, weathered bedrock, and bedrock; downhole geophysical logging to assess orientation of fractures and which fractures produced water; collection of water quality data including stable isotopes to assess recharge within the basin; design of aquifer testing program using normal operations of agricultural supply wells; and preparation of monitoring plan required by DWR. • Long Range, Reservoir-Basin Conjunctive Use Pre-Feasibility Assessment, El Monte and Moreno Groundwater Subbasins
Joe was the Project Manager and Senior Principal Hydrogeologist for study of long- range planning and conjunctiv e
us
e and system optimization of the San Vicente reservoir, El Capitan reservoir, and the El Monte Valley and Moren o V
alley groundwater subbasins. The study included a variety of groundwater recovery and extraction methods for the pre-feasibility assessment of conjunctive use alternatives between groundwater basins, reservoirs , and conveyance s
ystems using a combination of aquifer recharge and storage (ASR) wells, standard extraction wells, and streamb ed per
colation. The San Diego Simulation Model Version 4 was used to run simulations of the different alternatives.
S
alinas River Valley Groundwater Basin Study, Monterey County Water Resources Agency, C A Joe was the technical manager and chief hydrogeologist for this 5-year project to conduct a comprehensive water resources assessment of Zone 2C of the county's Salinas River Groundwater Basin. This two- part study was developed as part of the Monterey County Board of Supervisors Referral and the litigation settlement agreement between the Salinas Valley Water Coalition and the County of Monterey. The first part included a near -term assessment of the health and status of Zone 2C with regards to potential water supply issues, such as seawater intrusion, should current drought conditions continue. The assessment included developing a hydrogeologic conceptual site model, evaluating groundwater level and gradient changes resulting from historical pumping, developing water balance, and assessing water quality conditions. The results of the first part of the study were provided to Monterey County in a State of the Basin Report. He also reviewed stable isotope data for use in assessing recharge sources and effects of seawater intrusion and assisting with the coordination and facilitation of a technical steering committee and public outreach program.
S
GMA Technical Assistance and Modeling Support, California Department of Water Resourc es (DWR), CA Joe was a senior principal hydrogeologist for this contract and provided DWR with expert technical advice and consultation in service areas related to water budget development and integrated groundwater and surface water modeling. He assisted with the development of technical specifications for siting, design, and installation of groundwater monitoring networks that comply with SGMA. These specifications included initial assessment of the hydrogeologic environment and development of logging criteria of samples collected during drilling, specifically for identifying individual geologic formations. Drilling methods used for these wells involved mud-rotary, air-rotary, and reverse-circulation.
Relevant Publications/Presentations
“Case Study – Analysis of Aquifer Effects During Large Scale Agricultural Pumping”, with Tim Godwin, Paul Gosselin, and Dr. Andrew Kopania, in “Managing Irrigation Systems in Today's Environment”, UCID Water Management Conference, November 2012 Publisher, U.S. Committee on Irrigation and Drainage, pp. 331-355. “Geologic Understanding, Hydrogeologic Conceptual Models, and the GSP: Lessons Learned on How to Avoid Conflicts”.
Groundwater Resource Association of California, Sustainable Groundwater Management Act Symposium: Devel oping Groundwater Sustainability Plans for Success, June 8-10, 2016, Abstracts with Programs. “Groundwater Recharge Feasibility Using Industrial Mine Basins”. CALCIMA 2016 Education Conference, November 6- 9, 2016, Abstracts with Programs.
“Aquifer Studies and Recharge Assessment of the Northern California Lower Tuscan Aquifer System,” with Paul Gosselin, Dr. Andrew Kopania, and Dr. Christina Buck, University of California, Towards Sustainable Groundwater in Agriculture, June 28-30, 2016, Abstracts with Programs.
“Quantifying the Relationship Between Stream Flow and Groundwater Elevations to Assess Stream Depletion and the Effects on Groundwater-Dependent Ecosystems” with Dr. Andrew Kopania and Anthony Wohletz. 26 th Groundwater
Resources Annual Meeting, 2017 Time for Collaboration and Innovation, Toward Sustainable Management of Groundwater for Quality and Supply, October 3-4, 2017, Abstracts with programs.
EXHIBIT 2
Career Summary
Amer has more than 30 years of experience in civil and environmental engineering design. His experience includes preparation of design drawings, technical specifications, and bid documents. He understands the importance of a “buildable” design to minimize costly change orders during construction. Amer has previously been the Engineer of Record for design projects at a landfill site and provided geotechnical engineering services for a Superfund site. His project experience includes proposal development, project budget management, program design, work plan preparation, field supervision, data analysis, project QA/QC, and technical report preparation. He has extensive experience with Phase I Environmental Site Assessments (ESA), Preliminary Endangerment Assessments (PEAs), Phase II investigations, UST removals, groundwater monitoring/vapor extraction well installations, and soil and groundwater remediation system operations.
Relevant Project Experience
South Fork Kings GSA SGMA Support, Kings County, CA
Amer served as the project manager to support the preparation of the Groundwater Sustainability Plan (GSP) for the GSA that included feasibility analysis of proposed projects. Other responsibilities included extensive public outreach to various stakeholder groups. This included actively engaging with members of the public to address their concerns and incorporate solutions into the document.
Aquifer Storage and Recovery (ASR) Pilot Test, South Fork Kings Groundwater Sustainability Agency
Amer is the project manager and senior principal engineer for this ASR Pilot Test being completed by for the Tulare Lake Subbasin. The pilot test consists of injecting surface waters from a nearby canal system into existing supply well then extracting the water for use in irrigation practices as a test for ASR within the region. Prior to conducting the project, Amer prepared a feasibility study for the project that was used to develop a Work Plan that was submitted to the Regional Water Quality Control Board for approval. The Work Plan was approved the ASR pilot test begin in the Summer of 2021. Injection rates for the test range between 600 to 800 gallons per minute.
Engineering (Feasibility) Evaluation, Proposed Recharge Facility, Tulare County, California, Crescent Management, LLC. Amer is the project manager and senior principal engineer for this engineering evaluation (feasibility study) of a 60-acre parcel located near the City of Terra Bella, California. The goal of t he
pr
oject was to provide the client a preliminary feasibility assessment of the site as a groundwater recharge facility prior to purchase of the property. Specific objectives for the project included estimating the rate of recharge that could occur on the site and the expected fate of the recharge water and identifying data gaps needed to fully assess the recharge potential of the Site and provide recommendations for collecting these data.
Completion of Groundwater Sustainability Plans (GSPs) for the Vina and Wyandotte Creek Subbasins, Butte County Department of Water and Resource Conservation (BCDWRC), CA
Amer was the lead engineer for completion of these GSPs funded by a DWR-awarded Proposition 1 Grant. As part of this project, Amer prepared feasibility studies and cost analysis for proposed projects that included assessment of recharge basins throughout Butte County. Other responsibilities included extensive public outreach to various stakeholder groups.
This included actively engaging with members of the public to address their concerns and incorporate solutions into the document.
Confidential Client SGMA Support, Various Counties, CA
Amer served as the project manager representing a private agricultural business with multiple landholdings in various GSAs. He was responsible for coordinating their efforts to understand how different GSPs will impact their operations.
Amer Hussain, PE
Senior Principal
31 Years of Experience
5 Years with Geosyntec
P
roject Roles
Principal-in-Charge
Task 9 Lead
S
pecialties
Water Resources
Evaluation and
Development
Groundwater Investigation
and R
emediation
Civil Engineering
Geotechnical Engineering
Education
MS, Civil Engineering,
California State University
Fresno, 1995
BS, Civil Engineering,
California State University
Fresno, 1989
Registration & Certifications
California Professional
Engineer No. 57343
EXHIBIT 2
A
mer Hussain, PE
V
arious Irrigated Lands Programs, Tulare and Kern Counties, CA Amer served as the project manager for the monitoring and analytical programs for several coalitions. He assisted with the preparation of the updated QAPP documents. In addition, he oversaw the field monitoring crews to ensure quality control.
M
adera Irrigation District Monitoring Program, Madera, CA Amer oversaw the groundwater monitoring program for evaluating groundwater quality in eastern Madera County. The program included sampling and monitoring wells to evaluate potential impacts from dairy operations in the area.
P
rocess Water Reuse, Confidential Oil and Gas Client, Kern County, CA Amer developed a monitoring program to assist the client with permitting the use of oil field process water for agricultural use. He provided oversight on the treatment system design and implementation. He also prepared the Report of Waste Discharge and performed the anti-degradation analysis.
M
onitoring Network Cardoza Recharge Basin, Tulare Irrigation District, Tulare County, CA Amer oversaw the design and construction of a monitoring well network to evaluate recharge in the Dis trict’s boundaries associated with recharge basins. The evaluation was key to the location of future recharge basins.
P
inedale Groundwater Plume, The Vendo Company, Fresno, CA Amer assisted with the development of various plans, including a half-mile forced main pipeline, groundwater capture zone analysis, groundwater data evaluation, and removal action plan implementation.
M
onitoring Network Cardoza Recharge Basin, Tulare Irrigation District, Tulare County, CA Amer assisted the district with the selection and construction of a monitoring well network to evaluate recharge in the district’s boundaries associated with recharge basins.
N
ew Football Stadium, Merced Union School District, Phase I, CA A recent Phase I assessment included the location of the new football stadium for Merced Union School. The site is located adjacent to the existing school within the City of Merced, as such a number of ongoing groundwater investigations were identified and evaluated for potential impacts.
U
ST Assessments and Remediation, City of Merced, CA
Prior to joining Geosyntec, Amer served as the project manager and lead engineer for two UST sites in the City of Merced. The projects included extensive groundwater assessments over multiple blocks and at multiple depths. Several groundwater monitoring wells were installed and monitored to evaluate groundwater quality over time. Two soil vapor extractions systems were designed and installed to address the containment at the source. In addition, an in-situ oxidation system was installed to treat groundwater to cut-off plume migration from potentially impacting a City well.
C
hlorinated Volatile Organic Compounds Assessment and Remediation, DTSC, Delano, Kern County, CA Amer served as the principal lead for the Delano Groundwater Plume Project. DTSC created the project to further investigate and mitigate the sources of PCE contamination released to soil and groundwater from multiple dry cleaners in the downtown Delano area. Geosyntec is the lead consultant, and provides oversight of multiple source evaluations, identification of potentially responsible parties (PRPs), conducts soil vapor, indoor air, and groundwater investigations, develops remediation approaches, and monitoring and reporting soil gas and groundwater. Project work by Geosyntec has included data compilation from previous investigations, CSM development, and data gap identification. Critical data gaps identified included potential for impacts to City of Delano water supply wells, potential exposure from soil vapor to indoor air, and vertical delineation of PCE near the primary source areas. Geosyntec is currently reviewing the performance of an SVE pilot test, finalizing a PRP search, preparing a Removal Action Work Plan (RAW) for two source areas, supporting the California Environmental Quality Act (CEQA) requirements including Public Notification for the selected removal action, collecting pre-design data including the installation of soil vapor wells and, designing SVE systems to remediate PCE source areas. The PRP search will be used by the DTSC’s legal group to pursue responsible parties for participation in the City PCE investigation and cleanup. The RAW will present a source area remedy that will cut off source area releases and will also mitigate vapor intrusion to indoor air. Geosyntec is also supporting the DTSC in its public participation process by responding to a local action group.
EXHIBIT 2
Career Summary
Mr. Anderson has 30 years of professional consulting experience in hydrogeology and geophysics providing technical and project management support to clients in the western U.S. on groundwater resource characterization and management. He has supported public and private clients on a wide variety of surface water and groundwater projects including water supply development, aquifer exploration, water rights, water quality characterization, mining hydrogeology, basin planning, source water protection, and regulatory compliance. Bob is respected by regulators and works well with stakeholder groups addressing issues associated with water resources and water quality management. He is an expert on groundwater-surface water interaction and an accomplished modeler across a variety of modeling platforms.
Relevant Project Experience
Salem Aquifer Storage and Recovery MODFLOW Groundwater Model, City of Salem Oregon
Lead hydrogeologist for modeling of aquifer response to injection of 10 million gallons per day (MGD) of treated drinking water into a confined basalt aquifer.
Y
akima Basin FEFLOW Groundwater Model for Aquifer Storage and Recovery, Yakima Washington
Project director for modeling of 2 MGD capacity injection wells for water supply in a sub-basin with unique geologic structures that control basin-scale groundwater surface water interactions.
S
nohomish County Critical Aquifer Recharge Area Delineation, Everett, Washington
Delineated critical aquifer recharge areas and well head protection areas for Snohomish County.
C
ritical Aquifer Recharge Area Delineation, City of Woodinville Technical lead and project manager for delineation of CARA’s and stakeholder/city council interface.
T
ulare Lake Basin, California
Project director for development of a Groundwater Sustainability Plan (GSP) for the South Fork Kings GSA in the Tulare Lake Basin. Addressing complex agricultural demand issues, surface and groundwater availability, and subsidence.
Developed visualization of groundwater flow and infiltration from the Kings River.
Evaluated aquifer storage and recovery (ASR) as a potential planning action to offset groundwater overdraft.
B
orrego Basin, California
Senior technical advisor and quality assurance manager for development of a Groundwater Sustainability Plan (GSP) for the Basin.
S
alinas Basin, California
Technical review of hydrogeologic conceptual model for the Salinas Basin.
S
anta Ynez Basin, California
Technical support for public outreach components of Groundwater Sustainability Plan.
C
onfidential Client, California
Ongoing SGMA and groundwater development advice to a grower with multiple properties in Kern and Kings County. Conducting site-specific water budgets for selected facilities to assess potential SGMA impacts to operations.
Robert “Bob”
Anderson, LHG,
CWRE
Senior Principal
32 Years of Experience
7 Years with Geosyntec
P
roject Roles
Senior Technical Advisor
Specialties
Aquifer characterization
Water Supply Development
Groundwater modeling
St
ream-Aquifer Interaction
W
ater rights
Mining and geotechnical
Geophysics
Education
MS, Hydrogeology and
G
eophysics, University of
Wisconsin, Milwaukee,
Wisconsin, 1987
BS, Geology, University of
Washington, Seattle,
Washington, 1983
Registration & Certifications
Professional Geologist with
Hydrogeology Specialty
license (LHG), Washingto
n
#636
C
ertified Water Rights
Examiner (CWRE),
Washington, #22
EXHIBIT 2
B
ob Anderson, LHG, CWRE
Confidential Client, California
Ongoing SGMA support for a client with multiple industrial facilities throughout California. Conducting site-specific water budgets for selected facilities to assess potential SGMA impacts to operations.
S
ustainable Groundwater Management Act (SGMA) Support, Los Angeles Basin, California Project director for on-call support to Los Angeles Department of Water and Power related to formation of Groundwater Sustainability Agency (GSA) and development of a Groundwater Sustainability Plan (GSP) for the Santa Monica groundwater basin.
T
anana Basin MODFLOW-USG Integrated Groundwater Flow and Transport Model, Fairbanks, Alaska Lead hydrogeologist and task manager for development of a comprehensive base- wide groundwater flow and transport model at Eielson Air Force Base. The model is constructed in the recently released MODFLOW-USG (Unstructured Grid), which is the first major revision to MODFLOW’s numerical solution, using volume- based finite difference calculations.
T
ulare Lake Basin MODFLOW Groundwater Model, Lemoore, California Part of a multi-consultant team working on various aspects of a groundwater sustainability plan (GSP) required to comply with California’s Sustainable Groundwater Management Act (SGMA). Provided peer review of a regional MODFLOW model in the Tulare Lake Bed area of the San Joaquin Basin and utilized the model for scenario analysis. The multi-layer transient model includes capability for modeling of irrigation delivery, crop water demand, and ground subsidence.
S
pokane River MIKE-SHE Integrated Groundwater-Surface Water Model, Spokane Basin, Washington Project manager for development of a complex, integrated groundwater/surface water model of the Spokane River watershed. The main goal of the model was to support decision making during development of a watershed plan. The model simulates all hydrologic processes within the watershed.
I
ssaquah Valley Aquifer System MODFLOW Integrated Groundwater-Surface Water Model, Issaquah, Washington Lead hydrogeologist for modeling of wellfield withdrawal scenarios and impacts to streamflows in a glaciofluvial hydrogeologic setting. Conducted fieldwork for model calibration that included streambed piezometers and lakebed seepage meters to measure groundwater fluxes.
C
ross Valley Aquifer MODFLOW Groundwater Model and Capture Zone Delineation , Everett Washington Project manager for modeling of capture zones in a wellfield tapping multiple aquifers in a glaciofluvial hydrogeologic setting. Conducted fieldwork for model calibration that included pumping tests and monitoring across different aquifer zones.
S
noqualmie Basin MODFLOW Integrated Groundwater-Surface Water Model, Snoqualmie Basin, Washington Project manager for modeling of potential impacts from developing a 40 MGD wellfield in the upper Snoqualmie Valley.
