RESOLUTION APPROVING THE PLANS AND SPECIFICATIONS AND AWARDING A CONSTRUCTION CONTRACT FOR THE MORMON SLOUGH SANITARY SEWER REHABILITATION, PROJECT NO. UW18030 On July 16, 2026, the City Clerk of the City of Stockton opened, examined, and publicly declared the sealed proposals or bids offered for the Mormon Slough Sanitary Sewer Rehabilitation, Project No. UW18030; and The Municipal Utilities Department has implemented a Condition Assessment Program for the City’s sewer infrastructure comprised of comprised of Closed-Circuit Televised Video (CCTV) inspection, pipe cleaning, and engineering evaluation. This program generates a prioritized list of sewer replacement and/or rehabilitation projects for inclusion in the City’s Capital Improvement Plan; and The project will replace approximately 2,428 linear feet of 24-inch diameter sewer line with a 30-inch sewer line along Mormon Slough between Sierra Nevada Street and Beighle Avenue; and K. J. Woods Construction, Inc. is the lowest responsible bidder in the amount of $2,978,000 and its bid is regular in all respects; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF STOCKTON, AS FOLLOWS:
The City Council approves the plans and specifications for the Mormon Slough Sanitary Sewer Rehabilitation, Project No. UW18030.
The City Council awards a Construction Contract between the City of Stockton and K. J. Woods Construction, Inc., in the amount of $2,978,000, and the City Manager is authorized and directed to execute same, a copy of which is attached as Exhibit 1 and incorporated by this reference. //
//
//
//
//
//
//
//
The City Manager is hereby authorized to take whatever actions are necessary and appropriate to carry out the purpose and intent of this Resolution.
PASSED, APPROVED, and ADOPTED September 29, 2026 .
CHRISTINA FUGAZI
Mayor of the City of Stockton