RWCF Modifications ProjectEast Bank OutfallConstruction Change Order (CCO)-008 Council Water Committee
October 13, 2022
Agenda Item No. 3.3

RWCF Modifications Project
Original Contract Approach
Use existing pipelines to convey to existing outfall on west bank Allowed for CEQA and permitting to proceed to meet schedule Install temporary pipelines to serve until new outfall permitted and constructed Temporary solution
New outfall permitting to be completed within 5 years
Purpose of East Bank Outfall CCO-008
Consolidate operations on Main Plant (east side of River) Avoid cost of temporary pipelines and structures ~$1M
Allow gravity discharge >90% of time
Comply with NPDES Discharge Permit

East Bank Outfall Construction

Work No Longer Needed (Temporary)

East Bank Outfall CCO-008
Evaluation
Located formerly-used outfall pipe through levee (circa 1970s) Considered its use for east bank outfall
Determined acceptable for EBO
Updated Design
Pipe suitable for reuse with lining
Modify Final Effluent Pump Station (FEPS)
Reroute effluent pipeline to existing outfall pipe
Extend existing outfall pipe out and down into river

East Bank Outfall CCO-008
Permitting
Central Valley Flood Protection Board (Flood Board) - complete Reclamation District 404 - in progress
Corp of Engineers (COE) - in progress
Endangered Species Act (ESA): National Marine Fisheries Service (NMFS), Biological Assessment & Biological Opinion CEQA-complete

East Bank Outfall CCO-008
Remove:

Construction of pipeline on the west bank of the river
Modifications to the weir control box on the west bank of the river Construction of the connection to the existing pipeline under the railroad Construction of a new effluent control box at the tertiary plant Modify the Final Effluent Pump Station to accommodate gravity flow to the east bank of the river

East Bank Outfall CCO-008
Add:

Construction of effluent pipeline to the east bank of the river Reinstatement and upgrade of the existing pipe under the east bank levee Demolition of the existing apron structure on the east bank of the river Construction of a new outfall outlet on the east bank of the river

East Bank Outfall CCO-008
Findings (3.68.070):

Construction interface
Avoids $1M of temporary work
Early abandonment of Tertiary Plan
Assure compliance with June 1, 2024, permit deadline

East Bank Outfall CCO-008
Summary of Requested Actions
Approve findings pursuant to SMC 3.68.070
Approve CCO-008 for $6.8M
Incorporate CCO-001 through CCO-007
Administratively approved
Increase Phase 2B contract amount to $206,789,950.31
CCO-001 through CCO-008
Authorize City Manager to execute CCO-008
Authorize City Manager to execute payments for direct mitigation Not to exceed $150,000

Recommendation
Forward item to the City Council for consideration and approval 11