Resolution No.
STOCKTON CITY COUNCIL
RESOLUTION APPROVING THE NOTICE OF EXEMPTION NO. NOE10-22, APPROVING THE PLANS AND SPECIFICATIONS, APPROPRIATING FUNDING, AND AWARDING A CONSTRUCTION CONTRACT FOR THE HSIP 9 - INSTALL SIDEWALK AND MEDIAN FENCING ALONG DR. MARTIN LUTHER KING JR. BOULEVARD, PROJECT NO. WT19003/FEDERAL PROJECT NO. HSIPL-5008(186) On November 3, 2022, the City Clerk of the City of Stockton opened, examined, and publicly declared the sealed proposals or bids offered for the HSIP 9 - Install Sidewalk and Median Fencing Along Dr. Martin Luther King Jr. Boulevard, Project No. WT19003/Federal Project No. HSIPL-5008(186); and The installation of median fencing along Dr. Martin Luther King Jr. Boulevard will improve pedestrian safety by preventing jay walking and unsafe mid-block crossing. The project will include adding guardrail, signage, pavement markings, safety lighting, and replacing curb ramps; and United Pavement Maintenance, Inc. is the lowest responsible bidder in the amount of $538,159.85, and its bid is regular in all respects; and Caltrans National Environmental Policy Act determination was received on October 19, 2018. The State determined that the project is a Categorical Exclusion under 23 CFR 771.117(c): activity (c)(26). Similarly, the project is in conformance with the City’s General Plan, pursuant to California Government Code, section 65402; and The project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA) as specified under section 15301(a) of the CEQA Guidelines, because this is a discretionary project under the City’s jurisdiction and qualifies as a project which has been determined to not have a significant effect on the environment; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:
The City Council approves the filing of Notice of Exemption No. NOE10-22 under the CEQA for the HSIP 9 - Install Sidewalk and Median Fencing Along Dr. Martin Luther King Jr. Boulevard, Project No. WT19003 (formerly PW1903)/Federal Project No. HSIPL-5008(186), a copy of which is attached as Exhibit 1 and incorporated by this reference. //
//
The City Council approves the plans and specifications for the HSIP 9 - Install Sidewalk and Median Fencing Along Dr. Martin Luther King Jr. Boulevard, Project No. WT19003 (formerly PW1903)/Federal Project No. HSIPL-5008(186).
The City Council approves the appropriation of funds in the amount of $11,000.00 from the Measure K Maintenance Fund Balance to the HSIP 9 - Install Sidewalk and Median Fencing Along Dr. Martin Luther King Jr. Boulevard, Project No. WT19003 (formerly PW1903)/Federal Project No. HSIPL-5008(186).
The City Council approves the appropriation of funds in the amount of $97,470.00 from the Highway Safety Improvement Program to the HSIP 9 - Install Sidewalk and Median Fencing Along Dr. Martin Luther King Jr. Boulevard, Project No. WT19003 (formerly PW1903)/Federal Project No. HSIPL-5008(186).
The City Council awards a Construction Contract between the City of Stockton and United Pavement Maintenance, Inc. in the amount of $538,159.85, and the City Manager is authorized and directed to execute same, a copy of which is attached as Exhibit 2 and incorporated by this reference.
The City Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.
PASSED, APPROVED, and ADOPTED March 21, 2023 .
KEVIN J. LINCOLN II
Mayor of the City of Stockton
ATTEST:
ELIZA R. GARZA, CMC
City Clerk of the City of Stockton