NEW CITY HALL RENOVATIONS AND RELOCATION PROJECTPublic Works Department City Council MeetingDecember 12, 2023Agenda Item 15.3 PROJECT LOCATIONNew City Hall Renovations and Relocation Project PROJECT INFORMATIONNew City Hall Renovations and Relocation ProjectExisting Site: 4.83-acres with two buildings501 W. Weber – 5-Story building (58,929 sf)509 W. Weber – 5-Story building over basement (70,690 sf)Improvements: Tenant, onsite & parking lot across street2018-2021 – Space planning, design, construction plansIndigo Hammond + Playle ArchitectsNovember 2021 – Approve Construction Management ContractGriffin StructuresMay 2022 – Award Construction Contract Roebbelen Contracting, Inc. Consolidation of City Departments & ServicesMayor & CouncilCity ManagerCity AttorneyCity ClerkAdministrative ServicesCommunity DevelopmentEconomic DevelopmentHuman ResourcesInformation TechnologyFire AdministrationPublic Works PROJECT GOALNew City Hall Renovations and Relocation Project CONSTRUCTION PROGRESS – 1st Floor, Building No. 2New City Hall Renovations and Relocation Project Administrative Services Department – Revenue Counter
DESIGN ELEMENTS New City Hall Renovations and Relocation Project Fire Prevention / Administrative Services Department - Counter DESIGN ELEMENTSNew City Hall Renovations and Relocation Project City Council Chambers
DESIGN ELEMENTSNew City Hall Renovations and Relocation Project City Manager / Mayor / Council Office - Lobby
CONSTRUCTION PROGRESS – 4thFloor, Building No. 2New City Hall Renovations and Relocation Project Economic Development Department - Lobby
CONSTRUCTION PROGRESS – 4thFloor, Building No. 2New City Hall Renovations and Relocation Project Economic Development Department – North Side Corridor
New City Hall Renovations: Contract is approximately 60% complete.New Parking Lot across from New City Hall: Looking to advertise in Summer 2024.New City Hall and Parking Lot Construction: Complete Spring 2025. Phased department relocations will occur between Fall 2024 - Summer 2025.
PROJECT STATUS & NEXT STEPSNew City Hall Renovations and Relocation Project Contract modifications are needed to re-set the administrative authority, providing the City Manager the ability to approve future contract changes or amendments. The recommended actions do not increase project budget.Contract Change Order No. 7 with Roebbelen Contracting, Inc. – basement waterproofing Amendment No. 7 with Indigo, Hammond + Playle Architects, LLP – continue to respond to contractor inquiries and other design changes Amendment No. 2 with Griffin Structures, Inc. for additional construction management services PROJECT STATUS & NEXT STEPSNew City Hall Renovations and Relocation Project It is recommended that the City Council adopt a resolution authorizing the City Manager to:Execute Contract Change Order No. 7 to the Construction Contract with Roebbelen Contracting, Inc. in the amount of $93,261.41 Execute Amendment No. 7 to the Standard Agreement with Indigo, Hammond + Playle Architects, LLP in the amount of $820,000 for design construction support servicesExecute Amendment No. 2 to the Standard Agreement with Griffin Structures, Inc. in the amount of $288,464 for construction management services RECOMMENDATIONNew City Hall Renovations and Relocation Project Questions?