Resolution No.

STOCKTON CITY COUNCIL
RESOLUTION APPROVING THE NOTICE OF EXEMPTION NO. NOE36-22, APPROVING THE PLANS AND SPECIFICATIONS, AND AWARDING A CONSTRUCTION CONTRACT FOR THE WEBER POINT EVENTS CENTER SHADE STRUCTURE REHABILITATION – PHASE 2, PROJECT NO. WP22033 On August 31, 2023, the City Clerk of the City of Stockton opened, examined, and publicly declared the sealed proposals or bids offered for the Weber Point Events Center Shade Structure Rehabilitation – Phase 2, Project No. WP22033; and The project will replace the Weber Point Events Center shade structure, including the worn-out fabric membrane, “cat-eye” cables, small turnbuckles, aluminum clamp bars, and other miscellaneous hardware; and McFadden Construction, Inc. is the lowest responsive bidder, in the amount of $798,910, and its bid is regular and responsive in all respects; and The project is categorically exempt from the requirements of the California Environmental Quality Act (CEQA) as specified under section 15301(c) of the CEQA Guidelines, because this is a discretionary project under the City’s jurisdiction and qualifies as a project which has been determined to not have a significant effect on the environment; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:

1. The City Council approves the filing of Notice of Exemption No. NOE36-22 under the CEQA for the Weber Point Events Center Shade Structure Rehabilitation – Phase 2, Project No. WP22033, a copy of which is attached as Exhibit 1 and incorporated by this reference.

2. The City Council approves the plans and specifications for the Weber Point Events Center Shade Structure Rehabilitation – Phase 2, Project No. WP22033.

3. The City Council awards a Construction Contract between the City of Stockton and McFadden Construction, Inc., in the amount of $798,910, and the City Manager is authorized and directed to execute same, a copy of which is attached as Exhibit 2 and incorporated by this reference. //
//
//
//
//
//

4. The City Manager is hereby authorized to take whatever actions are appropriate and necessary to carry out the purpose and intent of this Resolution.

PASSED, APPROVED, and ADOPTED November 14, 2023 .
____________________________
KEVIN J. LINCOLN, II
Mayor of the City of Stockton