SILVER LAKE
CAMPGROUNDS
FACILITY ASSESSMENT
City Council Meeting
Agenda Item 16.4
November 4, 2025
BACKGROUND
Facility Condition Assessment conducted
by Kitchell in 2024.
Scope: Identify maintenance, repair, and
modernization priorities with cost
estimates.
COST
ESTIMATES:
CAPITAL RENEWAL
• The sum of the
capital improvement
costs for assessed
facilities.
• $5,846,220
COST
ESTIMATES:
REPLACEMENT
• The current
replacement cost of
assessed facilities.
• $22,323,000
ASSESSMENT RECOMMENDATIONS
1. Pursue capital renewal and reopening by initiating
necessary repairs.
2. Pursue replacement of facilities.
3. Cancel the Special Use Permit and return the
camp to the U.S. Forest Service.