PERSHING AVENUE TRAFFIC SAFETY UPDATE
Public Works DepartmentCity Council MeetingApril 29, 2025Council Agenda Item 15.3
Project LocationPershing Avenue from Brookside Road to Fremont Street
Complete StreetImplement a Road Diet to Reduce SpeedingCreate Safe Pedestrian ConnectionsCreate Protected Bicycle LanesPedestrian Improvements with Landscape
Complete Street – Road Diet
BeforeAfter
Areas of ConcernPershing Avenue Off-Ramp Smith Canal and Calaveras River bridge structuresCalaveras River Trail AccessesUniversity of the PacificStagg High SchoolPacific Law Academy High SchoolKohl ElementaryWalton Special Center SchoolVictory ParkHaggin MuseumStockton Fire Station 6
Pershing Avenue -Existing ConditionsStreet Classification: ArterialFour-Lane Roadway with Left Turn PocketsPosted Speed Limit: 35 MPH north of Calaveras River and 30 MPH south of Calaveras RiverTraffic Volume Flow: 13,169 –30,386 vehicles per dayPeak Hour Traffic: 8 AM & 4 PMTruck Route: From Willow Street to Fremont Street7 Existing Signals within Project Limits 35 MPH
TRUCK ROUTE30 MPH
Efforts to Date and Ongoing ProjectsCoordination with Pershing CommunityUpsized and Installed Additional Speed Limit SignsInstalled 1 Radar Speed Feedback Sign –Magnolia StreetSignal Retiming to Accommodate Pedestrian Crossing Restriped Lane Lines to Enhance VisibilityRestriped Crosswalks at Acacia and Harding IntersectionsPolice Department Speed EnforcementFacilitated Multiple Meetings with Caltrans to Reduce Speed at the Off-RampSecured Funding for the HAWK Project South Stockton Pedestrian HAWK ImprovementsNorth Pershing Avenue Safety EnhancementsAlpine Pershing Mendocino Bicycle-Pedestrian ConnectivityAquatic Facilities Renovations –Victory Park Pool North Pershing Avenue Safety Enhancements
I-5 Stockton Channel Viaduct Bridge Improvements Project (Caltrans) TimelineCommunity reached out to Public Works in 2021Advocated in 2024 at the One Voice D.C. Trip for funds for safety effortsIn 2025, City anticipates selection for federal Community Project Funding (earmark) award from Rep. Josh HarderAnticipate contract in May 2025 for Pershing Avenue Traffic Safety and Road Diet StudyAnticipate funding in 2025 - Pershing Avenue Road Safety Improvement and Enhancement Project (PARSIEP) Potential Grant Funding Programs for Future PhasesHighway Safety Improvement Program (HSIP)Congestion Mitigation and Air Quality (CMAQ)Active Transportation Program (ATP)Safe Streets and Roads for All (SS4A)
QUESTIONS?