04/20/22 Bid Summary
IFB
PW22-07 Concrete Sidewalk, Curb, Gutter, &
Driveway Approaches 2022
Project No. ST-22-02
Item Description QTY UNIT Unit Price Total Unit Price Total Unit Price Total 1 Remove and Reconstruct 4” Thick Concrete
Sidewalk 33826 SF 14.50$ 490,477.00$ 16.35$ 553,055.10$ 36.00$ 1,217,736.00$
2 Remove and Reconstruct 6” Thick Concrete
Sidewalk Driveway 3136 SF 15.00$ 47,040.00$ 25.10$ 78,713.60$ 39.50 $
123,872.00$
3 Remove and Reconstruct 6” Thick Concrete
Driveway Approach 3932 SF 15.00$ 58,980.00$ 25.10$ 98,693.20$ 40.00 $
157,280.00$
4 Remove and Reconstruct Curb and Gutter 7518 LF 75.00$ 563,850.00$ 105.00$ 789,390.00$ 82.00$ 616,476.00$
5 Remove Park Strip Concrete and Backfill with 4”
Topsoil (Revocable) 4,687 SF 2.00
$
9,374.00$ 4.20$ 19,685.40$ 3.00$ 14,061.00$
6 4” Thick Asphalt Concrete (Revocable) 2,700 SF 7.00$
18,900.00$ 16.35$ 44,145.00$ 5.00$ 13,500.00$
7 Adjust Utility Boxes in Sidewalk (Revocable) 6 EA 100.00$ 600.00$ 200.00$ 1,200.00$ 420.00$ 2,520.00$ 8 Replace Water Meter Box (Revocable) 12 EA 100.00$ 1,200.00$ 200.00$ 2,400.00$ 440.00$ 5,280.00$ 9 Tree and Stump Removal Medium Size 16” – 30” 29 EA 2,900.00$ 84,100.00$ 2,000.00$ 58,000.00$ 2,450.00$ 71,050.00$ 10 Tree and Stump Removal Large Size 31” or
Greater Diameter 22 EA 4,000.00$ 88,000.00$ 3,460.00$ 76,120.00$ 4,388.00$ 96,536.00$ 1,
362,521.00$ 1,721,402.30$ 2,318,311.00$
Surety
License
Sub Contractor Safe & Care
Tree Service Tree Removal USA Trucking All Trucking Reliable Tree Experts, Inc.
Tree and Stump
Removal
Del Secco
Diamond
Core & Saw,
Inc.
All Sawcutting
Bay Area
Tree
Specialists
Tree Removal
Stomp Grinding
10% Bid Bond
A
10% Bid Bond 10% Bid Bond
AA , C 8
Total Base Bid
Spencon Construction JJR Construction Inc. FBD Vanguard Construction, Inc. 3170 Crow Canyon Pl #250
San Ramon, CA 94583
Spencer Stahl
1120 Ninth Ave
San Mateo, CA 94402
Carlos Raposo
550 Greenville Road
Livermore, CA 94550
Billie Sposeto
Attachment 1