The multi-aquifer system has a complex geometry, prolific mountain front recharge, and significant interaction with the Snoqualmie River. Conducted fieldwork for model calibration that included geophysical exploration and pumping tests with monitoring across different aquifer zones.
C
ouer d’Alene Lake CE-QUAL-W2 and PHREEQUE Water Quality Model, Couer d’Alene, Idaho Project manager for comprehensive water quality modeling of Couer d’Alene Lake to support relicensing of a hydroelectric project. Water quality issues included total dissolved gas, trace metal inflows from adjacent mining areas, low dissolved oxygen, and temperature. CE-QUAL-W2 was used to simulate primary hydrodynamics processes and PHREQUE was integrated into the analysis to examine release of trace metals during periods of low dissolved oxygen in the hypolimnetic areas of the lake. Various scenarios were analyzed with and without hydroelectric operations.
A
htanum Creek GoldSim model of stream/aquifer interaction and irrigation delivery , Yakima Washington Project manager for flow routing analysis of irrigation delivery and streamflows from a proposed water storage project.
The model was developed to simulate various scenarios of water delivery based on crop types and incorporated year -to- year variations in hydrologic inputs to the proposed reservoir. The model was created using GoldSim, a systems dynamics model capable of incorporating complex uncertainty and feedback loop processes in a time- based simulation environment.
EXHIBIT 2
Career Summary
Dr. Thrupp has forty years of experience providing geological and hydrogeological consulting services to industrial and municipal clients. For numerous projects, he has conducted hydrogeologic evaluations and developed groundwater flow models as tools for assessing water resources and engineering design alternatives, designed wells and hydraulic testing programs, evaluated aquifer-testing and streamflow data, prepared and reviewed technical reports for CEQA projects, and negotiated permit conditions with regulatory agencies.
Applications of his hydrogeologic analyses and groundwater modeling include:
• Groundwater resources and sustainable yield evaluations • Recharge feasibility studies, and design of infiltration basins • Modeling of enhanced recharge and aquifer storage and recovery • Investigation of contaminant migration and design of remediation alternatives • Evaluation of hydraulic connection between surface water and groundwater • Construction dewatering design
• SB610 water supply assessments and technical studies for CEQA projects Relevant Project Experience
Feasibility Study of Recharge of Recycled Water, Newhall County Water District, Castaic, CA
Dr. Thrupp directed the compilation of hydrogeologic information and development of a groundwater model to evaluate feasibility of recharging recycled water in the Santa Clara River alluvial aquifer for augmentation of groundwater supply. The MODFLOW groundwater model served as a tool to estimate infiltration capacity, mounding of the water table, groundwater flow direction and velocity, feasible pumping rates of wells to recover the infiltrated water, and residence time. The analysis determined that the project was of limited benefit due to the small storage capacity and insufficient residence times of groundwater between recharge basins and production wells.
E
valuation of Influence of Recharge Basins on a Plume of VOCs in Groundwater, Chino Basin, General Electric Corporation, Ontario, CA Dr. Thrupp evaluated remedial alternatives and protection of municipal supply wells from two plumes of VOCs and chromium in groundwater in the Chino Basin.
He compiled hydrogeologic and geophysical data, conducted aquifer testing, and developed groundwater flow and transport models incorporating supply wells and infiltration from stormwater detention basins. He designed two 1,000 GPM extraction wells, collected samples bottom of the recharge basins, and recommended rehabilitation of the basins that resulted in a ten-fold increase in percolation rate. He also modeled the influence of increased recharge on the distribution of VOCs in groundwater. He collaborated with the Chino Basin Water Master, IEUA, the City of Ontario, and the Regional Water Quality Control Board to protect and manage groundwater resources in Chino Basin.
G
roundwater Modeling and Design of Injection Wells, Olin Corporation, Morgan Hill, CA Dr. Thrupp developed and used a groundwater model to evaluate the feasibility of remediation alternatives for containment of perchlorate impacts to groundwater. He designed, installed, and tested three injection wells that are used to re-inject treated groundwater into a shallow alluvial aquifer. The injection capacity of wells has continued to exceed project needs for several years.
R
eview of Groundwater Modeling to Evaluate Feasibility of In-Lieu Recharge, San Francisco PUC, San Mateo and San Francisco Counties, CA
Dr. Thrupp reviewed groundwater modeling to evaluate feasibility of in-lieu recharge when excess imported water is available and increased pumping when imported water is scarce. He indicated that the recharge rates assigned to the model were unusually high and that because precipitation mainly replenishes the shallow aquifer, the potential for depletion of the deeper aquifer in which the pumping occurs is a concern.
Gordon Thrupp,
PhD, PG, CHG
Senior Consultant
44 Years of Experience
16 Years with Geosyntec
P
roject Role
Senior Technical Advisor
Specialties
Geology and Hydrogeology
Groundwater Modeling
Water Resources
Assessments
Education
PhD, Earth Sciences,
University of California,
Santa Cruz, 1987
BS, Geology, Stanfor
d
U
niversity, 1980
Registration & Certifications
Registered Geologist,
California, Number 5849,
Arizona, Number 58233
Certified Hydrogeologist,
California, Number 541
EXHIBIT 2
G
ordon Thrupp, PhD, PG, CHG
S
alinas Valley Basin Groundwater Sustainability Plans, Salinas Valley Basin GSA, Monterey County , CA Dr. Thrupp was lead hydrogeologist and project manager for Geosyntec on the Montgomery & Associates consulting team engaged by the Salinas Valley Basin GSA to prepare the GSP for the 180-400 foot subbasin, which is a high priority basin due to saltwater intrusion of the coastal margin aquifers. Gordon compiled, reviewed, and documented information for the hydrogeologic conceptual model, including the subbasin setting, basin boundaries, water balance, geologic structure and stratigraphy, soils, aquifer characteristics, recharge and discharge areas, groundwater and surface water interaction, water quality, and groundwater dependent ecosystems. He also developed groundwater models as tools to evaluate feasibility of engineering measures to help curtail seawater intrusion and achieve sustainable utilization of groundwater resources. This multidisciplinary project involved numerous consultants, stakeholders including landowners and regulatory agencies, and the Monterey County Water Resources Agency.
E
ast Bay Plain Groundwater Sustainability Plan (GSP), East Bay Municipal Utility District (EBMUD), Alameda County, CA
Geosyntec is a key member of the Luhdorff & Scalmanini, Consulting Engineers (LSCE) team engaged by the EBMUD and the City of Hayward to prepare a GSP for the East Bay Plain Sub-Basin. Dr. Thrupp oversaw the development of a groundwater flow model as a tool to assess sustainable yield of groundwater, evaluate feasibility of potential projects to utilize groundwater resources during droughts, and develop monitoring criteria for management of groundwater resources in the East Bay Plain.
B
asin Evaluation and Water Supply Feasibility Study, Soquel Creek Water District, CA Dr. Thrupp evaluated alternatives to enhance water supply for the Soquel Creek Water District. Evaluated alternatives included additional groundwater pumping, enhancement of recharge, a shared County desalinization plant, diversion from Soquel Creek, exchange of water with an adjacent district, and groundwater banking with aquifer storage and recovery (ASR) wells. Subsequently, Dr. Thrupp was on an advisory panel convened by the National Water Research Institute (NWRI) for the District’s PURE Water Soquel Groundwater Replenishment Project.
W
ater Resource Capacity Study, San Luis Obispo County, Nipomo Mesa, CA Dr. Thrupp conducted a groundwater resource capacity evaluation of the Nipomo Mesa area for San Luis Obispo County Departments of Planning and Public Works. The project included reviewing DWR reports, consultant’s reports, and regional groundwater models; compiling hydrogeologic and groundwater monitoring data for the area; variable -density flow modeling with SEAWAT to evaluate seawater intrusion for a range of pumping rates; and making recommendations to San Luis Obispo County that were used to determine appropriate limits on growth rates and development on Nipomo Mesa. Dr. Thrupp presented his findings at public hearings.
M
onitoring Plan Update and Evaluation of Source of Arsenic in Groundwater, Kekaha Landfill, County of Kauai, HI Dr. Thrupp evaluated the source of arsenic in groundwater downgradient of Kekaha Landfill and determined that the landfill was likely not the source of the arsenic, but the reducing conditions associated with the landfill increased the solubility of arsenic that was present in the soil that was (1) naturally occurring is volcanic soils; and (2) associated with to a long history of use of herbicides and pesticides for agricultural operations in the vicinity. Dr. Thrupp also oversaw the preparation of an updated monitoring plan for the landfill and attended regulatory meetings.
EXHIBIT 2
Career Summary
Craig Riddle is a professional hydrogeologist and project manager with 14-years of experience with a focus in hydrogeologic and environmental work throughout California. He provides expertise in hydrogeologic evaluations, water supply planning and assessments, pre-construction permitting (local and State), and conducts well pumping tests, well rehabilitation, aquifer analysis, surface water and groundwater sampling, and water quality investigations. Typical responsible geologic work includes evaluation and interpretation of geologic, hydrogeologic and geophysical data for technical reports, interpretation of subsurface lithology and groundwater parameters, evaluation of groundwater flow and chemistry trends, aquifer analysis, and construction dewatering analysis. Mr. Riddle is an experienced project and task manager including project planning and scheduling, procurement/ delivery management, engineering and subcontractor schedule management, construction coordination, cost control, quality control, change order review and negotiation/administration, and safety management.
Relevant Project Experience
Aquifer Storage and Recovery Pilot Test, South Fork Kings GSA, Kings County, CA
As part of GSP implementation, Mr. Riddle conducted an Aquifer Storage and Recovery (ASR) pilot test in an existing active irrigation supply well within the South Fork Kings GSA. The test involved comprehensive monitoring of water levels and water quality and was designed to be compatible with typical irrigation operations in the area. Over 20 million gallons of water were injected into the aquifer, stored for 45 days, and then recovered for irrigation. Mr. Riddle conducted the aquifer test analysis (AQTESOLV) for transmissivity, hydraulic conductivity, storativity, specific capacity, and well efficiency.
P
roduction Test Well, San Joaquin Delta College, Stockton, CA Mr. Riddle oversaw the field operations/installation of a new test well for San Joaquin Delta College, Manteca Farm Campus. The project included providing specifications in order to secure a qualified C-57 licensed drilling subcontractor.
The scope of the test well included drilling to a depth of 350 feet, evaluating the geophysical log for zone selection, coordinating multiple zone tests of water- bearing zones, coordinating laboratory analyses, and preparing a technical report for use in preliminary design of the new potable water supply well.
R
elief Well Program, City of Sacramento DOU, Sacramento, CA Project manager and technical lead for pressure relief well condition assessments and rehabilitations for multiple projects covering 66 wells since 2017. Oversaw and performed mechanical rehabilitation, pre- and post-rehabilitation video inspection, pumping tests, and analysis of pumping tests and technical report detailing results including recommendations for well performance and maintenance.
P
ump Station Relief Wells, Sacramento Regional County Sanitation District, Sacramento, CA
The Sacramento Regional County Sanitation District constructed a ring levee at their South River Pump Station facility. A total of 32 pressure relief wells were installed to relieve groundwater pore pressure within the levee. Mr. Riddle provided construction oversight to ensure that wells were properly constructed, installed, and developed according to the County’s specifications by working closely with the County’s general contractor and drilling subcontractor and the lead Sacramento County inspector.
Craig Riddle, PG
Project Geologist
14 Years of Experience
1 Year with Geosyntec
P
roject Roles
Task 4, 5, 6, 7 Lead
Task 4 Preliminary Geotech
I
nvestigation Approach
P
lanning Activities
Task 5 Final Geotechnical
Plan
Task 7 Geotechnical
Investigation
Task 8 Hydrogeological
Characterization
Task 9 Feasibility Report
Specialties
Program/Project
Management
Hydrogeology
Groundwater Monitoring &
Assessment
Groundwater Supply Wells
Construction Dewatering
Environmental Site
Assessment
Education
BA (Cum Laude), Geology,
California State University,
Sacramento
Registration & Certifications
California Professional
Geologist No. 9369
OSHA 40-Hour
HAZWOPER Certified
EXHIBIT 2
Cr
aig Riddle, PG
California State Fair and Exposition Water Well # 1A, California Department of General Services, Sacramento, CA Mr. Riddle was the task leader for the design, construction, and testing of a new water supply well for the California State fairgrounds. Mr. Riddle assisted in preparation of contractor specifications, permitting, well design, construction oversight, and the final connection to the water conveyance system.
S
urface and Groundwater Sampling Programs, California Rice Commission, Sacramento Valley, CA The California Rice Commission has a monitoring and reporting program consisting of 3 surface water sampling and 1 groundwater sampling program. Mr. Riddle oversees all aspects of the programs, including the project management, coordination of the field staff, the fieldwork, and the analytical laboratories, and reporting to the regulating agency.
S
acramento Suburban Water District Wells 69 and N20 Condition Assessment, Sacramento, CA Mr. Riddle was the task lead for a well condition assessment and rehabilitation project for two of the Sacramento Suburban Water District’s municipal water supply wells (69 and N20). The project required a pre- inspection pumping test and water quality analysis for microbiologically induced corrosion, video inspection of the well interior, mechanical cleaning, chemical treatment of the wells for manganese and coliform bacteria, post -rehabilitation pumping test, and post- rehabilitation video inspection.
D
ewitt and Santa Ana Test Well, Site Evaluation, and Zone Water Quality Testing, City of Clovis, CA Mr. Riddle was the task lead for the installation of a new test well for the City of Clovis. The project included providing specifications in order to secure a qualified drilling subcontractor. The scope of the test well included drilling to a depth of 620 feet, evaluating the geophysical log for zone testing, coordinating multiple (5) zone tests of water -bearing zones, coordinating laboratory analyses, and preparing a technical report for use in preliminary design of the new munici pal well.
H
ydrogeological Assessment Report, Soper-Wheeler Company, Sonoma County, CA The Soper-Wheeler company owns a ranching and recreational property in Sonoma County, California. Mr. Riddle prepared a Hydrogeological Assessment Report for approximately 2,000 acres of the site in accordance with Sonoma County standards. The report included an assessment of the site hydrogeology, water basin, groundwater supply and aquifer testing, groundwater recharge, and water quality.
P
acific Gas and Electric (PG&E) Gas Line Retirement Bundle, Northern Sacramento Valley, CA Mr. Riddle was the task lead for the hydrogeologic and dewatering evaluation for four PG&E projects (R -1228, R-1216, R- 1233, and R-1247) involving excavations into shallow groundwater for gas transmission line retirements. As task lead coordinated the installation of multiple test wells and conducted aquifer tests to assess hydraulic conductivity and other groundwater parameters in support of proposed excavations at 10 sites. Coordinated the per mitting, fieldwork and regulatory communication in addition to performing analysis and reporting of hydrogeologic data acquired.
D
ewatering Assessment for Hydro-testing, Pacific Gas and Electric (PG&E) L-167, Northern Sacramento Valley, CA PG&E requested construction dewatering assessment and recommendations at select locations in preparation for hydro- testing and related construction of over 26 miles of their L-167 gas line. Mr. Riddle coordinated the installation of multiple test wells and aquifer tests (including pumping tests) to assess hydraulic conductivity and other groundwater parameters in support of proposed excavations at 13 sites. Mr. Riddle coordinated the permitting, fieldwork and regulatory communication in addition to performing analysis (AQTESOLV) and reporting of hydrogeologic data acquired.
S
urface Water Interceptor Project, City of Tacoma, WA
Mr. Riddle was the task lead for the evaluation of hydrogeologic conditions for dewatering considerations. The project involves over 3,400 linear feet of new stormwater conveyance pipeline with outfall to Commencement Bay. Mr. Riddle conducted aquifer testing in shallow groundwater areas to obtain aquifer parameters for use in formulating dewatering recommendations for construction and installation of the pipeline.
H
ydrogeological Assessment Report, Red Fan Winery, Sonoma County, CA Mr. Riddle prepared a Hydrogeological Assessment Report for an approximately 55- acre winery in accordance with Sonoma County standards. The report included an assessment of the well yields, site hydrogeology, groundwater basin, aquifer testing, groundwater recharge, and water quality.
EXHIBIT 2
Career Summary
David Finney is a geologist whose focus is on sustainable groundwater management projects and subsurface investigations. David earned his Master of Science degree from Sacramento State and has worked in Northern California on a number of projects over the past 5 years. His experience includes Superfund site remediation, aquifer storage and recovery, and water quality investigations. Some of his technical skills include performing geologic analysis and interpretations, groundwater plan development, and the design and construction of wells.
