CITY OF STOCKTON

PROFESSIONAL SERVICES CONTRACT AMENDMENT
This Amendment Number 11 to the above referenced Professional Services Contract, is entered into on _________________________, between the City of Stockton (“City”) and GRIFFIN STRUCTURES, INC. (“Consultant”) for the CONSTRUCTION MANAGEMENT FOR THE NEW CITY HALL RENOVATIONS AND RELOCATION, PROJECT NO. E016015.

RECITALS
Section 11, Contract Amendments, states that the Professional Services Contract may be amended only by written instrument signed by Consultant and City; and
The City needs to increase the Compensation, not to exceed amount in Section 2 of the Professional Services Contract and Exhibit B, by $320,989 to pay for the Consultant for additional services; and Now therefore, the City and the Consultant mutually agree as follows:

1. The maximum not to exceed amount to be paid to the Con sultant, including if authorized, reimbursement of expenses, in Section 2 of the Professional Services Contract and Exhibit B, will now read as follows:
“The m
aximum not to exceed amount in Section 2 of the Professional Services Contract and Exhibit B , is amended to $3,597,748.”

2. City shall pay Consultant for additional changes in scope outlined in Exhibit A.

All other terms and conditions of the Professional Services Contract shall remain unchanged and remain in full force and effect unless modified by a written amendment signed by both parties.

IN WI
TNESS WHEREOF, the authorized parties have executed this Contract.

CONSULTANT
_______________
__________________________________________________________________ _ _ Consultant’s Name (if other than an individual, state whether a corporation, partnership, etc.) _______________
________________________________________________________________ _____ Authorized Signature Date
_______________
______________________________________________________________ _______ Printed Name and Title of Person Signing
_______________
_____________________________________________________________ _______ Address

CITY OF STOCKTON
_______________
_______________________________________________________ ______________ Johnny Ford, City Manager Date
ATTEST:

_______________
________________________________________________________________ _____ Katherine Roland, CMC, CPMC, City Clerk

APPROVED AS T
O FORM:

Marci A. Arrendono, City Attorney
BY:

Contract
Number:

Amendment
Number:
422000450 11

GRIFFIN STRUCTURES, INC.

ATTACHMENT C

Page 1 of 4 ends

GRIFFIN STRUCTURES FEE PROPOSAL – AMENDMENT 11
Stockton City Hall Project
March 27, 2026
Griffin St ruc
tures’ Fee Proposal is based on all reasonable costs necessary to perform Construction Management services for the Stockton City Hall project. For these requisite services Griffin Structures proposes the following Time and Materials Fee:

Construction Management: $ 106,920
Scheduling $ 0
Special Inspection & Testing $ 213,000
Submittal Exchange Extensions $ 2,250
Insurance Expenses: $ 1,069
Total $ 320,989
All proposed hourly rates are fully burdened and include overhead, profit, taxes, and benefits. The hours identified for each individual employee and task are estimates only and are not to be construed as not to exceed hours for any individual task, phase, or time period. We reserve the right to reallocate hours between staff members and tasks, in consultation with City staff, in order to accomplish the overall objectives and requirements of the project.

SCOPE OF SERVICES
This amendment covers a portion of services based on an anticipated project completion in June of 2026.

The requested additional services fee is estimated to cover the Griffin Structures team through June 2026 Due to changes in scope and unforeseen circumstances, the project schedule has extended.

Due to the added scope and the contractor’s prosecutio n of work, additional Special Inspections and Testing are also required for a total of $213,000 including inspections already completed.

APPROACH TO STAFFING & PROJECT TEAM
To bring the highest level of efficiency and value to the City, Griffin Structures has assembled following team:

Robert Godrey will continue to support the project as Project Executive.

Andrew Simmons will remain as the on-site Construction Manager.

Jim Favour will continue as a Construction Manager on a part-time basis.

EXHIBIT A

ATTACHMENT C

Page 2 of 4 ends

QUALI

FICATIONS & EXCLUSIONS

1. H ourly rates are valid through December 31st, 2026 and will escalate by CPI annually thereafter.

2. Insura nc
e costs are included as a reimbursable expense and will be billed monthly at the rate of $10 per $1,000.

3. On-site trailer rental, furniture, utilities, and sanitary facilities for our field staff (Project Management team) are excluded. We assume that offices will be provided as part of the construction site trailer(s) being provided by the City or its contractor.

4. Costs for all permits required for the project are excluded. It is assumed that the City will pay for all permitting fees, assessments, easements, school fees, and other agency or governmental fees or costs to support the design and construction the project. We have not included any permit related fees within our fee proposal. Permits will be pulled by others.

5. Costs for construction staking, environmental and hazardous materials surveys, and all environmental and hazardous materials transportation and remediation costs are excluded.

6. Software licenses or user fees and all software training costs for specific project management software being required by either the City or their contractor(s) are excluded.

7. Cost of bulk blueprinting for plans and specifications for use by the contractors and subcontractors is excluded. Funds included in reimbursable expenses are for Griffin printing costs alone.

8. Independent or third-party testing companies such as Roofing, Peer Reviews, LEED, or other specialized third-party oversight services other than those listed herein are excluded.

9. No FF&E or OS&E procurement is included in this proposal.

10. Construction Site Security is excluded.

11. This proposal does not include a formal independent Inspector of Record (IOR); it is assumed that any Building Department inspections will be performed by the City’s Building Department inspections staff. It does include an Add Alternate for a Quality Assurance Inspector.

12. Construction Manager will review all RFI’s, Submittals, and Substitutions only for completeness.

Approvals shall be executed by the architect of record.

13. Construction Cost Estimates, when provided, are based on standard industry practice, professional experience, and knowledge of market conditions. Griffin has no control over material and labor costs, contractor’s methods of establishing prices or the market and bidding conditions at the time of bid. Therefore, Griffin does not guarantee that bids received will not vary from the cost estimate provided and Griffin is not liable for any costs, liabilities, or damages incurred by the City arising from Griffin’s opinion of cost, the actual project cost to the City, delays caused by events outside the control of Griffin, or any labor or material cost increases.

14. Griffin is not responsible for, and the City will hold Griffin harmless from, any schedule delays and/or any losses, damages, or liabilities resulting therefrom that are caused by (1) events or

EXHIBIT A

ATTACHMENT C

Page 3 of 4 ends

condit
ions that are outside of Griffin’s control or (2) the acts or omissions of parties for whom Griffin is
not legally liable (collectively, “Non-Consultant Delays”). The schedule for completion will be extended for any Non-Consultant Delays. If Griffin incurs additional costs or expenses due to Non-Consultant Delays, then Griffin’s fee compensation will be equitably adjusted to cover such additional costs or expenses.

15. For document tracking control, Griffin has included the use of Autodesk for managing construction documentation, and based the hours allocated in this proposal accordingly. The cost of this system is included here as a reimbursable expense.

16. FF&E services are included and management and oversight of the effort to be performed by the selected design team professionals.

17. Move management services are included as oversight only. Griffin will nonetheless oversee the solicitation, negotiation, and oversight of the move management consultant, but will not be providing the service itself.

18. Commissioning requirements are understood as per California Building Cod / Cal Green (Title 24) only. LEED Commissioning is excluded.

EXHIBIT A

ATTACHMENT C

Page 4 of 4 ends