Municipal Utilities Department Water DivisionCapital Projects Update
COUNCIL WATER COMMITTEE
Item 26-0021
January 8, 2026
Current Projects
Groundwater Recharge Project (Slide 4)
Automated Metering Infrastructure
Northeast Reservoir
Cathodic Protection at 14-mile and Weston Ranch Reservoirs Emergency Standby Generators (Slide 8)
South Stockton System Wells 3 and 9.
Future Projects
Delta Water Treatment Plant Campus Improvements
Well 30 upgrades to remove Trichloro propane (1, 2, 3, -TCP) Well 33 Site Development
Well SSS10 – Purchase Land
Emergency Standby Generators Weston Ranch Reservoir
SITE PLAN – Groundwater Recharge Project
Earthwork nearly complete
Ponds, Islands, and Levees substantially complete
Finalizing the designs for the piping infrastructure, roads, fencing, and visitor center.
Project delayed until spring 2026. (rainy season)
Progress to Date – Groundwater Recharge Project
Visitor Center– Groundwater Recharge Project
Public Visitor Center
Educational Signage
Small Park
Walking trail
Wildlife habitat (Bird Islands)
Visitor Center– Groundwater Recharge Project
Currently 0 Standby Emergency Generators on City Infrastructure in South Stockton Water System Protects up to 6 million gallons per day of source water Project includes Generators and Automatic Transfer Switches Expected completion March 2026
Wells SSS3 and SSS9 – Emergency Standby Generators
QUESTIONS?