Relevant Project Experience
Aquifer Storage and Recovery Monitoring Well Construction, City of Roseville, Roseville, CA
David planned well installations in potentially suitable zones for aquifer storage and recovery systems. Selected optimal drilling sites by developing cross-sections and interpreting geologic data. Performed sample logging and interpretation and oversaw drilling and installation of 8 monitoring wells within the city. Assisted with well design, developed final well schematics, and completed well completion reports. Oversaw well construction and water quality sampling.
G
roundwater Level Monitoring, North American Subbasin GSAs, West Placer and Sutter GSAs, Placer County, CA
David was responsible for conducting groundwater monitoring activities throughout the North American Subbasin to better estimate surface-groundwater connectivity and regional water quality and availability trends. Deployed and maintained an array of transducers and associated data. Assisted in site selection and analysis of various proposed gaging sites to ensure representative monitoring. Collected stream gauge data and analyzed relationships between stream flow, precipitation, and groundwater levels. Analyzed results to determine groundwater recharge and delivered technical reports.
A
erojet Superfund Site Groundwater/Soil Remediation, Aerojet, Rancho Cordova, CA
David designed, planned, permitted, and installed groundwater extraction and monitoring wells for the Aerojet Superfund site. Designed wells to capture the maximum possible extent of contaminant. Performed routine treatment plant operations and maintenance tasks including sampling and system monitoring.
G
roundwater Sustainability Plan, Buena Vista Water Storage District, Kern County, CA
David collected, analyzed, interpreted, and confirmed the accuracy of a decade’s worth of groundwater quality data from multiple sources and for multiple constituents. Assisted in writing narrative portions of GSP, created hydrographs for wells in the GSA, and performed extensive technical editing. Additionally, coordinated administrative elements of the final GSP submission process, including collecting and documenting all baseline information and references, migrating CASGEM data to SGMA, carefully correlating each SGMA article to the pertinent GSP section, and submitting every required element to the online portal.
G
round Water Sustainability Plan, Sacramento Groundwater Authority, Sacramento County, CA
David assisted with development of the groundwater sustainability plan. Notable contributions include the hydrogeologic conceptual model, groundwater conditions, sustainable management criteria, and monitoring networks. Compiled well construction data and groundwater information to develop a conceptual model and associated figures and text. Participated in project review process and contributed to development of the plan’s data management system. Developed and interpreted geologic data to construct detailed hydrostratigraphic cross sections.
David Finney
Professional
5.5 Years of Experience
8 Months with Geosyntec
P
roject Roles
Task 1 Data Review
Task 3 Surface Geophysical
Plan
Task 4 Preliminary
Geotechnical Investigation
A
pproach Planning
A
ctivities
Task 5 Final Geotechnical
Plan
Task 6 Permits
Task 7 Geotechnical
Investigation
Task 8 Hydrogeologic
Characterization
Specialties
Monitoring well installation
Hydrogeology
Groundwater Monitoring &
Assessment
Geostatistics
Environmental Site
Assessment
Education
MS, Geology, Californi
a
S
tate University,
Sacramento
BS, Geology, California
S
tate University, Long
B
each
R
egistration & Certifications
OSHA 40-Hour
HAZWOPER Certified
EXHIBIT 2
Dav
id Finney
North American Subbasin Groundwater Quality Technical Reports, West Placer and Sutter County, CA David assisted in the development of Groundwater Quality reports detailing regional water quality setting and trends.
Performed fieldwork to collected water quality data and performed spatio-temporal analysis on water quality samples using hydrographs, time series analysis, and Mann-Kendall test to detect trends. Used well construction and borehole data to develop cross sections for the final report. Proposed future water quality sampling protocols and helped in the development of standards for future well sites. Additionally, assisted in defining principal aquifers and helped to delineate sources of waters high in total dissolved solids.
C
entral Valley Flood Protection Project Variable Infiltration (VIC) modeling, Department of Water Resources, Sacramento, CA
David calibrated the California Department of Water Resources Central Valley VIC climate mode under various climate scenarios. Developed algorithms for managing model datasets and performed daily protocols to ensure model QA -QC.
Applied statistical methods and automation techniques to meet project goals. Analyzed model results and delivered technical reports to DWR staff.
EXHIBIT 2
Career Summary
Arthur Forma has over 23 years of consulting experience in geologic, hydrogeologic, geotechnical, and hazardous waste investigation and remediat ion projects throughout California. Arthur leads and coordinates projects with the Department of Toxic Substances Control (DTSC), various Regional Water Quality Control Boards (RWQCB), County of Sacramento Environmental Management Department, and other counties and cities throughout California for properties contaminated with petroleum hydrocarbons, chlorinated solvents, polycyclic aromatic hydrocarbons, metals, pesticides, and perchlorate.
Arthur’s primary responsibilities include project management, contaminated soil and groundwater investigation, implementation of remedial action programs, and assuring compliance with regulatory requirements. He is adept at the development and refinement of hydrogeologic conceptual site models for complex projects.
Arthur is experienced in the development and management of monitoring programs for projects in complex hydrostratigraphic terrains. He has experience in due diligence work including conducting numerous Phase I and Phase II environmental site assessments (Phase I/Phase II) for real estate transactions at industrial and commercial facilities, agricultural properties, and residential developments. Arthur has conducted various geologic and hydrogeologic investigations in soil, groundwater and soil vapor media utilizing a variety of subsurface drilling methodology including hollow-stem auger, sonic, direct-push sampling technology, mud rotary, air-rotary casing hammer, cone penetrometer testing, membrane interface probe, and laser-induced fluorescence technology.
Relevant Project Experience
Aerojet Superfund Site, Rancho Cordova, CA
Arthur manages the groundwater monitoring program for the site which includes over 3,000 monitoring wells separated into 17 programs across an approximate 60 square mile area. As part of this effort, various scheduling and tracking tools were developed to assure compliance with the monitoring requirements of the various federal and state orders for the project. Reporting tasks include performance evaluation reports for the multiple groundwater extraction and treatment systems, compliance monitoring reports, and routine monitoring reports. He also oversees management of the project’s database which includes daily incoming field and analytical data, data validation, and advanced project chemistry support.
Geosyntec is continuing to refine the data visualization program that will allow the various stakeholders to have access to new and historic data for the entire project.
L
incoln Center Environmental Remediation Trust (Trust), Stockton, CA Arthur manages the update of the project’s groundwater numerical flow model and conceptual site model. The updates to these models are necessary to set the basis for the upcoming feasibility study for the project’s final remedy. To do this, the 20-year subsurface investigation history was reviewed, compiled, and analyzed to identify characterization data gaps and to perform a depositional sequencing evaluation. Through this work, it was determined that the conceptual site model and subsequently the groundwater flow model required significant revisions.
D
elano Perchloroethylene (PCE) Groundwater Plume, Delano, CA Arthur is the hydrogeologic and conceptual site model (CSM) technical lead for the project. He provides oversight of multiple source evaluations, identifying potentially responsible parties (PRP), conducting soil vapor, indoor air, and groundwater investigations, developing remediation approaches, and monitoring and reporting in a large downtown area in Delano, California. His team compiled data collected from previous investigations, developed a CSM, and identified specific data gaps. Critical data gaps identified included evaluating the potential for impacts to the city of Delano water Arthur Forma, PG,
CEG, CHG, EIT
Senior Principal
23 Years of Experience
10 Years with Geosyntec
P
roject Roles
Task 2 Lead
Specialties
Groundwater Monitoring
P
rograms
Site Investigation and
R
emediation
Hydrogeologic Studies
Education
BS, Geosciences in
G
eology, Math Minor,
California State University,
Chico, California, 2000
Registration & Certifications
California Engineer-in-
Training, No. 119478
California Registered
P
rofessional Geologist, No.
8133
California Certified
E
ngineering Geologist, No.
2443
California Certified
H
ydrogeologist, No. 896
EXHIBIT 2
A
rthur Forma, PG, CEG, CHG, EIT
supply wells, evaluating potential exposure from soil vapor to indoor air, and vertical delineation of PCE near the primary source areas.
V
isalia Dry Cleaner Investigation Project, Visalia, CA
Arthur is the hydrogeologic and CSM technical lead for the project. He is providing technical oversite of an investigation of multiple sources, assisting in identification of PRPs, evaluating the extent of soil vapor, indoor air, and groundwater impacts, and developing the remedy approach in Visalia, California. The goal of this work is to obtain site characterization information, identify areas where the presence of contaminants poses unacceptable risks to human health and the environment, and identify PRPs.
R
ed Bluff PCE Investigation, Red Bluff, CA
Arthur is supporting the DTSC to assess the sources of PCE in the Red Bluff downtown area through high-resolution definition investigative methods to cost-effectively delineate the lateral and vertical extent of soil, soil vapor, and groundwater contamination. These data will then be used to identify target areas in support of groundwater monitoring well placement and future remedial actions.
D
ry Cleaner Remediation, Crestview Shopping Center, Carmichael, CA Arthur has provided hydrogeologic assessment and conceptual site model development for a landowner on a property with a former dry cleaner undergoing remediation. Soil vapor extraction (SVE) has been used to successfully remediate the vadose zone tetrachloroethene (PCE) impacts and has successfully cut off the migration of PCE to groundwater, resulting in declining PCE concentrations in all site monitoring wells. Recently, SVE rebound testing demonstrated that the vadose zone soils have been sufficiently remediated, and the case is expected to be closed within the next year without active remediation of groundwater.
S
ite Assessment and Remediation, Arnold Cleaners, Sacramento, CA Arthur is currently providing hydrogeologic and reporting oversight for the remediation activities at a former dry cleaner site in the Arden Arcade area of Sacramento. He led the site assessment effort and is overseeing the remediation evaluation and its indirect effect on groundwater. Currently, PCE concentrations in groundwater have been decreasing over time and active remediation of groundwater will likely not be required.
D
ry Cleaner Remediation, Southgate Norge Dry Cleaner Site, Sacramento, CA Arthur is currently providing senior hydrogeologic and report oversight for a former dry cleaner undergoing remediation in Sacramento, California. Records show that PCE was released along the sanitary sewer laterals and main and has impacted soil and soil vapor in the area. Arthur is currently responsible for conducting routine groundwater monitoring and reporting activities at the site and for evaluating hydraulic capture of the groundwater extraction system.
W
hite Rock North Dump, Rancho Cordova, CA
Arthur is the project manager for the continued monitoring and reporting for the former landfill located within the Aerojet Superfund site. Monitoring and reporting for the landfill are conducted in accordance with a Central Valley Regional Water Quality Control Board (CVRWQCB) Cleanup and Abatement Order (CAO) while remediation is conducted under the direction of the United States Environmental Protection Agency (USEPA). Monitoring at the landfill consists of sampling over 80 groundwater monitoring wells completed in four hydrostratigraphic units on variable frequencies. An innovative scheduling and tracking program was developed for the project to ensure that the CAO requirements are met for each reporting period.
F
ormer Whittaker Ordnance Facility, Hollister, CA
Arthur manages all investigation and monitoring tasks for a former explosives manufacturing facility. The site is located in a heavily faulted terrain with dipping stratigraphy that dominates groundwater flow and contaminant transport. Recently, Arthur updated the hydrogeologic conceptual site model for the site that will be used in future hydrogeologic and remedial planning activities. Investigation tasks include source area assessment and evaluations to optimize hydraulic containment of contaminants. Monitoring at the site includes incorporation of the project’s 5 remedial action performance monitoring plans and various discharge requirements on over 150 monitoring wells on varying sampling frequencies into semi -annual reports as required by the project’s orders and permits.
EXHIBIT 2
Career Summary
Naomi Dailey has over 4 years of private industry experience with structured query language (SQL) and database management, geographic information systems (GIS) analysis, and implementing automated solutions for data visualization and processing. She develops tools with Python and visual basic applications (VBA) for data quality assurance, designs and manages multiple databases, and utilizes GIS for spatial data analysis. Naomi’s experience includes building stored procedures and queries in SQL server and developing Access tools with VBA to easily retrieve and format data for requests from clients. She has rebuilt existing Access databases to optimize routine workflows and has developed data processing and GIS tools with Python to streamline workflows for several monitoring reports and visualization tasks.
Relevant Project Experience
Aerojet Superfund Site, Rancho Cordova, CA
Naomi is the assistant project manager for the project database and routine groundwater monitoring tasks. She is responsible for routine monitoring reports and data visualization tasks, manipulating databases, writing ad hoc queries in SQL server, and scheduling monthly sample collection. Naomi regularly generates figures and tables for routine reports and non-routine requests, and has streamlined the functionality of existing Access databases used for data processing and validation of laboratory analytical data. She assists with external reporting tools that allow users to interact with data, including tabular data queries, sample scheduling forms, and a project webmap that allows users to view and interact with data associated with project locations. She has automated and improved time-intensive data processing tools with Python and VBA, including data formatting macros and file transformation applications.
C
altrans Aerially Deposited Lead Task Orders, Los Angeles, CA Naomi is responsible for the database design, data manipulation and management, and figure generation of aerially deposited lead task orders for Caltrans in Southern California. She developed an Access database and user form that is easily recycled for each task order, reducing the overall effort in replicating each report. Additionally, Naomi produces final tables and figures with the help of a Python tool built to automate callout table generation in the figures.
B
aldwin Park Operable Unit of the San Gabriel Valley Superfund Sites, Los Angeles County, CA Naomi is the database administrator and GIS practitioner for the Baldwin Park Operable Unit (BPOU) annual performance evaluation reports. She is responsible for data analysis and database management, figure and table development, and Python data processing. Visualization outputs incorporate data from an external web- based database, public entities, water purveyors, and in-house modeled numerical data. Naomi regularly improves existing queries used in the Access data import tool and updates the Python scripts used to generate particle track shapefiles to increase efficiency year over year. She has also led the project’s documentation effort and gathered detailed workflows from team members to increase knowledge redundancy while also managing the data and contour updates for over 100 figures and 15 tables as part of the annual report.
F
ormer Occidental Chemical Corporation Facility, Lathrop, CA Naomi is a primary GIS practitioner for a large-scale groundwater monitoring project where she supports database design, transducer data management and analysis, and routine reporting figures. She also assists with maintaining a project webmap that allows users to view and interact with data associated with project locations.
F
ormer Whittaker Ordnance Facility, Hollister, CA
Naomi supports routine groundwater monitoring and reporting for the Former Whittaker Ordnance facility and assists the lead task manager in routine semi-annual groundwater monitoring reports and table generation, pulling ad hoc queries for the larger project staff as needed.
Geospatial Analysis and Cartographic Design
Naomi Dailey
Scientist
5 Years of Experience
4 Years with Geosyntec
P
roject Roles
Task 2 GIS-Based Survey
Specialties
Data Management and
V
isualization
Geospatial Analysis and
C
artographic Design
Programming and Modeling
Education
MA, Geography, University
of California, Davis, 2016
BA,
Anthropology,
U
niversity of California,
Berkeley, 2014
EXHIBIT 2
Naom
i Dailey
DTSC, Multiple Locations, CA
Naomi is the primary GIS practitioner for multiple California Department of Toxic Substances Control (DTSC) brownfield redevelopment projects located throughout California. Projects include a former lumber mill, oil recycling facilities, a wood treatment facility, a former smelter, and a former metal fabrication facility. She provides routine figure support for annual and semi-annual groundwater monitoring reports, and addresses ad hoc figure needs throughout the year. Naomi developed a Python script and associated database workflow to streamline labeling efforts for soil vapor samples in Delano, California, reducing the projected effort by half.
P
ort of Stockton Site 47, Stockton, CA
Naomi provides GIS support for ad hoc figure reporting and human health screening at Site 47. The site contains numerous contaminants of concern, and her figures allow regulators to visualize analytical concentrations spatially and by depth. She also assists the database administrator in manipulating and querying relevant data.
P
ort of Stockton Groundwater Monitoring, Stockton, CA
Naomi assists with the contaminant management program at the former Rough and Ready Island Naval Base. The site contains numerous sources of chlorinated solvents in soil and groundwater and Naomi is responsible for groundwater data visualization using EVS to identify data gaps for investigations and sampling redundancy, and generating 3D figures for routine reporting efforts. The emerging firefighting foam contaminants, per-and polyfluoroalkyl Substances (PFAS), have also been detected in groundwater and a management plan is currently in progress.
P
edrick Landfill, Davis, CA
Naomi leads an extract, transform, load (ETL) project using historical data from the Pedrick Landfill. Using variegated tabular data from the last 10 years, she designed a melt and transform procedure with Python that homogenizes files for streamlined appending. All data is compiled in a single database under a standard format for easy querying. Naomi also utilizes Python to scrape data tables from PDFs, ultimately saving the client over 80 hours in manual transcription.
Y
erba Buena Island Site 11, San Francisco, CA
Naomi manages the database design and tool development for historical data at the Yerba Buena Site 11 landfill site. She developed scripts with Python and VBA to scrape data from historic PDF reports and append into an Access database.
She is also responsible for digitizing historic maps in GIS and developing new analytical maps to use for upcoming work plans.
