Campus Improvements Project
Contract approved – design meetings
Programming needs, staff space, workflow
Anticipate providing an update when the design reaches 30%
Groundwater Recharge Project
The contractor is installing all underground piping and conduits Drywell construction started in August 2026
Total of 6 drywells, 30 feet deep
Civil Design 100%, Electrical 90%, Park and Visitor Center 90% Working on the last change order for the project, expected to bring to the City Council for consideration in September.
Golden Mussels
The contractor removed golden mussels from the fish screen and wet well at the Delta Water Intake Pump Station We are working with San Joaquin County for a field trip to sites within the Delta that have been impacted by the golden mussels.
Tentative Date September 25, 2026