Sunnyvale City Council
Presentation
April 26, 2022
Draft Master Plan at Peterson Middle School,
New Laurelwood Elementary School,
District Farm and Nature Center
1 Agenda
Schedule
Core Values and Vision 2035
Activities and Progress
Conceptual Strategies
Proposed Master Plans
Next Steps
2 3
Core Values Drive Design
• Students First
• Excellence Through
Continuous Improvement
• Integrity and Ethical
Stewardship
• Connected Families and
Collaborative Community
• Equity and Social Justice
• Empathy and Respect
Vision 2035
4 Activities Completed
Site Technical Data
• Topographic survey
• Arborist report
• Traffic study (in-progress)
• CDE site analysis
Stakeholder Input
• Community
• School leadership
• School staff
• PTA & Site Council
• Students (in-progress)
• District leadership
5 Conceptual Site Strategies
• Central Open Space
• Connected Pathways
• Visual Cues
Preferred Site Concepts
• Focus on two variations
• Discussed with school PTAs, Site
Councils and staff
• Discussed in Community Meetings
Preliminary Layout for Laurelwood
• Discussed with Laurelwood
Leadership, PTA & Site Council
• Continue to refine with additional
meetings
Master Plan Process
6 Quick Reminder: Project Components
Phase 1 – Measure
BB Funded
• New Laurelwood ES
• Peterson MS Track and
Field
• Patrick Henry demolition
Future Phases –
(unfunded)
• Peterson MS modernization
• Peterson MS parking and
drop-off improvements
• Peterson MS baseball
& softball fields
• Nature Center improvements
& Environmental Center
• Farm enhancements
• Tennis courts
7 Quick Reminder: Project Components
Phase 1 – Measure
BB Funded
• New Laurelwood ES
• Peterson MS Track and Field
• Patrick Henry demolition
Future Phases –
(unfunded)
• Peterson MS modernization
• Peterson MS parking and drop-
off improvements
• Peterson MS baseball
& softball fields
• Nature Center improvements
& Environmental Center
• Farm enhancements
• Tennis courts
8 Site Conceptual Strategies
A. Laurelwood - North Side of Site
• Connect schools' parking lots
• Relocated administration for Peterson
• Additional parking & bus loop for
Nature Center
• Tennis courts on Bryant
B. Laurelwood – South Side of Site
• Separate parking lots
• New administration & drop-off loop for
Peterson
• Track shift & new Peterson field
• Farm amenities off Dunford
C. Laurelwood – East Side of Site
• Single parking loop with separate
Preschool, TK, Kindergarten drop-off
• New Peterson curb appeal
• Farm amenities near Nature Center
• Centralized tennis courts 9
10 Draft Peterson Laurelwood
Master Plan
11 12
Next Steps
• Continue to meet with District transportation consultant and the City of Santa Clara and Sunnyvale transportation engineering departments
• Refine programming for Laurelwood ES
• Complete Master Plan for adoption – May/June 2022
• Continue environmental studies (DTSC and CEQA)
• Begin design of Peterson Track and Field (without bleachers) • Begin plans for demolition of Patrick Henry
13 14
Questions?
Website:
https://www.santaclarausd.org/Page/3677
Email:

[email protected]
Draft Peterson Laurelwood Master Plan