U
C Davis Pastured Poultry Farm, University of California, Davis (UC Davis), CA Naomi managed the UC Davis Pastured Poultry Farm, a research and demonstration farm at the university. Her responsibilities included training a student team on epidemiological data collection of Salmonella samples around the farm, and subsequent data processing and analysis. Naomi used open source programs such as R and QGIS to manipulate results and display data in interactive web maps used by local farms. Additionally, she created predictive models of statewide poultry disease using R. Data collected on the research farm was presented at numerous conference and resulted in publications in Poultry Science.
EXHIBIT 2
Career Summary
Wendy is a licensed geologist with over 16 years of experience in variety of environmental projects in both the public and private sectors. She has experience in the management, planning, implementation, data analysis, and reporting phases of environmental assessments including ASTM-compliant Phase I Environmental Site Assessments (ESAs), subsurface soil and groundwater investigations, and Brownfield’s redevelopment projects. Wendy also conducts environmental compliance assessments and audits to assist businesses looking to achieve and maintain compliance with environmental regulations in California and Nevada.
Wendy provides support to companies with regulatory issues/violations and businesses seeking assistance with agency interaction, strategy, and litigation support/risk reduction. Wendy has served as a technical reviewer on large litigation projects and has provided litigation support in a variety of environmental cases. Her management experience includes communicating with clients and client attorneys to meet project goals, coordination with regulatory agencies to meet designated requirements and cleanup goals, and managing field staff and activities. Wendy also has management experience leading California environmental compliance programs and health & safety programs for a Fortune 500 company.
Relevant Project Experience
Multiple Phase Is, Confidential Social Media Client, CA Wendy is a senior reviewer on a national program conducting and overseeing Phase Is at multiple locations in the western US for a large social media company.
Wendy is responsible for the quality and completeness of all products and she coordinates closely with corporate and legal staff to assure timely reporting to support acquisition of each property. For many properties, this responsibility includes early verbal reports and virtual meetings with the project team to facilitate the property acquisition process and timing.
P
hase I Environmental Site Assessments (ESAs) and Limited Environmental Compliance Reviews, Confidential Power Client, AZ, CA, HI, NV, NM Wendy provides technical support and project management services, including the identification of geographically local Geosyntec staff to implement project activities, for corporate transactions. Wendy conducts and provides senior oversight for compliance reviews and Phase I ESAs to evaluate for the potential presence of Recognized Environmental Conditions (RECs) at select distribution, repair, and training facilities in the western United States. The compliance portion of the projects typically includes a review of available hazardous waste manifests, environmental permits, Safety Data Sheets, and plans, such as Hazardous Materials Business Plans (HMBPs), Spill Prevention Control and Countermeasure (SPCC) Plans, and Stormwater Pollution Prevention Plans (SWPPPs).
L
imited Environmental Compliance Review and Environmental Site Assessment, Confidential Client, Milpitas, CA
In support of a potential commercial transaction, Wendy conducted a limited environmental compliance review and Phase I ESA to evaluate the potential presence of RECs at a building materials manufacturing facility and batch plant in Milpitas, California. As part of the limited compliance review, Wendy assessed whether the facility had the appropriate environmental permitting documents, including but not limited to, hazardous materials storage permits, stormwater permits, and air permits. As a result of Wendy’s evaluation, the client has requested Geosyntec complete an Air Permit Applicability Assessment to determine if the facility qualified for air permitting exemptions within the Bay Area Air Quality Management District’s (BAAQMD’s) regulatory jurisdiction.
Wendy Key, PG,
CEM
Senior Geologist
16 Years of Experience
7 Years with Geosyntec
P
roject Roles
Task 2 Site Assessments
Specialties
Environmental Due
D
iligence and Compliance
Site Investigation and
R
edevelopment
Education
MS, Geology, University of
Nevada, Reno, 2009
BS, Geology, California
S
tate University,
Sacramento, 2005
Registration & Certifications
Professional Geologist,
California No. 8915
Licensed Geologist,
Washington No. 3089
Certified Environmental
Manager, Nevada No. 234
5 O
SHA 40-Hour
HAZWOPER,
Environmental Complianc
e
S
ervices, Inc.
EXHIBIT 2
W
endy Key, PG, CEM
Limited Environmental Compliance Review and Environmental Site Assessment, Confidential Client, Fairfield and Rio Vista, CA
In support of a potential commercial transaction, Wendy participated in a limited environmental compliance review and Phase I ESA to evaluate the potential presence of RECs at a transformer oil testing facility located in Fairfield, California and a transformer repair facility located in Rio Vista, California. As part of the limited compliance review, Wendy assisted in the evaluation of whether the facility had the appropriate environmental permitting documents, including but not limited to, hazardous materials storage permits, stormwater permits, and air permits. Wendy also assisted in the evaluation of waste transportation, storage, and accumulation processes associated with these facilities.
P
hase I and Phase II Environmental Site Assessments, Confidential Automotive Retailer, Various locations in N V and WA
Wendy has managed and conducted Phase I and Phase II Environmental Site Assessments (ESAs) association with the acquisition of individual automotive dealerships and larger acquisitions consisting of multiple automotive dealerships in a particular geography. Phase II activities were conducted concurrently with Phase I ESA to evaluate impacts at facilities with known current or historical releases and facilities with features likely to result in a release to the environment, such as underground storage tanks (USTs), oil-water separators, and in-ground hoists.
L
itigation Support, Confidential Client, Portland, OR
As part of a larger team consisting of professionals from five Geosyntec offices, Wendy serves as a technical reviewer to evaluate previous environmental assessments and compliance documentation for numerous potentially responsible parties (PRPs) as part of the allocation process associated with the Portland Harbor Superfund Site. Wendy has reviewed thousands of pages and hundreds of documents to assess the origin of documented impacts in the Swan Island Lagoon and Willamette River. Upon review of these documents, Wendy has drafted supplemental information requests and developed PRP summaries to be submitted to the Allocation Team as part of the disclosure process.
P
hase I Environmental Site Assessments (ESAs), Various Clients, AZ, CA, HI, ID, NV, NM, OR, UT, WA Wendy has completed hundreds of Phase I ESAs, according to ASTM standards (ASTM E 1527- 05 and ASTM E 1527- 13), U.S. Environmental Protection Agency All Appropriate Inquiries Rule, and client -specific standards, for a broad range of clients including private and governmental agencies. In addition to providing technical support for the preparation of Phase I ESAs, Wendy also coordinates with local offices throughout Geosyntec to implement assessment activities and provide a consistent work product. Environmental conditions likely to affect the sites were evaluated. Activities included review of regulatory agency files, historical documents, including aerial photographs and topographic maps, completion of a site reconnaissance, and preparation of a final report.
B
ryte Landfill Waste Characterization, Downey Brand Attorneys, LLP, West Sacramento, CA Wendy currently provides project management and waste characterization support for the Former Bryte Landfill which operated as a burn dump from approximately 1940 through 1974 and possibly as late as 1981. The landfill needs to be removed to facilitate an expansion of the Sacramento Weir and Bypass, portions of the State Plan of Flood Control (SPFC), planned by the Sacramento Area Flood Control Agency (SAFCA) and others, including the California Department of Water Resources (DWR). Wendy assisted in the development of a Data Collection Work Plan designed to evaluate excavation, separation, management, reuse and disposal options for the landfill material. Implementation of the Work Plan was divided into two phases: Phase 1 included the installation of 40 trenches and potholes throughout the Site to evaluate the lateral and vertical extent and character of the waste; and Phase 2 included the excavation and screening of 500 tons of ash/waste material to assess the ratio of ash/soil to solid waste within the former landfill. Results of the investigation indicated that the total volume of ash and waste is present at the landfill was less than previously estimated. The investigation also revealed that while the majority of the ash was found to contain total and soluble lead concentrations that are considered hazardous in California, a limited area of ash contained soluble levels of lead considered hazardous per federal regulations and debris greater than 1-inch was generally inert.
I
nitial Site Assessments, Caltrans, Multiple Locations, CA Wendy has completed numerous Initial Site Assessments to evaluate roadways and adjacent properties for potential environmental conditions prior to planned completion of roadway improvement, addition, and/or widening activities.
Activities included review of regulatory agency files, historical documents, including aerial photographs and topographic maps, a site reconnaissance, and completion of a final report and a Caltrans environmental checklist.
EXHIBIT 2
Career Summary
Dr. Ghelerter has over 18 years of experience in the environmental consulting industry with focus on project management and hydrogeology. She has provided technical direction and oversight with industrial, landfills, irrigated farmland, oil fields, agricultural chemical processing facilities, refineries, and commercial and residential projects. Her current focus area supporting oil producers with various hydrogeology related regulatory compliance. Previous experience has been with environmental assessment, designing monitoring well networks and sampling strategies, developing and implementing remediation plans, designing remediation systems, remediation system optimization, and site closure. She has worked with large and complex groundwater plumes. She has been involved with soil and groundwater monitoring and remediation sites impacted by hydrocarbons, pesticides, chlorinated solvents, and metals. She has also been involved in vapor intrusion sampling and evaluation.
Relevant Project Experience
Orphan Project Program, California Department of Toxic Substances Control (DTSC), Various Sites, CA
Project Manager/PG for investigation, monitoring, reporting, and remediation of chlorinated solvents with a focus on perchloroethylene in soil, soil vapor, indoor air, and groundwater at city-wide plume sites. Included semi-annual groundwater monitoring and reporting, installation of soil vapor probes, collecting indoor air samples, preparing work plans, obtaining permits, oversight of remedial installation, and reviewing routine reports.
G
eorgia Underground Storage Tank Program, Statewide, GA
Program coordinator and geologist for numerous UST sites throughout Georgia.
Dr. Ghelerter provided technical direction and oversight for designing monitoring well networks and sampling strategies, developing and implementing remediation plans, remediation system optimization, and site closure. Tasks included assessment of indoor air, soil, groundwater, water supply wells, and surface water impacted with gasoline and/or diesel fuel including free product. Several groundwater plumes extended over 1-mile. Prepared and reviewed Corrective Action Plans and Monitoring Reports for the Environmental Protection Division.
Designed, installed, and operated remediation systems. Replaced impacted water supply wells and/or connected structures to the municipal water supply. The contract was pay-for-performance requiring remediation goals to be achieved within 2 years.
R
emedial Investigation, Confidential Client, Bakersfield, Kern County, CA Dr. Ghelerter’s work on this project includes preparing a comprehensive remedial investigation report for a former refinery with a 90-year history of operations, numerous hydrocarbon releases, and interim remedial actions. Petroleum constituents and non-aqueous phase liquids are present within various hydrostratigraphic zones. Active and interim remedial actions are on-going. The refinery is currently being converted into a renewable fuel facility.
F
irebaugh Facility, JR Simplot, Firebaugh, CA
Project Manager/PG for investigation, monitoring, and reporting of agricultural chemicals in soil and groundwater at a 20-acre active fertilizer production facility.
Soil and groundwater investigation resulted in monitoring well installation and quarterly groundwater monitoring and reporting of 1,2,3-trichloropropane, 1,2- dichloropropane, and 1,2-dibromo-3-chloropropane and nitrogen. Subsequent on- site and off-site soil assessment resulted in shallow soil impacted with chlorinated pesticides including toxaphene. Assisted client in demonstrating off site detections were not from site activities. Presented different options to client for removing/remediating shallow soil impacted with toxaphene.
Jill Ghelerter, PhD,
PG, CHMM, PMP
Senior Geologist
18 Years of Experience
1 Years with Geosyntec
P
roject Roles
Task 2 Agricultural
Assessment
Specialties
Project Management
Site Investigation
Underground Storage Tank
Programs
Groundwater Assessment
Groundwater Remediation
Regulatory Compliance
E
ducation
PhD, Chemistry with
C
oncentration in Geology,
Georgia State University,
Atlanta, 2014
MS, Geology, Florida
A
tlantic University, Boca
R
aton, 2005
BS, Geology, Florida
At
lantic University, Boca
R
aton, 2002
Registration & Certifications
Professional Geologist
California, No. 9684
Certified Hazardous
Materials Manager (CHMM),
Number 14803
Project Management
Professional, No. 1527604
EXHIBIT 2
J
ill Ghelerter, PhD, PG, CHMM, PMP
Regulatory Compliance, Former Retail Site, JR Simplot, Wasco, CA Project Manager/PG for investigation, remediation, and reporting of agricultural chemicals in soil vapor and groundwater at a 1-acre site. Soil assessments revealed subsurface soil and soil vapor impacts of 1,2,3- trichloropropane, 1,2- dichloropropane, and 1,2-dibromo-3-chloropropane to 250 feet deep. Two soil vapor extraction (SVE) systems were installed and were monitored monthly under an air permit issued by the Air Pollution Control District. Reports were prepared and submitted annually. Media from the SVE system was treated with granular activated carbon. Groundwater was monitored quarterly and was impacted with agricultural chemicals above background levels. Groundwater quarterly reports were submitted to the Regional Water Quality Control Board. Due to extensive pumping in the area, the aquifer beneath the site went from confined to unconfined, creating a natural subsurface vacuum resulting in downward migration of contamination. The SVE system was optimized to counteract this phenomenon. Surface soil was impacted with metals and pesticides; concrete capping was implemented as an interim mitigation measure.
U
nderground Injection Control Permitting and Consulting, Confidential Client, San Joaquin Valley, CA Dr. Ghelerter acts as the liaison between the client and both the RWQCB and the California Geologic Energy Management Division (CalGEM). She is assisting an oil company in obtaining permits for underground injection control of applying an innovative sustainable production technology in California. Duties include compiling permit materials and coordinating with regulators.
O
il Field Land Discharge Compliance and Hydrogeologic Investigation, McLennan Oil Company, Midway-Sunset Oil Field, CA
Dr. Ghelerter conducted hydrogeologic investigation and characterization of the subsurface and prepared a technical report for a small oil operation discharging to unlined wastewater ponds to comply with the RWQCB’s Waste Discharge Requirements. The hydrogeologic investigation included reviewing electric logs to determine the location of subsurface fluids and whether those fluids were hydrocarbon-producing or groundwater, creating cross sections, and evaluating if produced wastewater from the unlined ponds would migrate to underground fluids.
O
il Field Land Discharge Compliance and Hydrogeologic Investigation, Engineers Oil Company, Midway-Sunset Oil Field, CA
Dr. Ghelerter conducted hydrogeologic investigation and characterization of the subsurface and prepared a technical report for a small oil operation discharging to unlined wastewater ponds to comply with the RWQCB’s Waste Discharge Requirements. The hydrogeologic investigation included reviewing electric logs to determine the location of subsurface fluids and whether those fluids were hydrocarbon-producing or groundwater, creating cross sections, and evaluating if produced wastewater from the unlined ponds would migrate to underground fluids.
I
nitial Site Assessments, Caltrans, Multiple Locations, CA Ms. Key has completed numerous Initial Site Assessments to evaluate roadways and adjacent properties for potential environmental conditions prior to the planned completion of roadway improvement, addition, and/or widening activities.
Activities included a review of regulatory agency files, historical documents, including aerial photographs and topographic maps, a site reconnaissance, and completion of a final report and a Caltrans environmental checklist.
Site Investigations and Redevelopment
EXHIBIT 2
Career Summary
Chris is a geotechnical engineer with over 15 years of experience in geotechnical engineering and project management, with over a decade of that experience in engineering consulting. His experience includes management and execution of design, analysis, quality assurance monitoring, and geotechnical investigations for a variety of geotechnical systems including dams and levees. The bulk of his current practice relates to performing and supporting dam safety evaluations and providing related support to dam owners.
Chris recently served as Geosyntec’s principal-in-charge for work related to the ongoing modifications to the Flood Control District of Maricopa County’s Cave Buttes Dam. Chris’s dam safety experience includes serving as the project manager and technical lead for Geosyntec’s Embankment Dam Stability Evaluation and On-Call Dam Safety projects for the Southern California Edison as well as participating in Risk Informed Dam Safety Workshops for other utilities.
Prior to joining Geosyntec, Chris worked in the Water Resources division of the Los Angeles County Flood Control District. This division is trusted with providing for the safety of the Department’s 14 major dams.
Relevant Project Experience
Geotechnical Instrumentation for Cave Buttes Dam Modifications, Flood Control District of Maricopa County, AZ
Chris served as Geosyntec’s principal-in-charge for Geosyntec’s installation of geotechnical instrumentation at the Flood Control District of Maricopa County’s (FCDMC) Cave Buttes Dam as a subcontractor to the project’s general contractor.
Geosyntec’s scope of services in support of this tunneling under the embankment dam included installation, configuration and setup of the automated instrumentation (in-place inclinometers, borehole extensometers, automated motorized total stations, survey prisms) and automated data acquisition systems.
Working collaboratively with the project designer and the FCDMC, Geosyntec implemented the instrumentation system on-time. The tunneling which was the subject of this monitoring was successfully completed in September 2020.
