Resolution No.
STOCKTON CITY COUNCIL
RESOLUTION APPROPRIATING FUNDING AND APPROVING CONTRACT CHANGE ORDER NO. 5 FOR THE NORTHEAST STOCKTON LIBRARY AND COMMUNITY CENTER, PROJECT NO. CL17024 On December 15, 2020, by Resolution No. 2020-12-15-1404, Council awarded a Construction Contract, in the amount of $14,450,556.00, to Patriot Contracting, Inc. of Gardena, CA, for construction of the Northeast Stockton Library and Community Center, Project No. CL17024 (formerly PW1724); and Construction Contract Change Order (CCO) Nos. 1-4, in the total amount of $405,035.67, were approved by the City Manager under the administrative change order authority allowed under the original contract; and Appropriation of funding is needed to fund all other construction related costs to complete the project; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:
The City Council approves the appropriation of funds in the amount of $13,500,000.00 from the Measure M Strong Communities Fund Balance to the Northeast Stockton Library and Community Center, Project No. CL17024.
The City Council authorizes Construction CCO No. 5 in the amount of $9,717,288.14 with Patriot Contracting, Inc., Resumption Agreement, for the construction of the Northeast Stockton Library and Community Center, Project No. CL17024, a copy of which is attached hereto as Exhibit 1 and incorporated by this reference.
The City Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.
PASSED, APPROVED, and ADOPTED November 12, 2024 .