Resolution No.
STOCKTON CITY COUNCIL
___________
___________________________________________________________ RESOL
UTION ADOPTING THE REVISED EASTERN SAN JOAQUIN
GROUNDWATER SUBBASIN GROUNDWATER SUSTAINABILITY PLAN
RESOURCES
In 2014 , t
he Governor signed legislation creating the Sustainable Groundwater Management Act (SGMA) “to provide local groundwater sustainability agencies with the authority and technical and financial assistance necessary to sustainably manage groundwater” (Wat. Code, § 10720, (d)); and
The City o
f Stockton is a member of the Eastern San Joaquin Groundwater Authority (GWA) , formed to develop a groundwater sustainability plan (G SP) and coordinate sustainable groundwater management in the Eastern San Joaquin Subbasin (Subbasin). Wat. Code, section 10723.6(i) of SB 1168 states that “the following agencies created by statute to manage groundwater shall be deemed the exclusive local agencies within their respective statutory boundaries with powers to become a Groundwater Sustainability Agency (GSA)”; and
The SGM
A requires sustainable management through the development of GSPs, which can be a single plan developed by one or more GSA or multiple coordinate plans within a basin or subbasin (Wat. Code, § 10727); and
The GWA sub
mitted the GSP to the D epartment of Water Resources (D WR) on January 29, 2020; and
The DWR r
eviewed the GSP and by letter dated January 28, 2022 deemed it incomplete, triggering a 180-day timeline for the GWA to prepare an amended GSP and submit the document to DWR by July 27, 2022; and
On April
15, 2022, pursuant to California Water Code Section 10728.4, the GWA, on behalf of its member agencies, gave notice that its member GSAs intend to adopt the Eastern San Joaquin Subbasin Groundwater Sustainability Plan (GSP), and pursuant to Water Code 10728.4, no sooner than 90 days from the date of the notice, each of the member GSAs are to hold a public hearing and consider adopting the GSP; and Staff
recommends that the City Council adopt the R evised GSP for the Subbasin and authorize the GWA to take actions as may be reasonably necessary to submit the Revised GSP to the DWR; now, therefore,
BE I
T RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:
DRAFT
DRAFT PROPOSED RESOLUTION
ATTACHMENT E
1. Appr
ove and adopt the Re vised Groundwater Sustainability Plan for the Eastern San Joaquin Subbasin and Appendices, a copy of which is attached as Exhibit 1 and incorporated by this reference.
2. Aut
horize the Eastern San Joaquin Groundwater Authority, its consultants, and the Plan Manager to take such other actions as may be reasonably necessary to submit the Revised Groundwater Sustainability Plan to the Department of Water Resources by July 27, 2022 and implement the plan.
3. Aut
horize the Municipal Utilities Department to work in collaboration with other local agencies to implement the projects and programs developed in the Revised Groundwater Sustainability Plan in compliance with the Sustainable Groundwater Management Act.
4. The Ci
ty Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.
PASSED,
APPROVED, and ADOPTED July 26, 2022 .
KE VIN J. LINCOLN II
Mayor of the City of Stockton
ATTE
ST:
ELIZA R. GARZA, CMC
City Clerk of the City of Stockton