O
n Call Dam Safety Support Services, Southern California Edison, CA Chris is currently serving as project manager for a 5 year long on call dam safety contract providing a variety of dam safety support services to Southern California Edison. Among other items, Chris’s team has performed the following tasks under his direction for dams within California.
• Dam Safety Instrument Assessment: For a large embankment dam site, Geosyntec evaluated the condition and functionality of twenty-nine (29) standpipe-type piezometer installations with vibrating wire transducers, associated electrical components, and an automated datalogging system. This evaluation used standard diagnostic tools to collect system information in combination with a field visit to assess the condition of the system and its components. Geosyntec prepared a letter report summarizing the findings based on a review of available information, onsite measurements, configurations, and observations.
• FERC Part 12D Support: Implementation of significant updates to th e
S
upporting Technical Information Documents (STIDs) for several of Southern C
alifornia Edison’s dams in support of the FERC Part 12D process and annual reviews. These dams include embankment dams, concrete gravity dams and a c
oncrete multiple-arch dam.
• Seismic Evaluations of Gates: Performed structural evaluations of a steel drum gate on a concrete multiple-arch dam. Developed a 3D finite element model of the drum gates and conducted evaluations considering hydrostatic, hydrodynamic and seismic loading.
Chris Conkle, PE,
GE
Principal
18 Years of Experience
14 Years with Geosyntec
P
roject Roles
Task 4 Preliminary
Geotechnical Investigation
A
pproach and Planning
Activities
Task 9 Feasibility Report
Specialties
Geotechnical engineering
Seismic Risk
Water resources
engineering
Low Impact Development
Education
MS, Geoengineering,
University of California,
B
erkeley
BS, Civil Engineering,
University of California,
Berkeley
Registration & Certifications
Registered Professional
Engineer, Geotechnical,
California, No. GE 2926
Registered Professional
Engineer, Civil, California,
No. C 70923
EXHIBIT 2
Chr
is Conkle, PE, GE
• Stability Evaluations for Embankment Dam: Performed geotechnical stability evaluations for an embankment dam retaining a water supply reservoir with a height of over 200 feet which was originally constructed usin g hy
draulic fill. Evaluations included an assessment of liquefaction potential and resulting static and seismic stability using residual strengths.
• Stability Evaluations for a Concrete Gravity Dams: Performed geotechnical and structural stability evaluations for a series of three concrete gravity dams and related earthen embankments retaining a reservoir with a height of over 200 feet which is part of a hydroelectric project. • Evaluation of Wave Overtopping: To address questions raised by reviewers during the PFMA process, Geosyntec evaluated the potential for wave overtopping of a rockfill dam to threaten stability of the downstre am s
lope of the dam.
• Preparation of Field Investigation Works Plans for FERC Review: Geosyntec prepared Field Investigation W
ork Plans to address potential dam safety concerns at a variety of facilities. These proposed geotechnical investigations including standard penetration tests (hollow steam auger, sonic drilling), deep borings, Con e P
enetration Test soundings, and geophysical investigations. The facilities which were the subject of these work plans included embankment dams (both compacted and placed using sluicing) with heights up to 165 ft.
D
am Stability Evaluations, Southern California Edison Eastern Hydro Project, CA Geosyntec was retained by SCE as part of an ongoing Dam Safety and Risk Assessment Program (DSRAP) to better understand the risks associated with four of SCE’s hydroelectric dams in the Eastern Sierra including embankment dams and both concrete and wood faced rockfill dams. Chris served as project manager and technical lead for this project which includes static and seismic stability evaluations for these dams under FERC guidelines. The projects involved the use of numerical modeling (including FLAC and Quad4M as well as seepage modeling) to estimate seismic deformations.
R
isk Informed Decision-Making (RIDM) Pilot Project, Southern California Edison, CA Chris was retained by SCE to serve as the geotechnical engineering subject matter expert for the risk -based evaluation of concrete faced rockfill dam, as part of the semi quantitative and quantitative phases of the risk assessment of this dam under new FERC guidelines. This project is the first FERC regulated project to have a quantitative risk assessment conducted under these guidelines.
R
isk Informed Dam Safety Workshop, Los Angeles Department of Water and Power, CA Geosyntec was selected by LADWP to provide its staff with training regarding risk informed decision making as applicable to the Department’s dams. This training was the first of its kind for LADWP as the department begins to shift to a risk - based framework for evaluating their facilities. Chris assisting in facilitating the technical discussions during the training.
S
eismic Probabilistic Risk Assessment, Southern California Edison, CA Chris led the geotechnical portion of the team pioneering the use of Probabilistic Seismic Risk Assessments on hydroelectric and gas fired power plants for SCE. The project ultimately provided clear and actionable recommendations to SCE which can be implemented to reduce the overall seismic risk for their generating assets.
PS
15-06, Seismic Evaluation of Structures at Plants 1 and 2, Orange County, CA Chris is Geosyntec’s project manager for this ongoing planning study with the Orange County Sanitation District. This multidisciplinary earthquake engineering project involves the combined geotechnical and structural evaluations of 60 existing structure at Plants 1 and 2. These Plants when considered together as a system comprise the 3rd largest wastewater treatment plant west of the Mississippi River. The PS15-06 Study will identify vulnerabilities, estimate planning- level budgetary costs to implement the retrofits, and prioritize the importance of implementing these measures.
L
os Angeles Water Wheel, Los Angeles, CA
The Los Angeles River Water Wheel will deliver water from the Los Angeles River for use at the Los Angeles State Historic Park. Flows from the Los Angeles River will be diverted into a tunnel before being lifted by the wheel to above ground elevation. Chris is the lead geotechnical engineer for this project which will include construction of a rubber dam within the Los Angeles River as well as an approximately 40-foot-deep excavation adjacent to Metrolink tracks and other infrastructure. This construction is within the Los Angeles River channel (including inlet and outlet structures) and hence has involved significant interface with the US Army Corps of Engineers including for the design related to dam safety.
EXHIBIT 2
Career Summary
Todd Olsen has ten years of experience as a chemist performing a variety of analytical methods. He has four years of experience conducting analytical data verification and validation on environmental projects including organic and inorganic parameters for water, soil and air sample matrices. Additionally, Todd has led laboratory and sampling coordination on several projects.
Todd has over 4 years of experience conducting data verification and Stage 2A, 2B and 4 data validation. This experience includes the evaluation of organic and inorganic analytical methods for soil, water, and air sample matrices. Examples of Todd’s experience include: routine validation of volatile organic compound, N- nitrosodimethylamine, and perchlorate data from groundwater samples for the Aerojet Rocketdyne Superfund Site; validation of priority pollutant data for national pollution discharge elimination system (NPDES) samples; contaminated site investigations with soil and water samples including data for volatile organic compounds, semi-volatile organic compounds, pesticides, herbicides, polychlorinated biphenyls, polycyclic aromatic hydrocarbons, polyfluoroalkyl substances, metals, extractable metals, mercury, methylmercury, hexavalent chromium and sulfide; and indoor and sub-slab air samples in support of vapor intrusion investigations.
Relevant Project Experience
Aerojet Rocketdyne Superfund Site, Rancho Cordova, California Todd is on a team that manages groundwater monitoring and reporting for various annual, semi-annual, and quarterly monitoring requirements for multiple Operable Units and in accordance with federal and state requirements for the Superfund Site. Todd also provides project quality assurance/quality control support, support for field investigations, and assists with groundwater monitoring and reporting programs and database management.
A
erial Deposited Lead Investigations, California Department of Transportation (Caltrans), Los Angeles, CA
Todd coordinates field sampling, laboratory analyses and additional threshold- based analyses requests for several aerial deposited lead investigations along various highways in Los Angeles.
N
PDES Sampling and Monitoring, Lincoln Center Environmental Remediation Trust (LCERT), Stockton, CA
Todd coordinated the effluent and receiving water characterization study for LCERT between several laboratories and the field staff. This work included analytical method selection, laboratory contracting, field organization and laboratory communication.
D
oD Phase II Remedial Investigation Ogliuga Island Formerly Used Defense Site, AK
Todd conducted Stage 2B validation of the Phase II data sets including metals, petroleum hydrocarbons, VOCs, SVOCs and pesticides for soils, sediments and waters.
Todd Olsen
Scientist
10 Years of Experience
4 Years with Geosyntec
P
roject Roles
Task 7 Data
Mana
gement/Project
Chemist
Specialties
Data Verification and
V
alidation
C
hemistry/Laboratory
Support Task Management
Education
MS, Environmental
Engineering, University of
Illinois, Urbana-Champaign,
Illinois, 2014
BS, Chemistry, University of
Mont
ana, Missoula,
Montana, 2008
BA, Mathematics, University
of Montana, Missoula,
Montana, 2008
Registration & Certifications
40-Hour OSHA
HAZWOPER
EXHIBIT 2
T
odd Olsen
Data Verification and Validation
Todd has over 4 years of experience conducting data verification and Stage 2A, 2B and 4 data validation. This experience includes the evaluation of organic and inorganic analytical methods for soil, water, and air sample matrices. Examples of Todd’s experience include: routine validation of volatile organic compound, N-nitrosodimethylamine, and perchlorate data from groundwater samples for the Aerojet Rocketdyne Superfund Site; validation of priority pollutant data for natio nal pollution discharge elimination system (NPDES) samples; contaminated site investigations with soil and water samples including data for volatile organic compounds, semi-volatile organic compounds, pesticides, herbicides, polychlorinated biphenyls, polycyclic aromatic hydrocarbons, polyfluoroalkyl substances, metals, extractable metals, mercury, methylmercury, hexavalent chromium and sulfide; and indoor and sub-slab air samples in support of vapor intrusion investigations.
Stage Project Scope
2A LCERT Quarterly 2017-present: VOCs, TPH, SVOCs and metals 2A Aerojet Rocketdyne Daily 2017-present: VOCs, perchlorate and NDMA 2A Cache Creek 2018: Mercury and methyl mercury
2A Whittaker Groundwater Monitoring Quarterly 2018-present: VOCs, metals, CrVI and perchlorate 2A Caltrans 2019-present: Metals, TCLP metals, STLC metals 2A Brisbane Poerable Unit 2 2019: Metals, pesticides, PCBs, SVOCs, TPH, VOCs and asbestos
2A Port of Stockton 2019: VOCs, TPH, pesticides, dioxins, methyl mercury and metals
2A Fort Morrow 2020: TPH, VOCs, PAHs, metals and CrVI
2A Bryte Landfill 2020-2021: TPH, SVOCs, pesticides, PCBs, metals and anions
2A Ogliuga 2020-2021: TPH, metals, PCBs, VOCs and PAHs
2A SAFCA Sacramento Weir Widening
Project 2021: TPH, pesticides, metals and mercury
2A Target Davis Vapor Intrusion 2021: VOCs
2B Joint Base Elmendorf-Richardson 2020: PCBs, pesticides, herbicides, PAHs and SVOCs 2B Abbot Street and Harns Road Salinas 2022: Pesticides 4 Aerojet Rocketdyne 2022: Metals, CrVI and mercury
C
rVI - Hexavalent chromium
NDMA - N-Nitrosodimethylamine
PAH - Polycyclic aromatic hydrocarbons
PCB - Polychlorinated biphenyl
STLC - Soluble Threshold Limit Concentration
SVOC - Semi-volatile organic compound
TCLP - Toxicity Characteristic Leaching Procedure
TPH - Total petroleum hydrocarbons
VOC - Volatile organic compounds
EXHIBIT 2
Career Summary
Dr. Chambon is a senior professional in Geosyntec’s groundwater group. She is responsible for managing and supporting multiple projects that include water resources assessment, hydrogeological evaluation, groundwater flow and transport modeling, groundwater monitoring, remediation performance evaluation, site investigation and characterization, and well field design. Dr. Chambon has modeling, remediation, and strategic advisement experience with a wide variety and scale of sites. She applies her background in environmental engineering, hydrogeology, flow and transport modeling, and microbiology to remediation and water resources projects. Dr. Chambon has experience as a lead modeler for a groundwater modeling project to evaluate the feasibility of infiltration basins of recycled water and downgradient extraction for potable use at a project in Southern California.
Relevant Project Experience
Multiple Remedies including Groundwater Extraction and Treatment for Potable Use and Surface Water Discharge, Confidential Client, San Gabriel Basin, CA
Dr. Chambon is the project manager for multiple remedies at San Gabriel Valley Superfund Site. The project includes development of a conceptual site model, groundwater flow model, designing and implementing a 1,500 gallon per minute (gpm) groundwater extraction and treatment system with treatment for potable use and a 200 gpm groundwater extraction and treatment system with discharge to surface water. Constituents to be treated include volatile organic compounds (VOCs), perchlorate, 1,4-dioxane, nitrate, metals, and total dissolved solids. Dr.
Chambon is also the lead modeler on this project; she has updated an existing groundwater flow model and performed transient calibration. The FEFLOW model covered the entire San Gabriel Basin and consisted of 17 layers. The transient model was calibrated to a 40-year simulation period, and a series of datasets collected during multiple aquifer tests. Following model calibration, 30-year transient predictive simulations were performed to evaluate potential well field configurations for two proposed groundwater extraction systems. The model was also used to evaluate potential re-injection design for the remedy. The model will be used as a basis for monitoring and evaluating system performance during operation of the remedies.
G
roundwater Development and Augmentation Plan, Los Angeles Department of Water and Power, Los Angeles, CA
Dr. Chambon assists with management and technical analysis on a team developing a groundwater development and augmentation plan to enhance groundwater resources within the Los Angeles Plain south of the Elysian Narrows, including the Central, West Coast, Santa Monica, and Hollywood Basins. The work includes review and assessment of hydrogeological conditions, including groundwater flow modeling; hydraulic evaluation of the distribution system; and assessment of water sources for augmentation and treatment requirements.
O
cean Water Desalination Subsurface Intake Study, West Basin Municipal Water District, El Segundo, CA Dr. Chambon led the development of a guidance manual and screening tool for assessing feasibility of subsurface intakes for desalination facilities. The tool as developed as part of a feasibility study of subsurface intakes for a proposed desalination facility along the coastline of Santa Monica Bay, which require seawater intake rates of at least 40 million gallons per day (MGD). Dr. Chambon also assisted with the development of a cost estimate for implementation of a seabed infiltration gallery at El Segundo to support the preparation of the Environmental Impact Report by West Basin Municipal Water District.
R
echarge Feasibility Study, Newhall County Water District, Castaic, CA Dr. Chambon is the lead modeler for a groundwater modeling project to evaluate the feasibility of infiltration basins of recycled water and downgradient extraction for potable use. Dr. Chambon developed and calibrated the flow model and Julie Chambon,
PhD, PE
Senior Engineer
9 Years of Experience
9 Years with Geosyntec
P
roject Roles
Task 8 Modeling
Specialties
Groundwater Fate and
T
ransport Modeling
Water Resources
Hydrogeology
Education
PhD, Environmental
Engineering, Technical
University of Denmark,
Lyngby, Denmark, 2012
MS, Environmental
Engineering, Technical
University of Denmark,
Lyngby, Denmark, 2007
MS, Engineering, Ecol
e
C
entrale de Lille, Lille,
France, 2007
EXHIBIT 2
J
ulie Chambon, PhD, PE
used it to assess multiple infiltration and extraction alternatives. The feasibility assessment was presented to the client and other stakeholders.
N
umerical Model Calibration for Assessment of Water Supply Impacts, Crystal Geyser, Cartago, CA Dr. Chambon reviewed and updated an existing groundwater flow model and performed steady -state calibration. The model was used to estimate the impacts of future pumping scenarios on groundwater level, spring flow, and other water supply wells in the area. The modeling results were included in the Groundwater Mitigation and Monitoring and Reporting Plan and contributed to the approval of the Crystal Geyser project.
Re-I
njection Modeling Evaluation, Schlumberger Technology Corporation (STC), Middlefield-Ellis-Whisman Superfund Site, Mountain View, CA
Dr. Chambon led the development and use of a groundwater model to evaluate the feasibility of re- injection of extracted and treated groundwater. Dr. Chambon developed estimates of re-injection well capacity, and used the groundwater model to assess re-injection wellfield layouts, including evaluation of anticipated mounding and containment of the re- injected groundwater by the existing recovery wells.
N
umerical Model Development for Groundwater Flow and Solute Transport, VOC Plume , Santa Barbara County Public Works Department, Solvang, CA
To predict the longterm behavior of a VOC plume, Dr. Chambon developed, calibrated, and performed predictive simulations of a numerical flow and transport model. The simulation period covered 30 years, with calibration focused on a 12-year period of available site data. The model was used to assess natural attenuation of the VOC plume and support the design of the monitoring network.
N
umerical Model Development Strategy for Assessment of Source Remediation Alternatives, LDD Technologies, Ashdod, Israel
Dr. Chambon provided technical and project management support for development of a solute transport model to support the assessment of source remediation alternatives at an operating chemical plant. Dr. Chambon led the preparation of the work plan, including review of hydrogeological and analytical data at the site and regional scales, definition of model area and boundary conditions consistent with model purposes and available data, and determination of remediation scenarios to be evaluated using the model. The work plan was approved by the local regulatory authority. Dr. Chambon led the construction and calibration of the groundwater flow and solute transport model. The model was used to evaluate and compare multiple source reduction scenarios, including simulations of contaminant concentrations at downgradient monitoring and production wells.
N
umerical Model Calibration for Assessment of Water Supply Impacts, Crystal Geyser, Cartago, CA Dr. Chambon reviewed and updated an existing groundwater flow model and performed steady -state calibration. The model was used to estimate the impacts of future pumping scenarios on groundwater level, spring flow, and other water supply wells in the area. The modeling results were included in the Groundwater Mitigation and Monitoring and Reporting Plan and contributed to the approval of the Crystal Geyser project.
N
umerical Model Development for Groundwater Flow and Solute Transport for Quarry Reclamation Plan , Confidential Client, Aromas, CA
Dr. Chambon developed, calibrated, and performed predictive simulations of a numerical flow and transport 3D model for assessing reclamation alternatives for a quarry. The model was used to assess the impact of the development of the quarry on local and regional groundwater flow in a complex geological system with multiple faults and fractures.
G
roundwater Modeling Work Plan, Settling Work Defendants, Omega Chemical Corporation Superfund Site, CA Dr. Chambon led the preparation of the groundwater flow modeling work plan for the Omega Chemical Corporation Superfund Site, Operable Unit 2. The work plan described the development and calibration of the groundwater flow model that would support design of the pump-and-treat system, selection of the compliance monitoring wells, and performance evaluation of the remedy after system startup.
EXHIBIT 2
Career Summary
Dr. Wildman has over eight years of consulting experience in environmental engineering and project management, as well as eight years of prior academic research experience. In her consulting work, Dr. Wildman develops remediation strategies, work plans, feasibility studies, treatability studies, pilot studies, cost estimates, and remedial design and specification documents under the oversight of regulatory agencies. She applies her background in environmental engineering, water chemistry, and geochemistry to remediation and litigation technical support.
Dr. Wildman’s primary technical focus is on metals, and she is an active leader in Geosyntec’s internal geochemistry practice group. Her selected project experience is described below.
Relevant Project Experience
Evaluation of Copper Leaching from Sediments, Confidential Client, New York City, NY
Dr. Wildman performed geochemical modeling to evaluate leaching of copper from sediments under current conditions and under oxic conditions if sediments are disturbed. She used advanced software including Visual Minteq and Geochemist’s Workbench to model the expected concentration of copper in sediment porewater under current and projected conditions, including complexation with solid- and dissolved-phase organic matter. The model results were paired with an ecological toxicology assessment to inform the client of potential risks of a remedial strategy to leave sediments in situ.
E
valuation of Arsenic Background in Groundwater, Confidential Client, Morris, KS
Geosyntec supports a rail company and its consultant in evaluating the likely background concentration of arsenic in groundwater at a former rail yard in Kansas. The site is in the floodplain of the Kansas River, which is known to have an elevated arsenic concentration in soil and groundwater due to natural conditions. A nearby property owner has suggested that the former rail yard is the source of arsenic in their groundwater. Dr. Wildman and others have reviewed historical and regional arsenic groundwater data and provided a critical peer review to the sample collection program and statistical analysis performed by the other consultant.
A
sh Leaching Evaluation, Waste Management, El Sobrante, CA Dr. Wildman performed geochemical modeling to help justify waste acceptance criteria for ash at a landfill. She used advanced software including Visual Minteq and Geochemist’s Workbench to model the expected concentrations of the metals cadmium, copper, lead, and zinc in leachate when equilibrated with ash wastes.
Geosyntec’s effort helped gain approval from the Regional Water Quality Control Board for the waste acceptance criteria for ash.
F
easibility Study for Remediation of Mercury in Groundwater, Confidential Client, Oakland, CA
Dr. Wildman reviewed technical data and coordinated with the lead consulting firm to develop remedial strategy for a former chlor-alkali site. Along with other Geosyntec practitioners, she helped the lead consulting firm draft a viable FS addendum based on bench-scale treatability testing for a permeable reactive barrier to treat dissolved mercury in groundwater. Currently, Geosyntec supports the development of an updated conceptual site model for groundwater.
C
onceptual Feasibility Study on Iodine Addition for Perchlorate in Drinking Water, Confidential Client, Atlanta, GA
Dr. Wildman researched and prepared a conceptual FS on the addition of iodine to drinking water supplies to mitigate the health impacts of low levels of perchlorate.
Claire Wildman,
PhD, PE
Senior Engineer
15 Years of Experience
10 Years with Geosyntec
P
roject Roles
Task 8 Groundwater Quality
Specialties
Site Investigation,
Characterization, and
R
emediation
Litigation Support
Geochemistry Technical
Expert
Education
PhD, Environmental
Science, and Engineering,
California Institute of
Technology, Pasadena,
2011
MS, Environmental Scienc
e
and E
ngineering, California
Institute of Technology,
Pasadena, 2007
BS, Civil Engineering,
magna cum laude,
Washington University, St.
Louis, Missouri, 2005
Registration & Certifications
California Professional
Engineer No. 83691
40-Hour OSHA
HAZWOPER 29 CF
R
1910
.120(e)(3)I Training
American Red Cross First
Aid and CPR Certification
EXHIBIT 2
Cl
aire Wildman, PhD, PE
Geosyntec prepared and published a technical manuscript in the Journal of the American Water Works Association to assist in the client’s push for regulatory approval of this risk mitigation strategy. The journal article was published in Ju ne 2015. Geosyntec continues to advise the client on regulatory feasibility aspects of this concept.
M
onitored Natural Attenuation (MNA) Framework at Coal Combustion Residuals (CCR) Sites, Electric Power Research Institute (EPRI), National
Dr. Wildman supported a multi-office Geosyntec team in developing an EPRI guidance document for owners and operators of CCR sites, such as ash tailings piles. The document presents a framework to implement MNA, where appropriate, for metals and inorganic constituents at CCR sites, in compliance with previous USEPA and Interstate Technology and Regulatory Council (ITRC) guidance documents as well as current CCR regulations.
S
ource Characterization and Evaluation of Remedial Options, Confidential Client, CA Geosyntec provides technical assistance to a client with a wastewater stream high in particulates, antimony, and boron.
Services include an evaluation of the potential sources of antimony to the wastewater, an evaluation of on- site treatment options for antimony, an evaluation of treatment options for boron within the local wastewater treatment plant, and ongoing discussions with the local wastewater treatment plant operators. Geosyntec’s technical guidance has helped the client’s renovation project move forward with local permitting authorities.
P
eer Review Report of Ecological Risk Assessment for Deep-Sea Cyanide Tailings Discharge, Lihir Gold Operation, Newcrest Mining Limited, Lihir, Papua New Guinea Dr. Wildman managed a multi-office Geosyntec team to review Lihir Gold Operation’s Ecological Risk Assessment for Deep-Sea Cyanide Tailings Discharge, prepared for compliance with the International Cyanide Management Institute Code. Dr. Wildman maintained budget and coordinated the written report with technical findings from staff across the United States. The client then requested that Geosyntec prepare a single peer review panel report, synthesizing technical issues raised by Geosyntec and two other peer review teams hired by the client. The client was pleased with Geosyntec’s effort for striking a balance between criticism of the ecological risk assessment report and understanding of the client’s desire to comply with environmental regulations.
D
evelopment of Predictive Tools for Assessment of Natural Attenuation Capacity and Treatment Transition at Chlorinated Solvent Sites, SERDP, United States
Geosyntec, in partnership with Dr. Natalie Capiro of Auburn University, Dr. Kurt Pennell of Brown University, and Dr. Mark Widdowson of Virginia Technical Institute, is conducting a research project through the Strategic Environmental Researc h and Development Program (SERDP) of the United States Department of Defense. Dr. Wildman is the project manager for this project, which entails fundamental research on the natural attenuation capacity of soils and aquifer materials for sites with chlorinated solvent plumes. Geosyntec’s work focuses on coupling the findings of bench- scale experiments and contaminant fate and transport modeling with data available on project sites. The findings of this SERDP study, expected in 2023, will assist remedial site managers in evaluating and justifying the transition from active remediation to monitored natural attenuation on contaminated sites.
G
roundwater Remedial Technologies Review, United States Department of Energy Legacy Management, Navarro Research and Engineering, Shiprock, New Mexico and Tuba City, AZ Dr. Wildman manages a project to evaluate groundwater remedial technologies to address contamination of United States Department of Energy Legacy Management Sites at Shiprock, New Mexico, and Tuba City, Arizona. Both sites are former uranium mills with capped piles of tailings in complex geological settings. Tailings and other residual source mass have leached into groundwater over years of operations prior to remedial activities beginning in the 1990s, leading to groundwater contamination with uranium, nitrate, and sulfate, among other constituents. Existing groundwater extraction and treatment systems are approaching their design lifetimes. Geosyntec’s remedial technologies review includes in situ and ex situ technologies evaluated against the nine CERCLA criteria and recommends technologies to evaluate with further investigation activities.
EXHIBIT 2
Career Summary
Dr. Belli has three years of professional consulting experience and specializes in biogeochemistry and soil and groundwater remediation. He conducts field investigations, environmental media sampling, and data analysis to support soil and groundwater remediation projects. Dr. Belli has seven years of biogeochemistry research experience, including both laboratory and field studies, and his doctoral dissertation focused on the bioremediation of uranium- contaminated groundwater associated with nuclear processing facilities. Dr. Belli applies his experience in biogeochemistry, soil and groundwater sampling, and geochemical modeling to support remediation projects involving organic and inorganic contaminants in diverse geochemical and geological environments.
Highlights of his experience include the following projects.
Relevant Project Experience
Reconnaissance and Reporting, Confidential Client, Port of Richmond, CA Dr. Belli performed beach reconnaissance near a former oil seep to identity visible sheens and water seeps within the intertidal zone of the San Francisco Bay.
Reconnaissance included collecting photographs, global positioning system (GPS) locations, and detailed descriptions of visible sheens. Dr. Belli was the lead author of the Main Beach Inspection report, which was submitted to the San Francisco Bay Regional Water Quality Control Board.
U
ranium Mill Tailings Radiation Control Act Title I Sites, Navarro Research and Engineering, United States
Dr. Belli co-authored the revised Technical Approach to Groundwater Restoration (TAGR) for United States Department of Energy (DOE) sites regulated under Title I of the Uranium Mill Tailings Radiation Control Act (UMTRCA). The TAGR provides general technical guidance to implement restoration of uranium-impacted groundwater at Title I sites in accordance with requirements established under UMTRCA. Since publication of the original TAGR in 1993, several key programmatic documents and regulations have since been finalized. The revised TAGR clarifies groundwater restoration based on the standards promulgated by the United States Environmental Protection Agency (USEPA); recognizes current programmatic requirements, processes, and efficiencies for groundwater compliance actions plans and associated efforts; and incorporates advances in remedial technology and site management. This document will guide groundwater restoration efforts at 21 Title I sites across nine states and tribal lands.
R
egional Program for Multiple Superfund Sites, Volatile Organic Compound (VOC) Release, Former Manufacturing Facilities, Mountain View, CA Dr. Belli served as task manager for the preparation of an annual progress report related to a mile-long, regional trichloroethene (TCE) plume. His responsibilities included kriging of groundwater contour maps and extraction well capture zones using KT3D contouring software, preparation of 20 large chlorinated solvent isoconcentration contour maps, and Mann-Kendall trend analysis of chlorinated ethene concentrations at over 360 well locations. Dr. Belli coordinated peer, senior, and client review and submission of the annual progress report to the United States Environmental Protection Agency.
In-S
itu Chemical Oxidation (ISCO) Injections, Schlumberger Technology Corporation (STC), Middlefield-Ellis-Whisman Superfund Site, Mountain View, CA
Dr. Belli served as field staff for ISCO injections of sodium permanganate and sodium persulfate in a commercial and high-profile area that contained soil and groundwater impacted by chlorinated solvents. He was responsible for on- site supervision of subcontractors, collection of field data prior to and during injections, and preparation of daily summaries of injection details. Dr. Belli served as the lead author of the report summarizing the ISCO injection event, which was submitted to the United States Environmental Protection Agency.
Keaton Belli, PhD
Scientist
7 Years of Experience
3.5 Years with Geosyntec
P
roject Roles
Task 8 Groundwater Quality
Specialties
Biogeochemistry
Soil And Groundwater
Remediation
Environmental Site
Characterization
Education
PhD, Biogeochemistry,
Georgia Institute of
Technology, Atlanta, 2018
BS, Earth and Atmospheric
Sciences, Georgia Institut
e
of
Technology, Atlanta,
2010
Registration & Certifications
40-Hour OSHA
HAZWOPER 29 CFR
1910
.120(e)(3)I Training
American Red Cross First
Aid and CPR Certification
EXHIBIT 2
Keaton B
elli, PhD
Remedial Investigation and Pilot Studies at a Former Western Chemical Facil ity, Confidential Client, La Mirada, CA Dr. Belli assists with analysis and interpretation of geochemical data from a bench- top treatability study. The study examines a site characterized by a large 1,4 dioxane, tetrachloroethene (PCE), and TCE groundwater plume. Dr. Belli’s responsibilities include analyzing data from the treatability study to determine the efficacy of potential oxidants to be used in the forthcoming ISCO treatment at the site. He also assists with the design of the forthcoming ISCO injection pilot test.
G
roundwater Extraction and Treatment System Operations and Maintenance, Confidential Client, CA Dr. Belli assists with the operation and maintenance of a groundwater extraction and treatment system (GETS) featuring a fixed-bed bioreactor for removal of VOCs, selenium, chromium, and perchlorate.
C
onceptual Site Model and Transport Modeling of Molybdenum in Soil and Groundwater at a Molybdenum Processing Facility, Confidential Client, IA
Dr. Belli contributed to the development of a conceptual site model at a molybdenum processing facility where soil and groundwater are impacted by molybdenum. Dr. Belli evaluated soil and groundwater geochemical data to identify the dominant geochemical processes controlling the subsurface mobility of molybdenum. Based on the conceptual site model, Dr. Belli assisted with the development of a molybdenum fate and transport model and led the incorporation into the model of geochemical processes that retard the transport of molybdenum in groundwater. The molybdenum transport model successfully reproduced groundwater molybdenum concentrations at the site and was used to assess future changes to the molybdenum groundwater plume in response to operation and management of on- site groundwater production wells. Dr. Belli contributed to a technical memorandum that summarized the results of the molybdenum modeling exercises and was incorporated into a Remedial Action Plan.
I
n Situ Biological Remediation (ISBR) System Operations and Maintenance, Confidential Client, CA Dr. Belli assists with routine operations and maintenance of an ISBR remedy designed to reduce perchlorate concentrations within an isolated sand lens via pulsed injection of emulsified vegetable oil (EVO) into recirculated groundwater. Dr. Belli is involved in the analysis and interpretation of geochemical field data from the site to assess the efficacy of the remedy, and he summarizes these findings in the annual groundwater monitoring report submitted to the Regional Water Quality Control Board.
G
eochemical Controls of the Microbially Mediated Redox Cycling of Uranium and Iron , Georgia Institute of Technology , Atlanta, GA
For his Ph.D. dissertation, Dr. Belli studied microbial uranium reduction as a bioremediation strategy to address uranium- contaminated groundwater associated with nuclear processing facilities. This research investigated the effects of groundwater composition on uranium bioreduction kinetics and identified the geochemical conditions under which iron oxides are predicted to enhance or hinder uranium removal from solution via dissimilatory uranium reduction. These results were incorporated into a geochemical kinetic model that successfully reproduced the rate of uranium removal from groundwater over a wide range of conditions. Overall, this body of work identified geochemical parameters that should be considered when implementing uranium bioreduction technologies and advanced the ability to predict the fate of uranium in geochemically diverse environments.
S
ource, Composition, and Stability of Soluble Iron Fluxing from Continental Margin Sediments , Georgia Institute of Technology, Atlanta, GA
Dr. Belli spent eight weeks aboard the research vessel (R/V) Savannah investigating the flux of soluble iron from ocean sediments along the North Atlantic continental margin. Dr. Belli managed the onboard wet chemistry laboratory and was responsible for sediment core collection, core sectioning and porewater extraction, onboard porewater analysis, sample inventory, and sample storage.
EXHIBIT 2
Career Summary
Mike is a senior geologist and project manager with 16 years of experience in project management support, remedial investigations/feasibility studies, and remedial actions at hazardous waste sites. He provides expertise related to hazardous materials/hazardous waste services during the preparation of multiple ISAs in accordance with lead agency standards and related consulting for the Environmental Impact Report (EIR) and has assisted in the preparation of EIRs with respect to hydrogeology, geology, and hazardous materials assessments and other associated planning documents. Mike has been the lead professional geologist for various types of projects throughout California, including evaluation and interpretation of data for technical reports, geophysical evaluations, geological investigations, geologic field mapping and interpretation, borehole logging, soil classifications with an emphasis on USCS classification, measurement of soil mechanic properties using the Atterberg limits, interpretation of groundwater chemistry trends, aquifer vulnerability analysis, and field identification of rocks and minerals.
Mike has extensive experience as a contract and project manager, supporting environmental programs, contracts, and projects. These projects include site investigation and remediation services; hazardous materials and hazardous waste management; asbestos, lead-based paint; PCB management; and regulatory compliance on contaminated sites across central and Northern California. He has superior project management skills and places a high value in being responsive to his clients. Mike is an effective communicator and clients appreciate his advocacy on their behalf and has successfully led projects to close on schedule and on budget.
Relevant Project Experience
Environmental Site Assessment, BLT Property, Sacramento County, CA Responsible geologist for the site reconnaissance and preparation of a Phase I ESA on the property identified by the Sacramento County Assessor’s Office as Assessor’s Parcel Number (APN) 215-0244-027. During the Phase I ESA, recognized environmental conditions (RECs) were noted, including groundwater beneath the site, and surface water/sediment contamination along Don Julio Creek. Mike also performed a limited Phase II ESA to address the RECs discussed in the Phase I ESA by collecting surface water/sediment samples to assess for these potential RECs.
S
AFCA Area Wide Due Diligence Environmental Assessment for Natomas Basin Levees, Sacramento and Sutter Counties, CA
Provided technical oversight for Phase I ESAs for this area-wide due diligence assessment of properties owned by approximately 200 individual landowners along the Natomas Basin in Sacramento and Sutter Counties. The purpose of the due diligence assessment was to evaluate environmental conditions that could affect the proposed levee upgrade project. In the preliminary evaluation, properties were screened for potential presence of hazardous materials, recognized environmental conditions, and identified “significant data gaps”. Based on the results of the preliminary evaluation, individual properties with potential recognized environmental conditions were further evaluated in accordance with the ASTM Phase I ESA E 1527-05 process.
R
ice Pesticide Monitoring Program, California Rice Commission, Sacramento, CA Mike was the primary point of contact and program manager responsible for implementation of surface water sample collection and coordination of laboratory samples and analysis to monitor drainage basin water for sediment load and pesticides used for the production of rice. He was responsible for the review and quality assurance of field parameters and laboratory analysis reported to the California Rice Commission. Results were compiled and discussed in the annual groundwater assessment report as required under the Regional Water Quality Control Board’s long- term irrigated lands regulatory program. Mike worked directly with the California Rice Commission and Yuba County Water Agency SAFCA Phase I and II
Mike van den
Enden, PG
Senior Geologist
16 Years of Experience
1 Years with Geosyntec
P
roject Roles
Task 8 Infiltration Methods
Specialties
Hydrogeology
Groundwater monitoring
and as
sessment
Hazardous materials/waste
management
Education
BS, Geology, California
S
tate University, Stanislaus
Registration & Certifications
California Professional
Geologist No. 9286
EXHIBIT 2
M
ike van den Enden, PG
Groundwater Sustainability Agency for the placement of shallow groundwater monitoring wells that would be used to monitor first encountered groundwater trends.
G
roundwater Consultation, Sacramento County Waste Management District and Recycling, Sacramento, C A Mike was the primary point of contact and project manager responsible for preparing a Corrective Action Program Monitoring Well Rehabilitation-Reconstruction Work Plan. He helped to prepare a detailed conceptual model of the hydrogeologic environment to address the notice of violation issued for wells that were determined to be dry. The Work Plan provided rationale for using other existing monitoring wells to replace the dry wells in the monitoring program. Mike prepared a pilot study to evaluate the effectiveness of extracted groundwater being directed to designated, on- site infiltration basins. This was meant to reduce the carbon footprint of the groundwater treatment system and provide a beneficial re-use of groundwater through aquifer recharge, following written executive officer approval from the Water Board. Under the National Pollutant Discharge Elimination System, the Kiefer Road landfill groundwater treatment plant was authorized to discharge up to 2.17 million gallons per day of extracted groundwater into Deer Creek or to an on- site sedimentation basin during maintenance treatment system operations.
On-C
all Environmental Compliance and Program Development Services, Sacrament o Municipal Utility District (SMUD), Sacramento, CA
Mike was the program manager for numerous environmental projects on a multi-year, on-call contract. He oversaw and performed regulatory compliance (RCRA, TSCA); Phase I and II Environmental Site Assessments; soil removal; environmental compliance program development; environmental health and safety; site investigation and remediation design; UST removal and sampling; stormwater management; PCB management; training; emergency response planning; greenhouse gas reporting; and hazardous materials and hazardous waste management.
P
CB Management, SMUD, Sacramento, CA
Mike was the project manager and point of contact that worked with SMUD for the PCB notification and remedial management plan. His responsibilities included developing the scope of work and preparing cost proposals, work plans, and notifications to the United States Environmental Protection Agency (USEPA). Other tasks included collecting soil samples and performing statistical data analysis for soils containing PCBs. Mike worked closely with SMUD project managers to develop the approved PCB notification and remedial plan for SMUD headquarters’ building renovation project to manage PCB remedial waste in accordance with the USEPA’s risk-based disposal criteria.
P
hase II Environmental Site Assessments (Phase II ESA), Various SMUD Locations, Sacramento, CA Mike was the project manager responsible for conducting subsurface investigations utilizing hand- auger, hollow-stem, direct-push drilling, and CPT methods, groundwater well installations, groundwater monitoring, and groundwater well destructions. He coordinated underground storage tank (UST) removal activities and performed sampling and profiling of excavated contaminated soil for offsite disposal at licensed facilities.
C
alifornia Highway Patrol Academy Site Investigation and Remediation, Department of General Services (DGS), West Sacramento, CA
Mike managed this $1+ million, 5-year contract involving site investigation and remediation work at the California Highway Patrol Academy where a release from an onsite UST resulted in soil and groundwater contamination. He coordinated and oversaw the removal of existing USTs and was responsible for costs, client coordination, preparation of work plans, assigning pre-field tasks to staff, conducting safety meetings, and coordinating field activities. Mike provided oversight of the UST Removal Work Plans, Underground Service Alert notifications, geophysical surveys, UST excavation and disposal; soil sampling and waste disposal as well as preparation of removal report, and coordination with regulatory agencies including Yolo County Division of Environmental Health Services (YCDEHS) and UST Tank Fund. Follow -on work included preparation and submittal of additional site investigation work plans for well installations, hydro- punch groundwater sampling, additional well installations, and implementation of further remedial action plans.
EXHIBIT 2
Career Summary
Brandon Steets is a Senior Principal based in Santa Barbara with over 20 years’ experience. Mr. Steets specializes in NPDES and TMDL regulations, pollutant source investigation, watershed water quality modelling, and Green Infrastructure design. He often serves as technical expert on Clean Water Act litigation. He is a frequently invited speaker, including to statewide audiences through CASQA, SWRCB webinars, California Association of Sanitation Agencies, and the California Lawyers Association. He has led online training for nationwide organizations including ASCE and ITRC. His projects have been recognized with awards from ASCE, CASQA, and NACWA. He is a trusted resource to regulators, having led multiple high profile studies for the SWRCB (e.g., statewide drywell guidance, modeling for new instream flow criteria, septic nutrient source tracking, and modeling for the 2018 IGP Amendment alternative compliance options) that may form the basis of new statewide regulation or policy or modify an existing TMDL. And he helped develop new guidance for state regulators nationwide, for ITRC’s Stormwater BMP Performance and Harmful Cyanobacteria Bloom teams.
Mr. Steets is a subject matter expert on bacteria issues, including Microbial Source Tracking (MST), risk assessment, and modeling. He was a member of the SWRCB’s Clean Beaches Task Force, stormwater focus group member for the Statewide Bacteria and Numeric Nutrient Objectives Updates, co-editor of the ASCE report Pathogens in Urban Stormwater Systems, co-author of the Colorado E.
c
oli Toolbox guidance manual, expert peer reviewer on coastal bacteria topics for the journal Water Research, and advisor to the National Water Research I
nstitute on MST issues. He has published articles in Stormwater Magazine and W
ater Research on bacteria treatment and modeling. He supported a SWRCB- funded MST study with UCSB that was the first to publish on sewer exfiltration into s
torm drains. He has led or supported roughly 20 bacteria-controlled MS4 w
atershed plans, resulting in the planning of over $6 billion in new green i
nfrastructure, and was a TAC member for the San Francisco region’s Reasonabl e A
ssurance Analysis (RAA) guidance.
Relevant Project Experience
Statewide Drywell Guidance, CA
Project director for development of new statewide guidance for drywell siting, design, installation, maintenance, and monitoring. Includes review of existing data and published studies, identification of research needs and gaps, development of a framework to assess risks to groundwater quality, and management of a Technical Advisory Committee.
R
edding Stormwater Resource Plan (SRP), Redding, CA
Project director for a SRP developed per State Water Board guidelines, for local MS4 agencies to access Proposition 1 state grants. Includes public parcel screening, structural BMP project prioritization and design concept development, hydrologic and water quality modeling for estimation of water supply capture and pollutant load reduction benefits, capital and O&M cost estimation, quantification of other multi-benefits, and stakeholder outreach support. Includes BMP feasibility assessment, 30% design, and implementation grant application development for multiple top priority projects.
L
ower Santa Clara River Bacteria TMDL Implementation Plans, Ventura County, CA Project director for an Implementation Plan for agencies in the Lower Santa Clara River watershed, including identification/prioritization of structural and non-structural BMPs, Reasonable Assurance Analysis watershed modeling, implementation cost estimation, and recommendations for future monitoring and special studies. Includes development of multiple regional infiltration project design concepts for four cities and the County.
S
anta Barbara Countywide Stormwater Resource Plan (SRP), Santa Barbara County, CA Project director for development of a Countywide SRP, for County MS4 agencies to access State grants. Includes parcel screening, feasibility and permitting assessment, perc testing, project prioritization, conceptual through preliminary (30%) Brandon Steets, PE
Senior Principal
22 Years of Experience
18 Years with Geosyntec
P
roject Roles
Task 8 Infiltration Methods
Specialties
Stormwater planning and
per
mitting
Water quality modeling and
monitoring studies
Education
MS, Environmental
Engineering, University of
California, Santa Barbara,
2000
BS, Environmental
Engineering, Rensselaer
Polytechnic Institute, Troy,
New York, 1998
Registration & Certifications
Registered Professional
Engineer, Chemical, State
of
California, No. CH6132
EXHIBIT 2
B
randon Steets, PE
design, modeling of water supply and pollutant load reduction benefits, quantification of other multi-benefits, capital and O&M cost estimation, and stakeholder outreach support.
C
onfidential Stormwater Litigation Support, Major Northern California Power Utility Retained as technical expert to support negotiation of Consent Decree with environmental NGO plaintiff related to stormwater runoff from treated wood pole storage areas at over two dozen facilities, under RCRA (Ecological Rights Foundation v. Pacific Gas and Electric Company, U.S. District Court N.D., Cal. Case No. 3:10-cv-00121-RS; settled).
Includes analysis of sampling results, recommendations for numeric benchmarks and dioxin TEQ calculation/reporting procedures, and development of a stormwater sampling plan and BMP pilot study plan, to evaluate treatment performance among multiple BMP options. Ongoing work includes implementation of settlement – BMP design, construction, performance sampling, dilution factor calculations, and reporting.
C
onfidential industrial wastewater and stormwater WDR and NDPES permitting and enforcement support, Central Valley turkey processing facilities, CA
Retained as regulatory expert to support outside counsel in response to potential enforcement action. Followed by development of WDR permit application for discharge of treated industrial wastewater and stormwater to pasture land.
Includes water and pollutant mass balance modeling to evaluate antidegradation of groundwater for salts and nutrients, hydrogeological assessment, regulatory negotiation to support successful acquisition of new individual WDR permit, and ongoing permit compliance reporting. Involvement now extended to other facilities with tasks including discharge permit application for industrial stormwater (statewide IGP), compost stormwater (other statewide general NPDES permit), and discharge to land for small municipal wastewater treatment system (individual WDR order).
S
an Francisco Baykeeper v. Cities of Sunnyvale and Mountain View, Santa Clara County, CA Retained as technical expert supporting municipalities on Clean Water Act citizen suit case against NGO plaintiff over alleged non-compliance with regional MS4 NPDES permit and alleged bacteria Water Quality Standard exceedances.
Includes technical analysis of MST data and claims of sewer exfiltration, and regulatory analysis of permit compliance.
Tasks include production of expert and rebuttal reports, review of plaintiff expert reports, and deposition.
S
anta Monica Bay (SMB) Enhanced Watershed Management Plans (EWMPs) and Coordinated Integrated Monitoring Plans (CIMPs), Multiple Cities, Los Angeles County, CA Senior reviewer of CIMPs, to meet MS4 Permit receiving water and outfall monitoring requirements, and of Work Plans and EWMPs, including BMP identification and RAA modeling to demonstrate compliance with bacteria TMDL- based limits and other water quality standards, using the SBPAT and WMMS/LSPC models. The four SMB EWMP Groups include North SMB (led by City of Malibu), SMB J2/3 (led by City of Los Angeles), Southbay Beach Cities (led by Redondo Beach), and Peninsula Cities (led by Rancho Palos Verdes).
S
outh Orange County Water Quality Improvement Plan (WQIP), Orange County, C A Chief architect of a first of its kind, MST-based Pathogen Control Strategy to address the regional bacteria TMDL (including RAA modeling), in the first WQIP or EWMP in the State to address a bacteria TMDL primarily through source control rather than Green Infrastructure, with potential to reduce cost by over $600M while achieving greater public health protection. Ongoing work involves testing dry weather source water types (potable, reclaimed, sewage, groundwater) using novel forensic tools (community sequencing, pharmaceuticals and personal care products, ions, isotopes, H F183, and HF183 with PMA viability dye) to differentiate flow sources to MS4s.
S
an Diego Bay Sediment Recontamination Study, Paleta Creek and Naval Base San Diego, San Diego, CA Water quality monitoring plans, installation and programming of autosamplers, WinSLAMM model review/interpretation, data analysis, and reporting to evaluate risk of industrial and urban stormwater in recontaminating sediment remediation sites. Collaboration with researchers from Texas Tech, Univ. of Michigan, US Navy’s Space and Naval Warfare Systems Command (SPAWAR), and Univ. of Alabama, and funded through Department of Defense Strategic Environmental Research and Development Program (SERDP) grant.
EXHIBIT 2
Career Summary
Dr. Struck has 20 years of water resources experience with a focus on planning and implementation of stormwater management practices including green stormwater infrastructure to meet drainage and NPDES permit requirements. He is experienced in infrastructure prioritization, modeling, design, optimization, real- time controls, monitoring, performance assessment, economic and triple bottom line cost analyses, and integrated watershed planning. He has participated in projects throughout North America and has contributed to the development of several computational stormwater management and cost tools, including the cost module of EPA’s National Stormwater Calculator and the US National Academies of Sciences Watershed-Based Planning Approach and Toolbox. Dr. Struck serves as an associate journal editor for the Journal of Sustainable Water in the Built Environment and is currently the President of the Environmental and Water Resources Institute of the American Society of Civil Engineers.
Relevant Project Experience
Evaluating Low Impact Development (LID, Green Infrastructure) and Surface Water – Groundwater Interactions, Los Angeles County Public Works, Los Angeles, CA
Dr. Struck is project manager of this effort to better understand and quantify the volumetric benefits of various types of green stormwater infrastructure to provide water supply, aquifer recharge, prevent saltwater intrusion, and improve stormwater quality or receiving systems. Teamed with the Department of Energy’s Lawrence Berkeley National Laboratory and partnering with the US Bureau of Reclamation and the US Geological Survey, this project is collecting data to support surface water and groundwater models to better quantify the benefits of infiltrating stormwater and developing integrated and secure sources of groundwater supply while improving the water quality of stormwater runoff.
B
each Cities Enhanced Watershed Management Planning and Safe, Clean, Water Application, City of Manhattan Beach, City of Hermosa Beach, City of Torrance, and the County of Los Angeles Department of Public Works, CA This project supports municipal stormwater compliance through capture and treatment of stormwater runoff that to enhance groundwater replenishment, protect local beaches, improve overall water quality, and reduce local flooding providing integrated, multi-beneficial outcomes. The project leverages existing flood control infrastructure with a retrofit to infiltrate 140 ac-ft per year of stormwater runoff supplementing groundwater supply in the shallower aquifer and providing preventing seawater intrusion. Dr. Struck is the project manager.
R
egional Bioretention Literature Review and Volume 3 Update, Mile High Flood District (Urban Drainage Flood Control District), Denver, CO Dr. Struck is assisting the MHFD by providing a literature review of bioretention design and construction information to provide additional understanding of various material and design aspects to improve the water quality performance and improve plant survivability. Following the literature review, Geosyntec assisted MHFD as a team member to Update Volume 3 - Chapter 4 (Post Construction SCMs) of the Urban Storm Drainage Criteria Manual. Geosyntec has participated in stakeholder meeting as well as developed additional information to support bioretention media selection as well as the development of specialized media to target specific pollutants.
3 rd Party Stormwater Program Audit, City of Austin, Austin, TX Dr. Struck was technical lead for this project which assessed over 30 years of SCM performance data to document whether the City of Austin was 1) reducing pollution load to receiving waters to the maximum extent practicable and 2) were they maintaining and increasing baseflows in waterways to the maximum extent Scott Struck, PhD
Principal
19 Years of Experience
10 Years with Geosyntec
P
roject Roles
Task 8 Infiltration Methods
Specialties
Stormwater and Watershed
Management
Tool Development and
Mode
ling of Stormwater
BMPs
Watershed Planning and
I
mplementation
Monitoring and Performance
of
Stormwater BMPs
Policy Development and
T
raining
Education
PhD, Water Resources
Management, Indiana
U
niversity, Bloomington, IN,
2003
MS, Water Resources
Engineering and
Mana
gement, Indiana
U
niversity, Bloomington, IN,
2001
MP
A, Env. Policy and
N
atural Resource Mgmt.,
Indiana University,
Bloomington, IN, 2001
BS, Zoology, University of
Washington, Seattle, WA,
1995
BA, Psychology, Universit
y
of
Washington, Seattle, WA,
1995
EXHIBIT 2
S
cott Struck, PhD
practicable. Geosyntec’s provided this 3rd party audit through collection of City stormwater monitoring data sets, reports, criteria and design manuals, and inspection and maintenance practices to evaluate how well the existing programs, projects, guidance documents and permitting processes met regulatory objectives and provided recommendations on how programs and processes might be improved.
G
reen Infrastructure Project Identification and Conceptual Design, City of Omaha, Omaha, NE
This project evaluated five City of Omaha watersheds to identify and develop integrated stormwater management infrastructure projects that would be included in the City’s Long-Term Control Plan Update. The project developed a multi- objective decision analysis (MODA) evaluation process that identified over 50 specific opportunities, impacting over 3,500 acres of runoff into the combined sewer system. These opportunities included public and private property and greening of City streets and management of runoff from limited access roadways. Five projects were selected based on volumetric and flow performance and cost effectiveness (i.e., 20- year life cycle cost/gallon of CSO volume reduced). Conceptual designs were developed to support design and next phases. The selected projects maximized initial investment made by the City by exploring right of way and other regional facilities located on public property. Dr. Struck was the project manager.
B
lacksnake Creek Wastewater/Stormwater Separation Improvements using Green Infrastructure and Real Time Management, City of St. Joseph, St. Joseph, MS
Geosyntec’s role in the stormwater separation diversion structure and channel improvements on Blacksnake Creek was to develop and design green infrastructure and real time control projects to support the diversion of stormwater (creek water), for the CSO control design storm event, from the Blacksnake Creek combined sewer system to a new stormwater conduit. Geosyntec was tasked with planning and developing conceptual (30%), draft (60%) and final designs (90%, 95%, and 100%) for several kinds of green infrastructure as a part of combined system separation. Tasks include screening and evaluation of potential locations, hydrologic and hydraulic modeling, site inspection and feasibility analyses, evaluation of Real Time Control Concepts at Potential Sites, and conceptual, draft final, and final designs. In addition, Dr. Struck is involved in conducting public meetings and workshops assisting project and City staff in understanding and promoting the implementation, operation, and maintenance the selected green infrastructure and real time G
reen Stormwater Infrastructure Joint Program Management Services, Seattle Public Utilities and King County- Wastewater Treatment Division, Seattle, WA
Seattle Public Utilities (SPU) and King County’s Wastewater Treatment Division (WTD) have implemented a green stormwater infrastructure program for the City of Seattle to reduce the volume of stormwater runoff and improve water quality. Dr. Struck was a part of a team that provided development of equivalency policies with state regulatory requirements, monitoring, modeling, operation and maintenance, and economic triple- bottom-line evaluation of programmatic elements.
C
olorado Regulation 85 Nutrient Data Gap Analysis, Colorado Stormwater Council and Urban Drainage Flood Control District, Denver, CO
For Municipal Separate Storm Sewer Systems and Colorado Discharge Permit System permittees, Regulation 85 requires public education and outreach on stormwater impacts associated with nutrients, pollution prevention/good housekeeping for municipal operations, and data collection regarding the approximate nitrogen and phosphorus contribution to state waters due to discharges from MS4s. The project determined whether adequate information exists to allow for determinations of representative nutrient estimates by statistically evaluating Front Range municipal data collected in the past. In this way, future data collection can be focused on areas that have a paucity of data to address the remaining information requirements under Regulation 85. Dr. Struck was project manager for Geosyntec.
S
tormwater Management Planning and Permitting Support, General Services Administration, Denver Federal Center, Lakewood, CO
Dr. Struck has provided permit and compliance assistance through development of the installation Stormwater Management Plan and assistance with EPA interviews and audits. Additional compliance assistance was delivered through review of the Draft MS4 permit as well as developing necessary facility education and workshop training.
Registration & Certifications
Professional Wetland
Scientist, Assoc. of Prof.
W
etland Scientists, 2006
(
No. 1655)
Institute for Sustainable
I
nfrastructure Certified
Envision Sustainability
Professional, 2017 (No.
23008)
EXHIBIT 2
S
cott Struck, PhD
Additional services were provided through facility inspection and monitoring of dry weather flows and modeling as a part of future facility master planning.
T
hird Fork Creek Watershed Planning and Design, Durham, NC Dr. Struck was task manager for a $1M+ planning and design project in Durham, NC. Dr. Struck led teams for included stream assessment, stormwater retrofit planning and design, LID implementation, and BMP maintenance to meet programmatic goals for Third Fork Creek.
P
ipers Creek Flow Control Plan, Seattle Public Utilities, Seattle, WA Dr. Struck initiated efforts to assess the data available for the hydrology model used in Pipers Creek analyses. He also was a part of developing a standardized data assessment process that included development of a data inventory, creation of a data management system for geospatial and other electronic data, review of available data, evaluation of suitability of data compared to data needs, and identification of important data gaps. Scott also contributed to developing data quality objectives and a data collection QAPP that complies with SPU’s QAPP guidelines.
C
omprehensive Load Reduction Program for Pollutant Load Reductions and Environmental Compliance , City and County of San Diego, San Diego, CA
To improve the efficiency of limited planning resources, and to take advantage of an extended 20- year wet weather compliance timeline, The San Diego NPDES Co-Permittees have chosen to address multiple pollutants of concern through a comprehensive load reduction program strategy. Dr. Struck provided review of approaches taken and draft documents submitted for the evaluation and prioritization of regional and distributed stormwater management controls to meet load reduction requirements for multiple pollutant impairments within the five City of San Diego watersheds, as well as the San Luis Rey and Upper San Diego Rivers.
O
range County Transportation Authority Measure M2 Environmental Cleanup Program Tier 2 Grant Evaluation Assistance, County of Orange, Santa Ana, CA
Dr. Struck assisted a team in applying an integrated model to identify and categorize strategically effective areas for prioritizing best locations for water quality mitigation. He led the team in developing an evaluation methodology for determining cost-effective ranking of stormwater improvement plan submittals based on criteria developed through a technical advisory committee. The methodology ranked projects to determine award allocations to assist in implementation of the project with the greatest cost-benefit efficiency for stormwater improvements.
S
tormwater Strategic Planning, City of San Diego, CA
In order to ensure that stormwater management activities are sufficiently and cost -effectively contributing to an overall improvement water quality throughout the City, Dr. Struck assisted with the City’s stormwater strategic planning section (now within the Streets Division) to establish a systematic method for evaluation of BMP costs and impacts. He developed methodologies for collecting and organizing key information for programmatic evaluations and structural BMP performance for permit compliance within the City’s watersheds.
L
os Angeles County Watershed Planning, Los Angeles, CA
This project provided watershed planning assistance to prioritize and cost optimize implementation of stormwater controls to meet regulatory requirements. Dr. Struck has been involved with selection, design, placement, and cost optimization of runoff management and source control practices (LID and Green Infrastructure techniques) providing decision support for watershed planning and capital improvement projects in the unincorporated areas of Los Angeles County. Dr. Struck also assisted Los Angeles County engineers in the development of cost benefits analyses tools to assist in BMP selection.
O
tay Mesa Engineering and Drainage Reports Review, City of San Diego, San Diego, CA Dr. Struck managed this project which provided review of existing stormwater management plans, current land use and drainage patterns based on GIS data, and other relevant information to evaluate recommended improvements in the drainage plans of the Otay Mesa Area of San Diego. The project provided detailed review of previously completed planning and engineering reports and local and county storm water regulations to develop recommendations for the placement and design of storm water-management facilities and restoration projects that may be required to mitigate impacts to sensitive areas (e.g., vernal pools) and manage stormwater runoff.
EXHIBIT 2
Career Summary
Mason Albrecht has 14 years of experience implementing projects for the environmental remediation and water resources sectors. Mason has broad based project experience in site investigation, remediation, treatment system design, civil design, construction management, and operation and maintenance (O&M).
Relevant Project Experience
Engineering Consulting and Operation and Maintenance for CERCLA site, Aerojet Rocketdyne, Rancho Cordova, CA
Mason currently serves as the task manager and lead project engineer for engineering, O&M, and permit compliance support for several groundwater extraction and treatment (GET) systems that address a regional perchlorate, N- Nitrosodimethylamine (NDMA), and a volatile organic compounds (VOC) plume associated with former rocket manufacturing operations. He and the team developed O&M manuals for the GET systems with a detailed matrix of GET system parts and equipment inventory; description of component criticality and failure analysis; and maintenance checklists and procedures. The O&M manuals are a practical maintenance tool to be used by GET system operators. The purpose of the revised O&M protocols is to improve operational efficiency, reduce the risk of release of contaminants to the environment, and reduce non-routine O&M costs. Mason’s team has completed several engineering evaluations for the GET systems to improve treatment effectiveness and reduce O&M costs. For example, the team performed evaluations of several alternatives for water treatment and operations modifications to manage perchlorate in groundwater at two of the GET systems. The team also evaluated alternatives for management of biofouling in GET system extraction wells to reduce fouling of influent bag filters and O&M costs. Mason manages a complex national pollutant discharge elimination system (NPDES) discharge permit that incorporates discharge of treated water from 10 different GET systems. His support engineering staff is responsible for coordinating monthly flow monitoring, treatment system sampling, and reporting activities. This requires extensive experience with acute and chronic aquatic toxicity monitoring and toxicity reduction evaluations. The engineering staff has been able to successfully manage and coordinate several different team members while complying with the NPDES requirements, including GET system operators, sampling subcontractors, couriers, laboratories, and database managers.
R
emedial Action Evaluation, Optimization, and Project Management, Baldwin Park Operable Unit (BPOU) of the San Gabriel Valley Superfund Sites Mason serves as the project manager and technical liaison for this complex ongoing Superfund project since 2013. The remedial action consists of groundwater extraction and treatment, and delivery of treated groundwater, meeting drinking water standards, to the distribution system. The overall project objectives include hydraulic capture of site chemicals of concern (COC) including chlorinated VOCs, perchlorate, NDMA, and 1,4-dioxane; and chemical mass removal in groundwater. Mason’s team performs plume mapping and water quality trend evaluation using Earth Volumetric Studio (EVS®), statistical analysis of chemical concentration trends in groundwater, groundwater modeling using FeFlow, and preparation of the annual performance evaluation report. Mason also oversees the O&M along with monitoring and reporting associated with the discharge of wastewater produced as part of various water treatment operations at the potable water production plants within the BPOU. This involves coordination with plant operators on production schedules and operations, and coordination with the sanitation district for permit compliance.
Mason Albrecht, PE
Senior Engineer
14 Years of Experience
8 Years with Geosyntec
P
roject Roles
Task 9
Specialties
Investigation and
R
emediation
Vapor Intrusion Assessment
and Mitigation
Stormwater Compliance
Landfill Operations
Water/Wastewater
Education
MS, Civil and Environmental
Engineering, Stanford
U
niversity, 2006
BS, Civil and Environmental
Engineering, University of
California, Davis, 2004
Registration & Certifications
California Professional
Engineer No. 78130
40-Hour OSHA
HAZWOPER 29 CFR
1910
.120(e)(3) In Training
8-Hour OSHA Supervisor
Training
EXHIBIT 2
M
ason Albrecht, PE
C
orrective Active Management Unit and Stabilization for Lead Waste, Former Bryte Landfill, West Sacramento, C A Mason provided remedial action design, planning, and engineering support on this project involving waste removal, treatment and grading. The former landfill was historically used as a burn dump and is located adjacent to the existing Sacramento Bypass, which will be expanded as part of a larger flood control project for the City of Sacramento and surrounding areas. Waste in the former landfill was relocated to a corrective action management unit (CAMU) to accommodate the bypass expansion and portions of the waste with lead exceeding state and federal leaching criteria were treated with a stabilizing reagent prior to placement in the CAMU. Mason prepared the Remedial Design and Implementation Plan (RDIP), coordinated site civil design in AutoCAD Civil3D, prepared design plans and specifications, and develops cost estimates for bid procurement while also coordinating waste treatment pilot testing activities and evaluation and selection of lead stabilization reagent.
C
alifornia Low Threat UST Case Closure Sites, Multiple Caltrans Sites Mason provided engineering support for the evaluation of site closure for multiple Caltrans properties under the California Low-Threat UST Case Closure Policy (LTCP). As part of these evaluations, Mason updated conceptual site models (CSM) and compared current site conditions to LTCP requirements for closure. Based on the closure evaluations, he either assisted with preparing a formal request for closure or a work plan for additional site investigation/remediation.
Mason provided engineering support for preparation of work plans for pilot testing innovative remedial technologies at multiple Caltrans sites. Geosyntec is evaluating innovative technologies to help progress Caltrans sites to closure and identify those effective technologies that can be applied in full scale at similar Caltrans sites statewide.
S
oil Vapor Extraction (SVE) Systems for Chlorinated Volatile Organic Compounds (CVOC), Sacramento, CA Mason is the lead engineer for the design, installation, and O&M of SVE systems for the remediation of CVOCs in vadose zone soils at two former dry cleaner sites in Sacramento. Design responsibilities include analysis of pilot test results, developing system design parameters, well spacing and construction, system curve development, equipment selection, and plans and specifications. The pilot testing results were rigorously evaluated, compared to SVE guidance documents, and incorporated into the full-scale design. Mason’s team obtained the necessary permits from the Sacramento Metropolitan Air Quality Management District for discharge of treated vapors from the SVE system. Source testing for the permit involved analysis of vapor samples and monitoring of treatment system performance to demonstrate compliance with permitted CVOCs emissions limits. Samples of soil vapor processed through the SVE treatment system are routinely collected to evaluate CVOC mass removal and compliance with the air permit. Routine O&M activities include measurements of system process flow, vacuum, temperature, relative humidity, air permit compliance monitoring (above), inspection of mechanical equipment (e.g., positive displacement blower, motors, heat exchanger, condensate water transfer pump), and adjusting flow rates from extraction wells to optimize CVOC mass removal.
Remedial Cap for Pesticides and Metals Impacted Soils, Former San Joaquin Drum Company Site, DTSC, Bakersfield, CA
Mason currently supports the development and implementation planning for this former waste drum storage facility site managed by the California Department of Toxic Substances Control (DTSC). Mason prepared a Remedial Action Work Plan (RAW) consistent with the National Contingency Plan (NCP) and the Comprehensive Environmental Response Compensation and Liability Act (CERCLA), and the RDIP. A low permeability modified asphalt cap was selected for groundwater and human health protection from shallow soils impacted by pesticides, semi -volatile organic compounds (SVOC), and metals. The cap remedy will contain stormwater management measures that includes concrete drainage ditches, drop inlets, drain piping, and a retention basin, and involves hydrologic and hydraulic analysis per local standards. Soil and concrete sampling were performed at the site to characterize contamination in this media prior to implementation of the RAW and for the evaluation of disposal options. The analyses included the federal toxicity characteristic leaching procedure (TCLP) and the California Waste Extraction Test (WET) to evaluate the leachability and hazardous waste classification.
EXHIBIT 2